WPA Form 5 - Order of Conditions N/A
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
A. General Information
Important: Northampton
When filling 1. From: Conservation Commission
out forms on
the computer, 2. This issuance is for(check one): a. ® Order of Conditions b. ❑ Amended Order of Conditions
use only the
tab key to 3. To: Applicant:
move your
cursor-do not David Graves
use the return a.First Name b.Last Name
key. Kollmorgen Electro Optical
c.Organization
347 King Street
d.Mailing Address
Northampton MA 01060
e.City/Town f.State g.Zip Code
4. Property Owner(if different from applicant):
a. First Name b.Last Name
Hospital Hill Development LLC
c.Organization
160 Federal Street
d.Mailing Address
Boston MA 02110
e.City/Town f.State g.Zip Code
5. Project Location:
Village at Hospital Hill Northampton -
a. Street Address b.City/Town
38A 99, 102
c.Assessors Map/Plat Number d.Parcel/Lot Number
Latitude and Longitude, if known: 43.30964 72.64703
e.Latitude f.Longitude
6. Property recorded at the Registry of Deeds for(attach additional information if more than one parcel):
Hampshire
a.County b.Certificate Number(if registered land)
6925 302
c.Book d. Page
7. Dates: June 5, 2009 July 23, 2009 _ August 2, 2009
a.Date Notice of Intent Filed b.Date Public Hearing Closed c.Date of Issuance
8. Final Approved Plans and Other Documents (attach additional plan or document references as
needed):
Kollmorgen Electro-Optical Village Hill Northampton, Massachusetts Application for Site Plan Approval
a.Plan Title
Tighe and Bond Francis Hoey and Joseph Vaiamari, Jr.
b.Prepared By c.Signed and Stamped by
06/05/2009 _ 1"=40'
d. Final Revision Date e.Scale
f.Additional Plan or Document Title g.Date
wpaform5.doc• rev.2/27/08 Page 1 of 10
Bk: 09989 Pg: 308
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands MassDEP File Number:
WPA Form 5 - Order of Conditions N/A
Ir
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Findings
t. Findings pursuant to the Massachusetts Wetlands Protection Act:
Following the review of the above-referenced Notice of Intent and based on the information provided
in this application and presented at the public hearing, this Commission finds that the areas in which
work is proposed is significant to the following interests of the Wetlands Protection Act. Check all that
apply:
a. ® Public Water Supply b. ❑ Land Containing Shellfish c. ® Prevention of Pollution
d. ® Private Water Supply e. ❑ Fisheries f. ® Protection of Wildlife
Habitat
g. ® Groundwater Supply h. ® Storm Damage Prevention i. ® Flood Control
2. This Commission hereby finds the project,as proposed,is:(check one of the following boxes)
Approved subject to:
a. ® the following conditions which are necessary in accordance with the performance standards set
forth in the wetlands regulations. This Commission orders that all work shall be performed in
accordance with the Notice of Intent referenced above, the following General Conditions, and any
other special conditions attached to this Order.To the extent that the following conditions modify or
differ from the plans, specifications, or other proposals submitted with the Notice of Intent, these
conditions shall control.
Denied because:
b. ❑ the proposed work cannot be conditioned to meet the performance standards set forth in the
wetland regulations. Therefore,work on this project may not go forward unless and until a new Notice
of Intent is submitted which provides measures which are adequate to protect these interests, and a
final Order of Conditions is issued. A description of the performance standards which the
proposed work cannot meet is attached to this Order.
c. ❑ the information submitted by the applicant is not sufficient to describe the site, the work, or the
effect of the work on the interests identified in the Wetlands Protection Act. Therefore, work on this
project may not go forward unless and until a revised Notice of Intent is submitted which provides
sufficient information and includes measures which are adequate to protect the Act's interests, and a
final Order of Conditions is issued. A description of the specific information which is lacking and
why it is necessary is attached to this Order as per 310 CMR 10.05(6)(c).
Inland Resource Area Impacts: Check all that apply below. (For Approvals Only)
3. ® Buffer Zone Impacts: Shortest distance between limit of project disturbance and 30
wetland boundary(if available) a.linear feet
Resource Area Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
4. ❑ Bank a.linear feet b.linear feet c.linear feet d.linear feet
5. ❑ Bordering Vegetated _
Wetland a.square feet b.square feet c.square feet d.square feet
6. ❑ Land Under Waterbodies a.square feet b.square feet c.square feet d.square feet
and Waterways
e.cly dredged f.Gy dredged
wpaform5.doc• rev.2/27/08 Page 2 of 10
Bk: 09989 Pg: 309
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands MassDEP File Number:
WPA Form 5 - Order of Conditions N/A
1 Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Findings (cont.)
Resource Area Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
7. ❑ Bordering Land
Subject to Flooding a.square feet b.square feet c.square feet d.square feet
Cubic Feet Flood Storage e.cubic feet f.cubic feet g.cubic feet h.cubic feet
8. ❑ Isolated Land Subject
to Flooding a.square feet b.square feet
Cubic Feet Flood Storage c.cubic feet d.cubic feet e.cubic feet f.cubic feet
}
e 9. ❑ Riverfront area a.total sq.feet b.total sq.feet
Sq ft within 100 ft c.square feet d.square feet e.square feet f.square feet
Sq ft between 100-200 ft square feet h.square feet i.square feet g. q q q j.square feet
Coastal Resource Area Impacts: Check all that apply below. (For Approvals Only)
10. ❑ Designated Port Areas Indicate size under Land Under the Ocean, below
11. ❑ Land Under the Ocean —
a.square feet b.square feet
c.Gy dredged d.Gy dredged
12. ❑ Barrier Beaches Indicate size under Coastal Beaches and/or Coastal Dunes below
13. ❑ Coastal Beaches a.square feet b.q square feet c.Gy nourishmt. d.Gy nourishmt.
14. ❑ Coastal Dunes a.square feet b.square feet c.Gy nourishmt. d.dy nourishmt.
15. ❑ Coastal Banks
a.linear feet b.linear feet
16. ❑ Rocky Intertidal Shores a.square feet b.square feet
17. ❑ Salt Marshes a.square feet b.square feet c.square feet d.square feet
18. ❑ Land Under Salt Ponds a.square feet b.square feet
c.Gy dredged d.dy dredged
19. ❑ Land Containing
Shellfish a.square feet b.square feet c.square feet d.square feet
20. ❑ Fish Runs Indicate size under Coastal Banks, inland Bank, Land Under the
Ocean, and/or inland Land Under Waterbodies and Waterways,
above
a.Gy dredged b.c/y dredged
21. ❑ Land Subject to Coastal
Storm Flowage a.square feet b.square feet
wpaforrn5.doc• rev.2/27/08 Page 3 of 10
J
Bk: 09989 Pg: 310
L71Ma
ssachusetts Department of Environmental Protection
Bureau of Resource Protection -Wetlands MassDEP File Number:
WPA Form 5 - Order of Conditions N/A
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
C. General Conditions Under Massachusetts Wetlands Protection Act
• (only applicable to approved projects)
1. Failure to comply with all conditions stated herein, and with all related statutes and other regulatory
measures, shall be deemed cause to revoke or modify this Order.
2. The Order does not grant any property rights or any exclusive privileges; it does not authorize any
injury to private property or invasion of private rights.
3. This Order does not relieve the permittee or any other person of the necessity of complying with all
other applicable federal, state, or local statutes, ordinances, bylaws, or regulations.
4. The work authorized hereunder shall be completed within three years from the date of this Order
unless either of the following apply:
a. the work is a maintenance dredging project as provided for in the Act; or
b. the time for completion has been extended to a specified date more than three years, but less
• than five years, from the date of issuance. If this Order is intended to be valid for more than three
years, the extension date and the special circumstances warranting the extended time period are
set forth as a special condition in this Order.
5. This Order may be extended by the issuing authority for one or more periods of up to three years each
upon application to the issuing authority at least 30 days prior to the expiration date of the Order.
6. Any fill used in connection with this project shall be clean fill.Any fill shall contain no trash, refuse,
rubbish, or debris, including but not limited to lumber, bricks, plaster, wire, lath, paper, cardboard,
pipe, tires, ashes, refrigerators, motor vehicles, or parts of any of the foregoing.
7. This Order is not final until all administrative appeal periods from this Order have elapsed, or if such
an appeal has been taken, until all proceedings before the Department have been completed.
8. No work shall be undertaken until the Order has become final and then has been recorded in the
Registry of Deeds or the Land Court for the district in which the land is located, within the chain of title
of the affected property. In the case of recorded land, the Final Order shall also be noted in the
Registry's Grantor Index under the name of the owner of the land upon which the proposed work is to
be done. In the case of the registered land, the Final Order shall also be noted on the Land Court
Certificate of Title of the owner of the land upon which the proposed work is done. The recording
information shall be submitted to this Conservation Commission on the form at the end of this Order,
which form must be stamped by the Registry of Deeds, prior to the commencement of work.
9. A sign shall be displayed at the site not less then two square feet or more than three square feet in
size bearing the words,
"Massachusetts Department of Environmental Protection"[or, "MassDEP"]
"File Number N/A
wpaform5.doc• rev.227/08 Page 4 of 10
Bk: 09989 Pg: 311
iLMassachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands MassDEP File Number:
WPA Form 5 — Order of Conditions N/A
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
t
C. General Conditions Under Massachusetts Wetlands Protection Act
10. Where the Department of Environmental Protection is requested to issue a Superseding Order, the
Conservation Commission shall be a party to all agency proceedings and hearings before MassDEP.
11. Upon completion of the work described herein, the applicant shall submit a Request for Certificate of
Compliance (WPA Form 8A)to the Conservation Commission.
12. The work shall conform to the plans and special conditions referenced in this order.
13. Any change to the plans identified in Condition #12 above shall require the applicant to inquire of the
Conservation Commission in writing whether the change is significant enough to require the filing of a
new Notice of Intent.
14. The Agent or members of the Conservation Commission and the Department of Environmental
Protection shall have the right to enter and inspect the area subject to this Order at reasonable hours
to evaluate compliance with the conditions stated in this Order, and may require the submittal of any
data deemed necessary by the Conservation Commission or Department for that evaluation.
15. This Order of Conditions shall apply to any successor in interest or successor in control of the property
subject to this Order and to any contractor or other person performing work conditioned by this Order.
16. Prior to the start of work, and if the project involves work adjacent to a Bordering Vegetated Wetland,
the boundary of the wetland in the vicinity of the proposed work area shall be marked by wooden
stakes or flagging. Once in place, the wetland boundary markers shall be maintained until a Certificate
of Compliance has been issued by the Conservation Commission.
17. All sedimentation barriers shall be maintained in good repair until all disturbed areas have been fully
stabilized with vegetation or other means. At no time shall sediments be deposited in a wetland or
water body. During construction, the applicant or his/her designee shall inspect the erosion controls on
a daily basis and shall remove accumulated sediments as needed. The applicant shall immediately
control any erosion problems that occur at the site and shall also immediately notify the Conservation
Commission,which reserves the right to require additional erosion and/or damage prevention controls
it may deem necessary. Sedimentation barriers shall serve as the limit of work unless another limit of
work line has been approved by this Order.
18. The work associated with this Order is(1)Q is not(2)® subject to the Massachusetts
Stormwater Policy Standards. If the work is subject to the Stormwater Policy, the following
conditions apply to this work and are incorporated into this Order:
a) No work, including site preparation, land disturbance, construction and redevelopment, shall
commence unless and until the construction period pollution prevention and erosion and
sedimentation control plan required by Stormwater Standard 8 is approved in writing by the issuing
authority. Until the site is fully stabilized, construction period erosion, sedimentation and pollution
control measures and best management practices (BMPs)shall be implemented in accordance with
the construction period pollution prevention and erosion and sedimentation control plan, and if
applicable, the Stormwater Pollution Plan required by the National Discharge Elimination System
Construction General Permit.
wpaform5.doc• rev.2/27/05 Page 5 of 10
Bk: 09989 Pg: 312
Massachusetts Department of Environmental Protection
Bureau of Resource Protection -Wetlands MassDEP File Number:
WPA Form 5 - Order of Conditions N/A__
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
C. General Conditions Under Massachusetts Wetlands Protection Act (cont.)
b) No stormwater runoff may be discharged to the post-construction stormwater BMPs until written
approval is received from the issuing authority. To request written approval, the following must be
submitted: illicit discharge compliance statement required by Stormwater Standard 10 and as-built
plans signed and stamped by a registered professional engineer certifying the site is fully stabilized; all
construction period stormwater BMPs and any illicit discharges to the stormwater management system
• have been removed; and all post-construction stormwater BMPs were installed in accordance with the
plans (including all planting plans)approved by the issuing authority, and have been inspected to
ensure they are not damaged and will function properly.
c) Prior to requesting a Certificate of Compliance,the responsible party(defined in General
Condition 18(e))shall submit to the issuing authority an Operation and Maintenance (0& M)
Compliance Statement for the Stormwater BMPs. This Statement shall identify the responsible party
for implementing the Operation and Maintenance Plan and also state that: 1. "Future responsible
parties shall be notified in writing of their continuing legal responsibility to operate and maintain the
stormwater management BMPs and implement the Pollution Prevention Plan; and 2. The Operation
and Maintenance Plan for the stormwater BMPs is complete and will be implemented upon receipt of
the Certificate."
d) Post-construction pollution prevention and source control shall be implemented in accordance with
the long-term pollution prevention plan section of the approved Stormwater Report and, if applicable,
the Stormwater Pollution Prevention Plan required by the National Discharge Elimination System
Multi-Sector General Permit.
e) Unless and until another party accepts responsibility, the issuing authority shall presume that the
responsible party for maintaining each BMP is the landowner of the property on which the BMP is
located. To overcome this presumption,the landowner of the property must submit to the issuing
authority a legally binding agreement acceptable to the issuing authority evidencing that another entity
has accepted responsibility for maintaining the BMP, and that the proposed responsible party shall be
treated as a permittee for purposes of implementing the requirements of Conditions 18(f)through
18(k)with respect to that BMP. Any failure of the proposed responsible party to implement the
requirements of Conditions 18(f)through 18(k)with respect to that BMP shall be a violation of the
Order of Conditions or Certificate of Compliance. In the case of stormwater BMPs that are serving
more than one lot, the legally binding agreement shall also identify the lots that will be serviced by the
stormwater BMPs. A plan and easement deed that grants the responsible party access to perform the
required operation and maintenance must be submitted along with the legally binding agreement.
f) The responsible party shall operate and maintain all stormwater BMPs in accordance with the
design plans, the Operation and Maintenance Plan section of the approved Stormwater Report, and
the Massachusetts Stormwater Handbook.
g) The responsible party shall:
1. Maintain an operation and maintenance log for the last three years including inspections,
repairs, replacement and disposal (for disposal the log shall indicate the type of material and
the disposal location);
2. Make this log available to MassDEP and the Conservation Commission upon request; and
3. Allow members and agents of the MassDEP and the Conservation Commission to enter and
inspect the premises to evaluate and ensure that the responsible party complies with the
Operation and Maintenance requirements for each BMP set forth in the Operations and
Maintenance Plan approved by the issuing authority.
h) All sediments or other contaminants removed from stormwater BMPs shall be disposed of in
accordance with all applicable federal, state, and local laws and regulations.
i) Illicit discharges to the stormwater management system as defined in 310 CMR 10.04 are
prohibited.
wpaform5.doc• rev.2J27/08 Page 6 of 10
Bk: 09989 Pg: 313
Massachusetts Department of Environmental Protection
Bureau of Resource Protection -Wetlands MassDEP File Number:
WPA Form 5 — Order of Conditions N/A
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
C. General Conditions Under Massachusetts Wetlands Protection Act (cont.)
j) The stormwater management system approved in the Final Order of Conditions shall not be
changed without the prior written approval of the issuing authority. Areas designated as qualifying
pervious areas for purpose of the Low Impact Site Design Credit shall not be altered without the prior
written approval of the issuing authority.
k) Access for maintenance of stormwater BMPs shall not be obstructed or blocked. Any fencing
constructed around stormwater BMPs shall include access gates. Fence(s)shall be at least six inches
above grade to allow for wildlife passage.
Special Conditions (if you need more space for additional conditions, please attach a text document):
See "Attachment A"
D. Findings Under Municipal Wetlands Bylaw or Ordinance.
1. Is a municipal wetlands bylaw or ordinance applicable? ® Yes ❑ No
2. The Northampton hereby finds (check one that applies):
Conservation Commission
a. ❑ that the proposed work cannot be conditioned to meet the standards set forth in a municipal
ordinance or bylaw specifically:
1.Municipal Ordinance or Bylaw 2.Citation
Therefore, work on this project may not go forward unless and until a revised Notice of Intent is
submitted which provides measures which are adequate to meet these standards, and a final
Order of Conditions is issued.
b. ® that the following additional conditions are necessary to comply with a municipal ordinance or
bylaw:
Northampton Wetlands Ordinance Chapter 337 of the
1.Municipal Ordinance or Bylaw Code of Ordinances
3. The Commission orders that all work shall be performed in accordance with the following conditions
and with the Notice of Intent referenced above. To the extent that the following conditions modify or
differ from the plans, specifications, or other proposals submitted with the Notice of Intent, the
conditions shall control.
The special conditions relating to municipal ordinance or bylaw are as follows (if you need more space
for additional conditions, attach a text document):
See"Attachment A"
wpaform5.doc• rev.2/27/08 Page 7 of 10
Bk: 09989 Pg: 314
Massachusetts Department of Environmental Protection 14
Bureau of Resource Protection - Wetlands Mass EP File Number
L
WPA Form 5 - Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
City/Town
E. Signatures and Notary Acknowledgement
This Order is valid for three years, unless otherwise specified as a special 2P6 t
condition pursuant to General Conditions#4, from the date of issuance. 1.Date of issuance
Please indicate the number of members who will sign this form.
This Order must be signed by a majority of the Conservation Commission. 2.Number of Signers
The Order must be mailed by certified mail (return receipt requested)or hand delivered to the applicant. A
copy also must be mailed or hand delivered at the same time to the appropriate Department of
Environmental Protection Regional Office, if not filing electronically, and the property owner, if different
from applicant.
Signat
•
Notary Acknowledgement
01E-
Commonwealth of Massachusetts County of 45*(02
CSRD Z�
On this Day of Month Year
Before me, the undersigned Notary Public, lllts__
personally appeared Name of Document Signer
proved to me through satisfactory evidence of identification, which was/were
0364irCD6E
Description of evidence of identification
to be the person whose name is signed on the preceding or attached document, and acknowledged to
me that he/she signed it voluntarily foes stated purpose.
As member of Ci /Tdo P'f'" Conservation Commission
own
Signsl(p�A�'�'^ .11iic4
Printed Name of Notary Public
Place notary seal and/or any stamp above. AFL ' ` Zcx�( 3
My Co fission Expi es(Date)
This Order is issued to the applicant as follows:
❑ by hand delivery on III by certified mail,return receipt requested,on
Date Date
wpaform5.doc• rev.11/0B Page 9 of 11
Bk: 09989 Pg: 315
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands MassDEP File Number:
•
WPA Form 5 - Order of Conditions N/A
1 Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
F. Appeals
The applicant, the owner, any person aggrieved by this Order, any owner of land abutting the land subject
to this Order, or any ten residents of the city or town in which such land is located, are hereby notified of
their right to request the appropriate MassDEP Regional Office to issue a Superseding Order of
Conditions. The request must be made by certified mail or hand delivery to the Department, with the
appropriate filing fee and a completed Request of Departmental Action Fee Transmittal Form, as provided
in 310 CMR 10.03(7)within ten business days from the date of issuance of this Order. A copy of the
request shall at the same time be sent by certified mail or hand delivery to the Conservation Commission
and to the applicant, if he/she is not the appellant.Any appellants seeking to appeal the Department's
Superseding Order associated with this appeal will be required to demonstrate prior participation in the review of
this project. Previous participation in the permit proceeding means the submission of written information to
the Conservation Commission prior to the close of the public hearing, requesting a Superseding Order or
Determination, or providing written information to the Department prior to issuance of a Superseding Order
or Determination.
•
The request shall state clearly and concisely the objections to the Order which is being appealed and how
the Order does not contribute to the protection of the interests identified in the Massachusetts Wetlands
Protection Act(M.G.L. c. 131, §40), and is inconsistent with the wetlands regulations (310 CMR 10.00).
To the extent that the Order is based on a municipal ordinance or bylaw, and not on the Massachusetts
Wetlands Protection Act or regulations, the Department has no appellate jurisdiction.
Section G, Recording Information is available on the following page.
•
wpaforrn5.doc• rev.2/27/08 Page 9 of 10
Bk: 09989 Pg: 316
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
MassDEP File Number:
WPA Form 5 — Order of Conditions N/A
1 Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
G. Recording Information
This Order of Conditions must be recorded in the Registry of Deeds or the Land Court for the district in
which the land is located, within the chain of title of the affected property. In the case of recorded land,the
Final Order shall also be noted in the Registry's Grantor Index under the name of the owner of the land
subject to the Order. In the case of registered land, this Order shall also be noted on the Land Court
Certificate of Title of the owner of the land subject to the Order of Conditions. The recording information on
this page shall be submitted to the Conservation Commission listed below.
Conservation Commission
Detach on dotted line, have stamped by the Registry of Deeds and submit to the Conservation Commission.
To: •
Conservation Commission
Please be advised that the Order of Conditions for the Project at:
Project Location MassDEP File Number
Has been recorded at the Registry of Deeds of:
County Book Page
for:
Property Owner
and has been noted in the chain of title of the affected property in:
Book Page.
In accordance with the Order of Conditions issued on:
Date
If recorded land, the instrument number identifying this transaction is:
Instrument Number
If registered land, the document number identifying this transaction is:
Document Number
Signature of Applicant
wpaform5.doc• rev.2/27/08 Page 10 of 10
Bk: 09989 Pg: 317
"ATTACHMENT A"
19. Prior to the initiation of any work, the applicant/owner shall submit a letter of
understanding to the Commission stating that he/she has received,read, understands and
shall comply with these Orders. The applicant, and, his or her contractor, foreman and/or
• construction manager shall sign the letter of understanding.
20. Prior to the initiation of any work,the applicant shall submit to the Commission a
sequencing plan for construction, and erosion and sedimentation control installation.
• 21. Prior to the start of any site work,excavation or cons ction, a pre-construction
conference shall be held on the site,between the contctor conducting the work,the
site/project engineer, the applicant,and a member or agent of the Conservation
Commission, in order to ensure that the requirements of this Order are understood by all
parties. Prior to the pre-construction meeting, all erosion control devices must be
installed.
22. All required permits must be obtained from the applicable federal, state and municipal
agencies and departments prior to the start of any prof t.
23. A copy of this Order and associated plans shall rem ' on site during all construction
and/or building activities. The project manager and all equipment operators shall be
familiar with the approved plans, and shall be informe of their location on the site.
This location shall be accessible to all contractors henever work is occurring on
site.
•
24. All revised plans,referenced within this Order of Con itions, shall be approved by the
Conservation Commission and incorporated into the p rmit by reference and shall be
followed during the course of construction.
25. The areas of construction shall remain in a stable condition at the close of each
construction day. Erosion control measures shall be i pected at this time, and
maintained or reinforced as necessary. All such devic s shall be inspected, cleaned or
replaced during construction and shall remain in place until such time as stabilization of
all areas that may impact resource areas is permanent. These devices shall also be
inspected to assure that the maximum control has bee provided. Any entrapped silt shall
be removed to an area outside the buffer zone and res ce areas, and maintained or
reinforced as necessary. Erosion controls shall be ins ected after every rainfall to assure
that maximum control has been provided.
26. An adequate stockpile of erosion control materials shall be on site at all times for
emergency or routine replacement and shall include materials to repair or replace silt
fences, straw bales, erosion control blankets,riprap, filter berms or other devices planned
for use during construction.
Bk: 09989 Pg: 318
27. Soils exposed for periods greater than two months shall be stabilized with erosion control
blankets and netting, a covering of straw mulch, or a temporary cover of rye or other
grass to prevent erosion and sedimentation. Drainage ditches shall be stabilized and
seeded with a native perennial grass mixture. Any stabilization materials such as jute
netting shall be firmly anchored to prevent them from being washed from slopes by rain
or flooding. Preference should be given to biodegradable materials.
28. All disturbed areas shall be graded, loamed and seeded, or stabilized with erosion control
blankets or netting, and a covering of straw mulch prior to November 30, of each year.
No disturbed areas or stockpiled materials will be left unprotected or without erosion
control after this date.
29. No disposal of soils or other materials shall be allowed within: a 100-year floodplain; 40
feet of the 100-year floodplain elevation; any wetland; or any area within 100-feet of a
wetland, unless such areas are specifically approved by the Commission, in accordance
with 310 CMR 10.00, and City of Northampton Ordinances.
30. Ongoing conditions that shall not expire with the issuance of a Certificate of Compliance
are as follows: N/A
31. Upon completion of the work covered by this Order, the applicant shall submit an as-built
plan, signed and stamped by a registered professional engineer or land surveyor, together
with a written request for a Certificate of Compliance.
The plan and written request shall specify any ways that the completed project differs
from the plans referenced in the Order. The as-built plan shall include, at a minimum, and
as applicable to the project: elevations of all pipe inverts and outlets, pipe sizes,
materials, and slopes; all other drainage structures; limits of clearing, grading, and fill; all
structures, pavement, and contours within 100 feet of wetland boundaries; all alterations
within the wetland resource areas; and all dates of fieldwork.
32. The owner of the property described in this Order must advise any potential buyer of the
property that any construction or alteration to said property, including brush cutting or
clearance, may require approval by the Northampton Conservation Commission.
Any instrument conveying any or all of the owners' interest in said property or any
portion thereof, shall contain language similar to the following:
"This property is subject to the Northampton Wetlands Ordinance and/or
the Massachusetts Wetlands Protection Act. Any construction or major
maintenance work performed on this property requires an Order of
Conditions, and/or a Determination of Applicability from the Northampton
Conservation Commission.
Bk: 09989 Pg: 319
33. Applicant shall monitor and remove all invasive species within the disturbed area of the
100 foot buffer zone to the isolated wetlands. Invasive monitoring and removal shall
commence upon completion of work and continue for a period of two years.
•
ATTEST: HAMPSHIRE,A'Ltua vat,o •° { ,REGISTER
MARIANN'E L. DONOHUE
tSK: uyyo rg: Sub
HAMPSHIRE I 101 it
1111191
N
REGISTRY OF DEEDS 1
Bk: 9989Pg:306 Page: 1 of 14
Recorded: 10/13/2009 11:57 AM
DOCUMENT
COVER SHEET
For use with documents that do not meet For Registry Use Only
document formatting standards. Information
from original document takes precedence
when indexing data into Registry system.
THIS IS THE FIRST PAGE OF THIS DOCUMENT-DO NOT REMOVE
PROPERTY ADDRESS: T1cL 4kt
DOCUMENT TYPE: OVI z.. o` Cat m lJW S
NAME REFERENCE: I(D GeldIES
Hampshire County -20/20 Perfect Vision i2 Document Detail Report
Current datetime: 1/24/2012 6:49:14 PM
Doc# Document Type Town Book/Page File Date Consideration
25196 ORDER 09989/306 10/13/2009
Property-Street Address and/or Description
VILLAGE AT HOSPITAL HILL
Grantors
GRAVES DAVID, KOLLMORGEN ELECTRO OPTICAL, HOSPITAL HILL DEVELOPMENT LLC, NORTHAMPTON CITY CONSERVATION
Grantees
ORDER OF CONDITIONS
References-Book/Pg Description Recorded Year
06925/302 DEED 2002
Registered Land Certificate(s)-Cert# Book/Pg