SECTION 01640 - OWNER FURNISHED PRODUCTS
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes:
1. Wal-Mart Furnished Products.
B. Related Sections:
1. Section 01600 - Product Requirements: General product requirements related to all products.
1.2 DEFINITIONS
A. Owner: Defined in Construction Agreement. Owner may also be referred to as Wal-Mart.
1.3 RESPONSIBILITIES FOR WAL-MART FURNISHED PRODUCTS
A. Product Delivery: Unless specified otherwise, product supplier will deliver products to jobsite for Contractor to
receive on delivery date established by Contractor. Supplier will contact Contractor after Award of Contract to
establish a product delivery and installation date, quantities of materials, and a coordination procedure. In the event
Supplier contact cannot be made, contactRPS Construction and Equipment at (479) 204-0683, Option 3, or e-mail:
construction.buyouts@walmart.com.
B. Wal-Mart Responsibilities:
1. Responsibilities by Wal-Mart shall correspond to the party furnishing the product as specified hereinafter.
2. Arrange for delivery of supplier furnished shop drawings, product data, samples, and installation instructions to
Contractor.
3. Arrange and pay for product delivery to site, in accordance with agreed upon construction management plan in
Section 01320.
C. Contractor Responsibilities:
1. Review supplier furnished shop drawings, product data, and samples under provisions of Section 01330. Submit
to supplier with notification to Architect and Wal-Mart's Construction Department of any discrepancies or
problems anticipated in the use the products.
2. Receive and unload products at the Site when specified.
3. Verify quantity of products furnished with shop drawings, Final Field Use Drawings, or Bills of Lading as
applicable.
4. Promptly inspect products upon receipt for shortages, damaged, or defective items; report to Wal-Mart's
Construction Department. Upon notification, Wal-Mart will arrange for delivery of replacement products.
5. Handle products at site, including uncrating, storage, and protection unless otherwise specified.
6. Install products when specified.
7. Provide for installation and hook-up at time of delivery of Wal-Mart installed equipment.
8. Protect installed products from damage.
9. Replace items damaged by Contractor.
10. Remove trash, debris, and rubbish.
11. Manufacturing Defects: Report suspected product manufacturing defects to Wal-Mart Construction Manager
and Product Supplier. Upon notification, Wal-Mart will arrange for repair of product manufacturing defects.
1.4 CONTRACTOR INSTALLATION OF WAL-MART FURNISHED PRODUCTS
A. Install in accordance with manufacturer's instructions.
B. Unpack and set in place, plumb, level, and secure.
C. Connect to mechanical, plumbing, and electrical systems as required.
Not For Construction01640-2
2901 - Northampton, Massachusetts - 1452013 April 21, 2015
D. Remove packaging and clean products.
E. Test and adjust as required.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
3.1 PRODUCTS FURNISHED BY OTHERS
A. Equipment may be furnished by Wal-Mart for installation by either the Contractor or by others as specified in the
Products Furnished by Others Schedule included hereinafter.
B. The Products Furnished by Others Schedule includes a listing of Owner furnished products as required in the listed
specifications sections or drawings. Refer to the applicable drawings or individual sections for specific details
regarding Owner furnished products therein. The Schedule provides summary information only and does not
preclude or supersede requirements contained in the individual sections. Contact Wal-Mart Contracts
Administration for resolution of discrepancy between Schedule and Drawings or individual Sections.
C. Coordinate installation of Wal-Mart installed products and equipment. Work in harmony with all subcontractors,
suppliers and manufacturers. Unless otherwise specified, Contractor shall coordinate delivery date of Wal-Mart
furnished equipment. If significant order lead times are required for a specific product, lead time shall be as
specified for that product.
PRODUCTS FURNISHED BY OTHERS SCHEDULE
Specification
Section
Description Furnished
By
Received
By
Installed
By
Order
Date*
Delivery Date*
Drawings Interior Stainless Steel Pipe
Bollards
Wal-Mart Contractor Contractor Contractor to
schedule
Architectural
Drawings
Prefabricated Cash Wraps Wal-Mart Wal-Mart Contractor Wal-Mart to
Schedule
Architectural
Drawings
Fitting Rooms Wal-Mart Wal-Mart Contractor Wal-Mart to
Schedule
06610 Glass Fiber Reinforced Plastic
Panels
Wal-Mart Contractor Contractor Contractor to
Schedule
07721
Structural Roof Curbs Wal-Mart Contractor Contractor Contractor to
Schedule
07900 Sealant for Caulking Around
Columns at Resilient Flooring
Wal-Mart Wal-Mart Wal-Mart Contractor to
Schedule
09310 Ceramic Tile and Accessories Wal-Mart Contractor Contractor Contractor to
Schedule
09320 Vestibule Tile and Accessories Wal-Mart Wal-Mart Wal-Mart Contractor to
Schedule
09650 Resilient Floor Tile and Adhesive Wal-Mart Wal-Mart Wal-Mart Contractor to
Schedule
Floor Treatment Materials Wal-Mart Wal-Mart Wal-Mart Contractor to
Schedule
09655 Resilient Base and Accessories Wal-Mart Contractor Contractor Contractor to
Schedule
09680 Carpet C-1 (Pharmacy) Wal-Mart Wal-Mart Wal-Mart Contractor to
Schedule
09900 Paints (Limited Quantities) Wal-Mart Contractor Contractor Contractor to
schedule
10160 Metal Toilet Compartments
(Hardware)
Wal-Mart Contractor Contractor Contractor to
schedule
10260 Refrigerated Case Protection Wal-Mart Contractor Contractor Contractor to
Schedule
Not For Construction01640-3
2901 - Northampton, Massachusetts - 1452013 April 21, 2015
Specification
Section
Description Furnished
By
Received
By
Installed
By
Order
Date*
Delivery Date*
Drawings Signage (unless otherwise noted) Wal-Mart Contractor Separate
Contractor
Contractor to
Schedule
w/Sign Dept.
10810 Toilet Accessories Wal-Mart Contractor Contractor Contractor to
Schedule
11141 Auto Service Equipment Refer to Architectural Drawings for
Schedule of Equipment
Contractor
coordinate with
equipment
supplier
11400 Food Service Equipment Refer to Grocery Drawings for Schedule
of Equipment
Contractor
coordinate with
equipment
supplier
13810 Energy Monitoring and Control
Systems
Wal-Mart,
unless
noted
otherwise
Contractor Contractor Contractor to
Schedule
15100 Pumps (except Truck Well Pumps)
and Water Piping Specialties
(Examples: drains, cleanouts, hose
bibbs, hydrants, valves, vacuum
breakers, mixing valves, pressure
reducing valves, expansion tanks)
Wal-Mart Contractor Contractor Contractor to
schedule
15410 Plumbing Fixtures Wal-Mart Contractor Contractor Contractor to
schedule
15600 Refrigeration and Refrigeration
Equipment including Compressor
Rack Systems, Condensers,
Condensing Units, Evaporators, Ice
Flakers, Produce Misting Systems,
Refrigeration Alarm System
Wal-Mart Contractor Contractor Contractor to
coordinate w/
Wal-Mart
Mechanical
Services Dept.
Grocery
Drawings
Refrigerated Cases Refer to Architectural Drawings for
Schedule of Equipment
Contractor to
coordinate w/
Wal-Mart
Mechanical
Services Dept.
16500 and
Electrical
Drawings
Light Fixtures Refer to Electrical Drawings for Lighting
Fixture Schedule
Contractor to
schedule
delivery
Architectural
Drawings
Sales Area Merchandise Fixtures
Gondolas
Half Gondolas
Heavy Duty Gondolas
End Caps
Bike Racks
Wal-Mart Wal-Mart Wal-Mart Wal-Mart to
Schedule
Architectural
Drawings
Anchorages for Sales Area
Merchandise Fixtures
Wal-Mart Contractor Contractor Wal-Mart to
Schedule
Architectural
Drawings
High Stock Fixed Racks/Lockable
Storage Rack Systems
Wal-Mart Wal-Mart Wal-Mart Contractor to
Schedule
Architectural
Drawings
Anchorages for Fixed Stock Fixed
Racks/Lockable Storage Rack
Systems
Wal-Mart Contractor Contractor Contractor to
Schedule
Electrical
Drawings
Power Poles for Cash Registers Wal-Mart Contractor Contractor Week of
possession
Electrical
Drawings
Pre-wired Power Poles Wal-Mart Contractor Contractor Contractor to
Schedule
Drawings Cash Registers Wal-Mart Wal-Mart Separate
Contractor
Week of
possession
Drawings Alarm Systems Separate
Contractor
Separate
Contractor
Separate
Contractor
Contractor to
Schedule
Not For Construction01640-4
2901 - Northampton, Massachusetts - 1452013 April 21, 2015
Specification
Section
Description Furnished
By
Received
By
Installed
By
Order
Date*
Delivery Date*
16700 Telecommunications/Data Systems Wal-Mart Wal-Mart Wal-Mart Contractor to
Schedule
END OF SCHEDULE