CCD5 Narrative of ChangesWALMART STORES, INC. STORE NO. 2901 10/14/15
PROJECT: NORTHAMPTON, MA CONSTRUCTION CHANGE DIRECTIVE #5
PROJECT NO. 1452013
Page 1 of 2
NOTE: The General Contractor shall obtain approval of the Walmart Construction Manager before beginning the
Work defined in this Construction Change Directive.
SCOPE: The scope of this Construction Change Directive is to revise the originally issued contract documents
of Northampton, MA dated 04/21/15, and all subsequent contract modifications, to reflect the following:
SUMMARY OF CHANGES:
(OD) Owner Directed Change
1) Reface and minor structural repairs to adjacent tenant per DM approval on 10/7/15.
GENERAL
SHEET C1 – COVER SHEET
STRUCTURAL
1. Add Sheet S4 – FOUNDATION PLAN AND DETAILS to set. (OD1)
ARCHITECTURAL
SHEET D1 – DEMOLITION PLAN
DETAIL 1 – DEMOLITION PLAN
1. Add storefront graphic and doors to the Adjacent Tenant front wall. (OD1)
2. Add interior CMU inside Adjacent Tenant and related dimensions and notes. (OD1)
DETAIL 2 – ADJACENT TENANT DEMOLITION ELEVATION
1. Add detail to sheet. (OD1)
SHEET A1.2 – INTERIOR FINISH PLAN AND DETAILS
DETAIL 7 – ADJACENT TENANT WALL SECTION
1. Add detail to sheet. (OD1)
DETAIL 8 – PARAPET DETAIL
1. Add detail to sheet. (OD1)
DETAIL 9 – ENLARGED DETAIL
1. Add detail to sheet. (OD1)
DETAIL 10 – SPLICING DETAIL
1. Add detail to sheet. (OD1)
SHEET A2 – EXTERIOR ELEVATIONS
DETAIL 7 – ADJACENT TENANT ELEVATION
1. Add detail to sheet. (OD1)
STRUCTURAL
SHEET S4 – FOUNDATION PLAN AND DETAILS
1. Add entire sheet. (OD1)
SPECIFICATIONS
SECTION 00007 - SEALS PAGE
1. Resign and seal per change. (OD1)
WALMART STORES, INC. STORE NO. 2901 10/14/15
PROJECT: NORTHAMPTON, MA CONSTRUCTION CHANGE DIRECTIVE #5
PROJECT NO. 1452013
Page 2 of 2
SECTION 06100 – ROUGH CARPENTRY
1. Revise section at 1.1; A; adding “Framing with Dimensional Lumber” to summary. (OD1)
END OF NARRATIVE