32C-149 Project Meeting Minutes 120904The Office of
P E T E R F R O T H I N G H A M
Registered Architect
181 Main Street, Suite One
Northampton MA 01060
USA
413 585 5910
5-Sep-12
M E M O R A N D U M
Re: McCarthy Properties Façade Reconstruction
Subject: 4 Sep 12 Project Meeting Minutes
Present: Name:Organization:Initials:
Susan Hewett McCarthy Properties, Inc. SH
Louis Gallinaro TCI LG
Michael Fitzgerald TCI MF
Chris Burkhardt TCI CB
Ryan Hellwig RHPE RH
Peter Frothingham PFRA PF
ITEM DESCRIPTION ACTION PERSON
OLD BUSINESS
1 Meeting relocated to Watering Hole
lounge
PF to note in meetings that future
meetings also relocated 04-Sep-12
2
CB reports TCI has started mobilization,
confirming existing conditions, beginiing layout
for new roof support structure.
None 04-Sep-12
3
Sidewalk removal scheduled to begin
Thursday morning, begin at Beehive end,
cutting for a few hours, removal follows.
MF to arrange for TCI staff on hand to redirect
pedestrians, SH notify tenants Wednesday 04-Sep-12
4
Parking arrangements reviewed. TCI using
McCarthy overflow parking lot, Zuli's lot, and
street parking. MF indicates that TCI dump
truck will overnight in McCarthy lot.
SH will get recycling bins recently placed in
front of jersey barriers relocated to create
another parking space.
SH
5
Installation of temporary protection walls is
beginning. Due to need to cut gypbd in order
to get attic beams in and still have
maneuvering room, at first temporary walls in
third floor apartment will be taped poly, once
beam in place, then plywood temporary wall
installed.
CB will notify Northampton Coffee of
temporary wall installation, probably Tuesday
next week maybe the next day. SH to confirm
notifiction w/ tenant
04-Sep-12
6
CB reviewed roof support post details, RH
confirms attachment at bottom of post on
plate on existing 6x6 beam on masonry wall;
splicing the post, stagger by a foot, close to
floor or ceiling.
CB & RH will review in field after meeting 04-Sep-12
Page 1 of 4
7
CB reviewed roof support beam bearing
details. RH confirms not splicing the beam,
beams begin and end on centerline of post,
suggests lapping 2x6 down sides for lateral
bracing and attachement; no bearing
plate/saddle needed.
None 04-Sep-12
8
CB points out there is barely enough room
above third floor false ceiling and under attic
ceiling joists for beams, both in terms of depth
of beam and to accomdate out-of-level
condition of existing building.
Conclusion to keep as designed, slope beam
to existing conditions. RH will determine
allowable amount to be trimmed if/when
necessary; confirms no saddle shop drawing
submittal required.
04-Sep-12
9
CB indicates staging installation is scheduled
to occur on Tuesday and Wednesday next
week. MF notes this may slide a day or two,
depending on foundation inspection
requirements.
None
9.1 4 Sep 12 - TCI will request larger outriggers to
provide more maneuvering room. MF to arrange MF
10
TCI anticipates sufficient sidewalk removal
Friday to provide three foundation inspection
pits: 2'deep, 2' wide, and 3-5' long.
CB will notify RH & PF when ready, RH will
inspect and if needed indicate locations for
further excavation and inspection.
04-Sep-12
11
MF explains once foundation trench is
complete in an area, trench will be partially
filled w/ membrane installed at an angle with
excess collected above fill placed on top of
membrane, to povide base for scaffolding.
TCI to sumbit and PF to review membrane
shop drawing immediately.TCI, PF
12
MF notified SH that McCarthy Properties or
HPMG need to submit request to Gas
Company for relocation of gas meters within
next few weeks.
SH to contact HPMG SH
12.1 Not resolved yet TCI to contact Gas Co. CB
13 PF & CB reviewed detail 6/A4.2 None 04-Sep-12
14 CB indicates single electrical outlet in
basement is insufficient for temporary needs.
CB will contact Beaulieu to arrange for
temporary power from basement 04-Sep-12
15
EWS is removing baseboard heat at third floor
apartment Wednesday. CB has reviewed with
tenant.
CB to confirm if this removes heating from
entire apartment or just front rooms.04-Sep-12
16
CB reports the dumpster will be placed in
parking spaces in center of building day after
scaffolding is complete.
None
17
LG noted to SH that third floor tenant
contacted TCI for an update, CB is in touch
with him each day.
None
18 SH announced that second floor apartment is
rented as of 1 Sept. TCI to install temporary wall before move-in. SH
18.1 SH indicates tenant will move in mid-Sept. SH will confirm actual dates SH
19 LG asked PF to review draft submittal
schedule to confirm items needed.PF to review 04-Sep-12
19.1
PF did review draft, which was for
confirmation of required submittals, no dates
included. Ryan asked to be included in the
distribution.
TCI to submit.MF
Page 2 of 4
20
PF reported that price quoted to Beaulieu for
light fixture "A" is well over estimate provided
by distributor in Boston. PF is attempting to
contact distributor. PF suggested we may
wish to consider an alternative approach,
particularly if it coordinates with business
tenants' requests for vertical signage above
awnings. SH indicated McCarthys are not
enthusiastic about banners.
PF to follow up with distributor. PF
20.1
PF contacted CT distributor instead of Boston
distributor, who offered a substitute. PF also
contacted a third distributor to get a second
quote for originally chosen fixture, distributor
submitted quote that fits budget, indicating an
example was to be installed imminently in
West Hartford we could visit.
PF to follow up, visit site. PF
21
SH requested that when soil is removed for
foundation inspection, samples be taken for
submittal to Umass extension service for
analysis to determine if there is something in
soil that is killing trees in sidewalk.
SH will coordinate w/ Bill McCarthy to be
available on Friday with three buckets to
receive samples.
SH
NEW BUSINESS
22 LG requests that distrubution include subs LG to provide list, PF to include in distribution LG, PF
23
CB reports storefronts anticipated to be
removed by end of day; tenant in third floor is
OK with work beginning at 7am with notice;
roof beam installation begins tomorrow;
trenching along foundation begins tomorrow
weather permitting.
SH to confirm Emily is sole source of
Northampton Coffee direction.SH
24
Observation Holes: Brick appears in rough to
poor condition to a depth of perhaps 9
courses down. RH requests deeper trench to
confirm condition of top 24" of existing brick.
MF indicates trench to 36" deep, will use
excavation equipment to accomplish.TCI
25
Observation Holes: top of foundation wall
appears to have bowed in 4" +/- towards
center, top of foundation wall will not be under
new bond beam. RH indicates need for piers
to be poured exterior of existing foundation to
below frost; agreement that north and south
ones will be smaller than intermediate ones.
RH will email dimensions for footings by
Thursday morning, record sketch to follow
within a few days. TCI to excavate for piers,
clean brick and pin, provide forms to be
buried based on RH info. Pour piers
Thursday, backfill on Friday.
RH, TCI
26
CB inquired of location of new basement
footings. RH confirmed under corner of flat
and sloped framing in first floor alcoves.
None.
27
CB and RH reviewed threaded rod and epoxy
requirements at saddles and existing brick
foundation wall. RH confirmed use of Hilti
HY20 with screen tubes.
None.
Page 3 of 4
28 MF reports foundation membrane arrives
Thursday.
TCI to confirm with Northampton DPW exact
sub-sidewalk specification requirements.TCI
29 LG submitted draft pay req. PF to review.PF
NEXT MEETING:
1pm, 11 Sep 12, at Watering Hole
Please bring to the architect's attention errors or omissions in these minutes by replying all to this email within 48 hours.
cc: Susan Hewett Louis Gallinaro
Michael Fitzgerald Chris Burkhardt (via MF)
Ryan Hellwig Louis Hasbrouck
HL Foster EWS Plumbing
Beaulieu Electric Peter Frothingham