32C-012 (7) BP-2023-1261
110 MAIN ST COMMONWEALTH OF MASSACHUSETTS
Map:Block:Lot:
32C-012-001 CITY OF NORTHAMPTON
Permit: Alts Renovations
Repair
PERSONS CONTRACTING WITH UNREGISTERED CONTRACTORS
DO NOT HAVE ACCESS TO THE GUARANTY FUND (MGL c.142A)
BUILDING PERMIT
Permit# BP-2023-1261 PERMISSION IS HEREBY GRANTED TO:
Project# ROOF 2023 Contractor: License:
PEAK PERFORMANCE ROOFING
Est. Cost: 41200 LLC CS-103061
Const.Class: Exp.Date: 09/21/2024
Use Group: Owner: P+Q LLC
Lot Size (sq.ft.)
Zoning: CB Applicant: PEAK PERFORMANCE ROOFING LLC
Applicant Address Phone: Insurance:
1 LOVEFIELD ST 413-203-5888 R2WC342657
EASTHAMPTON, MA 01027
ISSUED ON: 09/12/2023
TO PERFORM THE FOLLOWING WORK:
STRIP AND REROOF
POST THIS CARD SO IT IS VISIBLE FROM THE STREET
Inspector of Plumbing Inspector of Wiring D.P.W. Building Inspector
Underground: Service: Meter: Footings:
Rough: Rough: House # Foundation:
Final: Final: Final: Rough Frame:
Gas: Fire Department Driveway Final: Fireplace/Chimney:
Rough: Oil: Insulation:
Smoke: Final:
THIS PERMIT MAY BE REVOKED BY THE CITY OF NORTHAMPTON UPON VIOLATION OF
ANY OF ITS RULES AND REGULATIONS.
Signature:
1, . 1. ,2 , T)15,
Fees Paid: $288.00
•
212 Main Street,Phone(413)587-1240,Fax: (413)587-1272
Office of the Building Commissioner
DocuSign Envelope ID:4127BE52-5EA2-46C0-9E07-5DA49D5CD229
Versionl.7 omm cc eldi�ng Permit May 15, 2000
Department use only
City of Northa pton /-ptatus of Permit:
Building De rtme t S�` '‘CCut/Driveway Permit
212 Main'Sy J 2w eptic Availability
Room 10t O. ? r. Wat ell Availability
Northampton, MA 0 o
' ti `v Tw Sets Structural Plans
phone 413-587-1240 Fax 413- ot/sit Plans
; Othe Specify
APPLICATION TO CONSTRUCT, REPAIR, RENOVATE, CHANGE T USE 0 OCCUPANCY OF, OR DEMOLISH ANY BUILDING
OTHER THAN A ONE OR TWO FAMILY DWELLING
SECTION 1 -SITE INFORMATION
1.1 Property Address: This section to be completed by office
Map Lot Unit
110 Main Street
Northampton Zone Overlay District
Elm St. District CB District
SECTION 2 -PROPERTY OWNERSHIP/AUTHORIZED AGENT
:?.1 Owner of Record:
110 MAIN ST., Northampton
Name(Print) PO LLC Current Mailing Address:
ATTN: Boa Kwang
646 286 1234
Signature; pAt,.R Telephone
2.2 Authorized Agent:
James J. Flannery/ Peak Performance Roofing LLC ; 1 Lovefield St., Easthampton MA 01027
Name(Print) Current Mailing Address:
413-203-5888
Signature Telephone
SECTION 3 -ESTIMATED CONSTRUCTION COSTS
Item Estimated Cost(Dollars)to be Official Use Only
completed by permit applicant
1. Building 41200 (a) Building Permit Fee
2. Electrical (b) Estimated Total Cost of
Construction from (6)
3. Plumbing Building Permit Fee
4. Mechanical (HVAC) �"6
5. Fire Protection
6. Total = (1 + 2 + 3 +4 +5) 41200 Check Number q y Of 7
This Section For Official Use Only
Building Permit Number Date
Issued
Signature:/h'"2
it/Z- 2oZ3
Building Commissioner/Inspector of Buildings Date
DocuSign Envelope ID:4127BE52-5EA2-46C0-9E07-5DA49D5CD229
Version1.7 Commercial Building Permit May 15,2000
SECTION 4-CONSTRUCTION SERVICES FOR PROJECTS LESS THAN 35,000
CUBIC FEET OF ENCLOSED SPACE
Interior Alterations ❑ Existing Wall Signs El Demolition❑ Repairs❑ Additions ❑ Accessory Building❑
Exterior Alteration ❑ Existing Ground Sign❑ New Signs ❑ Roofing E Change of Use❑ Other ❑
Brief Description Replace flat roof. Install Genflex fully adhered EPDM roof system.
Of Proposed Work:
SECTION 5-USE GROUP AND CONSTRUCTION TYPE
USE GROUP (Check as applicable) CONSTRUCTION TYPE
A Assembly ❑ A-1 D A-2 ❑ A-3 ❑ 1A I ❑
A-4 ❑ A-5 0 1 B ❑
B Business 0 2A ❑
E Educational ❑ 2B ❑
F Factory ❑ F-1 ❑ F-2 ❑ 2C ❑
H High Hazard 0 3A ❑
I Institutional ❑ I-1 0 1-2 ❑ 1-3 ❑ 3B 0
M Mercantile 0 4 ❑
R Residential 0 R-1 ❑ R-2 0 R-3 0 5A 0
S Storage ❑ S-i ❑ S-2 ❑ 5B ❑
U Utility ❑ Specify:
M Mixed Use ❑ Specify:
S Special Use ❑ Specify:
COMPLETE THIS SECTION IF EXISTING BUILDING UNDERGOING RENOVATIONS, ADDITIONS AND/OR CHANGE IN USE
Existing Use Group: Proposed Use Group:
Existing Hazard Index 780 CMR 34): Proposed Hazard Index 780 CMR 34):
SECTION 6 BUILDING HEIGHT AND AREA
BUILDING AREA EXISTING PROPOSED NEW CONSTRUCTION OFFICE USE ONLY
Floor Area per Floor(sf)
1st 1st
2nd 2nd
3rd 3rd
4th 4n
Total Area (sf) Total Proposed New Construction (sf)
Total Height(ft)
Total Height ft
7.Water Supply(M.G.L. c.40, § 54) 7.1 Flood Zone Information: 7.3 Sewage Disposal System:
Public ❑ Private ❑ Zone Outside Flood Zones Municipal ❑ On site disposal systems
DocuSign Envelope ID:4127BE52-5EA2-46C0-9E07-5DA49D5CD229
Versionl.7 Commercial Building Permit May 15,2000
SECTION 10-STRUCTURAL PEER REVIEW(780 CMR 110.11)
Independent Structural Engineering Structural Peer Review Required Yes El No
SECTION 11 -OWNER AUTHORIZATION -TO BE COMPLETED WHEN
OWNERS AGENT OR CONTRACTOR APPLIES FOR BUILDING PERMIT
PQ LLC ATTN. Boa Kwang
I, �A.� �.. ', as Owner of the subject property
James J. Flannery / Peak Performance Roofing, LLC
hereby authorize to
act on my behalf, in all matters relative to work authorized by this building permit application.
C/O : 8/28/2023
(1414.
Signature of'Owner" Date
James J. Flannery / PEAK PERFORMANCE ROOFING LLC as Owner/Authorized
Agent hereby declare that the statements and information on the foregoing application are true and accurate,to the best of my knowledge
and belief.
Signed under the pains and penalties of perjury.
James J. Flannery
Print Name
Flanreii. 08/25/2023
Signature of Owner/Agent Date
SECTION 12-CONSTRUCTION SERVICES
10.1 Licensed Construction Supervisor: Not Applicable ❑
Name of License Holder: James J. Flannery .,, CS-103061
License Number
Holyoke, MA 01040 _.. . . 09/21/2024
Address Expiration Date
�amv� annertt 413-203-5888
Signature Telephone
SECTION 13-WORKERS'COMPENSATION INSURANCE AFFIDAVIT(M.G.L.c. 152, §25C(6))
Workers Compensation Insurance affidavit must be completed and submitted with this application. Failure to provide this affidavit will result
in the denial of the issuance of the bui ing permit.
Signed Affidavit Attached Yes No 0
DocuSign Envelope ID:4127BE52-5EA2-46C0-9E07-5DA49D5CD229
The Roofing Process : What to Expect
When will my roof be scheduled? Once the contract, deposit, and building permit
are all in place, we can proceed with installing your roof. Roofing is hazardous and the safety of
our crew is a priority. We must work around the weather forecast; here in New England, this
means we can't plan our schedule very far in advance, and can't promise specific installation
dates. Long stretches of inclement weather will cause delays. We appreciate your flexibility and
patience in our dealings with Mother Nature!
Your project manager will contact you a few days before they wish to proceed. Our crews are
hardworking and efficient; most residential installations take only 1-2 days to install.
Do I need to do anything to prepare? As noted on your contract, we are not
responsible for dirt/debris that may fall into the attic. Depending on the condition of the
plywood, you may see little to no debris, or it could be more substantial. If you store items in the
attic, we recommend covering with plastic sheeting.
Do I need to notify my neighbors? If your home is extremely close to other homes
or driveways, there's a possibility we may need to be on their property temporarily to lay
protection or collect debris. In this case, yes, please notify your neighbors. Otherwise, it is a
courtesy. Your neighbors will likely appreciate notification of the noise/traffic.
Materials and Dumpster Delivery: The materials and dumpster may arrive the day
before the scheduled installation (especially if your installation is taking place on a weekend).
Depending on your home's layout and driveway(s), we may need vehicles moved at this point.
Parking: On the day of the installation, we ask that you move ALL vehicles out of ALL
driveways, and away from the house, to avoid any damage, and for our access.
How early will you start? Our crews will begin as early as 7.30am. They will work a
long day, often until dark if necessary. We aim to have the installation completed in as few days
as possible to minimize disruption to you and your neighbors.
Do I need to be home? It's up to you. Some customers like to keep an eye on what's
going on. Others would rather not be home because of the noise. Be aware that roofing is loud
(banging, nail guns, etc) so you may need to make arrangements for residents, tenants or pets.
Please do not plan on outdoor activities while we are working, for safety's sake. Please keep
pets inside, or on a leash away from the roofing activities.
DocuSign Envelope ID:4127BE52-5EA2-46C0-9E07-5DA49D5CD229
What if I have an urgent question? If you have an urgent issue outside of regular
office hours, call or text your project manager directly on his cell.
Unforeseen Issues: Once we remove the existing roofing, we can inspect the underlying
sheathing. Your contract states we will replace a small amount of plywood at no additional cost
if needed. If more serious issues are found, the project manager will contact you to explain.
There may need to be an upcharge on the final bill, consistent with the per sheet or square foot
amount quoted in your estimate.
Cleanup: No way around it, roofing is messy work. Rest assured that when the job is done,
we will pickup all debris and do magnetic sweeps. Since we may work until dark, the main crew
may need to leave before cleaning up, or if the job ends midday, they may leave to start another
job. Another staff person will come later or the next day for more cleaning.
There are materials left over. Did I get charged for those?
Your job is priced according to the measurements. We always bring extra material for the
jobsite, just to be safe. You were not charged for those and we will be collecting them. One of
our staff will pick up the extra material after the installation crew is gone, usually within 1-2 days.
When will the dumpster be removed? The dumpster is usually removed the next
business day after the main crew has finished. Weekends or holidays may delay pickup.
The dumpster company should check for any debris after removal, but please do a visual check
before walking or driving over the area where the dumpster was located. If you see any debris
there, please let us know.
The job is done but I have concerns, what should I do?
Please be aware that even after the main installation crew has left, that doesn't mean our job is
done. The project manager will be coming by as soon as possible to do a final inspection, and a
staff person will come by to do a final sweep, and pickup leftover items. Depending on our
schedule, all of the final touchups, cleaning & pickups are usually completed in about 1-3 days
after main installation is complete. If you have any other questions, please let us know.
Thank you for choosing Peak Performance Roofing!
We will do our very best to make this major home improvement a smooth experience for you!
P akL 8/28/2023
pE IK 1 Lovefield St., Easthampton MA 01027
- m 3-5888 M-F 9am-4
P E R T Ol R C 4
ROOF I N to peak P mail.com
performanceroofin II 9 @9
The Commonwealth of Massachusetts
=——i 1, Department of Industrial Accidents
_ 1 n1- 1 Congress Street,Suite 100
tr_#il_ Boston,MA 02114-2017
,,;,t www.mass.gov/dia
Workers'Compensation Insurance Affidavit:Builders/Contractors/Electricians/Plumbers.
TO BE FILED WITH THE PERMITTING AUTHORITY.
Applicant Information Please Print Leeib1v
Name (Business/Organization/Individual): PEAK PERFORMANCE ROOFING, LLC
Address: 1 LOVEFIELD STREET
City/State/Zip:EASTHAMPTON, MA 01027 Phone #:413-203-5888
Are you an employer?Check the appropriate box: Type of project(required):
1.0 I am a employer with 4 employees(full and/or part-time).* 7. ❑New construction
2❑I am a sole proprietor or partnership and have no employees working for me in 8. ❑Remodeling
any capacity.[No workers'comp.insurance required.]
9. ❑Demolition
3.❑1 am a homeowner doing all work myself.[No workers'comp.insurance required.]t
10❑Building addition
4❑I am a homeowner and will be hiring contractors to conduct all work on my property. I will
ensure that all contractors either have workers'compensation insurance or are sole 11.❑Electrical repairs or additions
proprietors with no employees. 12.❑Plumbing repairs or additions
5.0 I am a general contractor and I have hired the sub-contractors listed on the attached sheet. 13.0 Roof repairs
These sub-contractors have employees and have workers'comp.insurance.:
6.❑We are a corporation and its officers have exercised their right of exemption per MGL c. 14.❑Other
152,§1(4),and we have no employees.[No workers'comp.insurance required.]
*Any applicant that checks box#1 must also fill out the section below showing their workers'compensation policy information.
t Homeowners who submit this affidavit indicating they are doing all work and then hire outside contractors must submit a new affidavit indicating such.
:Contractors that check this box must attached an additional sheet showing the name of the sub-contractors and state whether or not those entities have
employees. If the sub-contractors have employees,they must provide their workers'comp.policy number.
I am an employer that is providing workers'compensation insurance for my employees. Below is the policy and job site
information.
Insurance Company Name:BERKSHIRE HATHAWAY GUARD
Policy#or Self-ins.Lic.#:R2WC202869 Expiration Date:04/27/2024
Job Site Address: 110 Main St. City/State/Zip:Northampton, MA
Attach a copy of the workers' compensation policy declaration page(showing the policy number and expiration date).
Failure to secure coverage as required under MGL c. 152, §25A is a criminal violation punishable by a fine up to$1,500.00
and/or one-year imprisonment,as well as civil penalties in the form of a STOP WORK ORDER and a fine of up to$250.00 a
day against the violator.A copy of this statement may be forwarded to the Office of Investigations of the DIA for insurance
coverage verification.
I do hereby certify under the pains and penalties of perjury that the information provided above is true and correct
Signature: James J Flannery Date: 8/28/2023
Phone#:413-203-5888
Official use only. Do not write in this area,to be completed by city or town official.
City or Town: Permit/License#
Issuing Authority(circle one):
1.Board of Health 2.Building Department 3.City/Town Clerk 4.Electrical Inspector 5. Plumbing Inspector
6.Other
Contact Person: Phone#:
City of Northampton 212 Main Street, Northampton, MA 01060
Solid Waste Disposal Affidavit
In accordance of the provisions of MGL c 40, S54, I acknowledge that as
a condition of the building permit all debris resulting from the construction
activity governed by this Building Permit shall be disposed of in a properly
licensed solid waste disposal facility, as defined by MGL c 111 , S 150A.
Address of the work: 1 10 Main St.
The debris will be transported by: Aaron's 24/7 Towing and Roll-On
The debris will be received by: Valley Recycling
Building permit number:
Name of Permit Applicant Peak Performance Roofing LLC/ James Flannery
8/28/2023 James Flannery
Date Signature of Permit Applicant
DocuSign Envelope ID:4127BE52-5EA2-46C0-9E07-5DA49D5CD229
Peak Performance Roofing LLC
1 Lovefield St. P E K
Easthampton, MA 01027
413-203-5888 PERFOR CE
peakperformanceroofingllc@gmail.com ROOFING
MA HIC#183698 MA CSL#103061
Contract
ADDRESS CONTRACT# 11075
PQ LLC DATE 08/24/2023
ATTN: Boa Kwang
110 Main Street
Northampton, MA 01060
PQllcma@gmail.com
646 286 1234
JOB LOCATION
110 Main St. NOHO
DESCRIPTION
Peak Performance Roofing will provide the labor and materials to perform the following:
SMALLER ROOF: $17,700
1. Remove EPDM and underlying fiberboard insulation.
2. On the lower slow portion at the base of the roof, remove all of the material down to the wood decking.
3. Replace rotted wood, up to 100 ft2 included in the base bid. Additional wood replacement will cost $3
per square foot.
4. Mechanically fasten 1/2" high density polyisocyanurate insulation
with screws and plates.
5. Install GenFlex fully adhered EPDM roof system.
6. Roof material wall extend up the wall the same height as is the existing roof and termination bar will be
fastened to prevent material from slipping off the wall.
7.All necessary flashings will be completed.
8. Fabricate and install 032 gauge aluminum drip edge after front and lower edges.
LARGER ROOF: $23,500
Same as above minus number two.
DocuSign Envelope ID:4127BE52-5EA2-46C0-9E07-5DA49D5CD229
DESCRIPTION
Remove all debris from premises, and throughout the job, continue cleanup and keep the premises
undamaged. WE ARE NOT RESPONSIBLE FOR DEBRIS THAT MAY FALL INTO
ATTIC/INTERIOR.
Please use reasonable caution during the installation process: do not walk or drive under active work or on
areas of potential roofing debris. Installations are weather permitting; inclement weather will cause
scheduling delays.
Peak Performance Roofing LLC will obtain the building permit.
Warranty confirmation shall be provided upon final payment. Installation and manufacturer warranties
are not in effect until Paid In Full.
TOTAL: $41,200
DEPOSIT DUE ASAP $15,000
BALANCE DUE ON OR BEFORE JANUARY 15, 2024.
TOTAL $41,200.00
r—DocuSigned by:
per,, Q 8/28/2023
Accepted By `—sse7so9Fossc43F... Accepted Date
CONSTRUCTION CONTROL WAIVER
From:
James Flannery dba Peak Performance Roofing LLC •
1 Lovefield St.
Easthampton, MA 01027
413-203-5888
To:
Jonathan Flagg
Building Commissioner
City of Northampton
212 Main Street
Northampton, MA 01060
The Massachusetts Building Code, section 107.1 allows for an exclusion from requirements for
construction control in certain situations. In accordance with code section 104.10, I request that you
grant a modification to waive the requirement for construction control of the project at
110 Main St., Northampton, MA
because the work is of a minor nature,will not affect structural elements, health, accessibility, life or fire
safety, and will be done in accordance with the prescriptive requirements of the code.
Thank you for your consideration.
Respectfully,
'a4 ec ?a49