2017_1108 Monthly Report - October CONTROLLED CONSTRUCTION SUMMARY: OCTOBER 2017 PROJECT NAME/LOCATION: LIVE 155/155 Pleasant St ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 11/08/2017 ESTIMATED % COMPLETION: 65% SCHEDULE CONFORMANCE: YES PRESENT ON SITE: Peter Makrauer - LDa, Peter Frothingham – PFRA I) WORK IN PROGRESS: · PV panel installation underway · Roof parapet metal cap installation is ongoing · Priming and painting near completion and ready for finishes at 2nd- 4th floor units · Rain screen fiber cement panels being installed at south elevation · Rough electrical, plumbing, HVAC, FP provisions ongoing · Masonry work is ongoing – ½ way complete with final wing wall at NE · Drywall installation is ongoing · Door frame installation underway II) OBSERVATIONS: · 2nd – 4th floor – west end gyp-crete floors have been poured · First shipment of rain screen panels are being installed smoothly · Site appears to be managed well, safety protocols are emphasized & enforced by GC · Site trailer continues to be the location for all regular job meetings · Work appears to be completed in accordance with plans and specifications III) ANTICIPATED WORK IN THE NEXT 4 WEEKS · Complete installation of PV panels · Begin laying tile in bathrooms · Continue installation of metal parapet cap at roof · Continue drywall installation · Continue priming and painting walls and ceilings · Finish masonry work · Continue installation of FCP panels (complete south elevation) · Continue installation of frames and begin installing doors. IV) INFORMATION/ACTION REQUIRED: · None at this time. NOTE: WEEKLY CONSTRUCTION ACTIVITY SUMMARIES & PROJECT SCHEDULE UPDATES ARE INCLUDED WITH THIS DOCUMENT. PREPARED BY: Peter Makrauer - Project Manager - LDa WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 10.04.17 ACCOMPLISHMENTS 1. Rain Screen: North side paper, furring and fins 2. Windows: Pleasant Street masonry opening windows installed and insulated 3. Roof: Started tackling firestop detail at parapet 4. Storefronts: Submittal returned, all parts and materials ordered, template Monday 5. Masonry: Mason mobilized and laying bring above South Entrance Canopy 6. 4th Floor: Drywall loaded and closing walls underway 7. 4th Floor: Framing modifications for Line Set roof penetration openings completed 8. 1st Floor: Bathroom and kitchen ceilings framed, sprinkler heads and fans being roughed 9. 2nd & 3rd Floors: Corridors being drywalled and taped 10. 2nd & 3rd Floors: Paint colors provided, priming ongoing ready for paint 11. Sitework: Marion mobilized and working to complete remaining underground GOALS 1. Windows: Conference call with AD, Design Team and Wayfinders to reach consensus on best path forward 2. Bike Path: Mobilize and complete all AVB, blocking, rigid insulation, paper and furring 3. Rain Screen: Continue to measure and order siding (North) 4. Roofing: Start metal parapet cap south, working from pinch point West 5. 4th Floor: Gyp-crete 10/12 6. 4th Floor: MEP Rough, set pace for drywall / close walls load on 10/26, all clear 10/30 7. 1st Floor: Cut back sprinkler heads, set fans, wire and connect drywall load 10/19, all clear 10/23 8. Showers: Plan and coordinate work sequence for proper execution / quality control 9. Sitework: Complete Comcast, Verizon, North Canopy drain, generator pad 10. Design Team priorities a. Generator Pad Location (discuss option presented earlier in week) b. Paint colors (remaining colors?) c. Stair details (forwarded, questions / concerns / clarifications) d. Storefront tie-in to FCP (detailed in returned storefront shop drawings) e. All MEP RFI’s and submittals f. Window Testing Memo Updates WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 10.11.17 ACCOMPLISHMENTS 1. Windows: Assist from LDa ratcheting up pressure on AD for solution to and implementation of fix for test failures, documentation of same, casement re-test today 2. Masonry: Brick above South Entrance Canopy complete, just wash down remaining 3. Rain Screen: West end of North elevation field dimensions taken, material ordered 4. Roof: Parapet cap metal commenced 5. Gyp-crete: Pre-installation conference with specific discussion about need for precision in bathrooms, West end 4, 3 and 2 ready for Th/Fri 6. 4th Floor: East end MEP rough on pace for kitchen & bathroom ceilings 10/23, drywall load 10/26 7. 1st Floor: Sprinkler heads and fans in bathroom and kitchen ceilings complete 8. 2nd & 3rd Floors: Corridors being closed and taped 9. 2nd & 3rd Floors: First coat of finish paint being applied in rooms 10. Sitework: Marion remaining underground complete, vault, transformer, canopy drain GOALS 1. Windows: Confirmation of proposed solution to double hung failures and mobilization to implement fix for week of 10/23 2. Bike Path: Complete all required work and field measure for fiber cement 3. Rain Screen: Campora mobilize at nook & pinch point, complete paper & furring, field measure, would like material week of 11/6 4. Roofing: Sufficient progress on South parapet cap, out of way for cement siding arrival 10/23 5. Mason: Mobilize NE for final sections, goal to be off site by end of month 6. 4th Floor: Complete tape and finish West end after gypcrete, paint and ready for finishes 10/30 7. 4th Floor: Complete MEP Rough east end, 10/23 clear for bathroom and kitchen ceiling framing, sprinkler, fans and insulation, drywall / close walls load on 10/26, all clear 10/30 8. 1st Floor: Bathroom and kitchen ceiling inspections, load drywall 10/19 9. Sitework: Coordination / sequence meeting with Marion, PVCS, Valley Landscaping for work to commence 10/23 10. Design Team priorities a. All RFIs b. Window Testing Memo Updates c. Submittals for finishes with all color selections WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 10.18.17 ACCOMPLISHMENTS 1. Windows: Casement units passed last Wednesday, remedy for double hung units somewhat agreed to, AD mobilization for double hung retro-fit and retest solidified for next week 2. Bike Path: Work requiring access from Bike Path complete 3. Gyp-crete: West end 4th, 3rd and 2nd floors poured 4. Masonry: Fully washed above SE canopy, mobilized NE and moving swiftly 5. Roof: Parapet cap fascia piece South, West and North 6. Rain Screen: Fins installed at pinch point, fry reglet received and being installed 7. 4th Floor: East end rough remains on pace for kitchen & bath ceilings 10/23, drywall load 10/26 8. 1st Floor: Sprinkler heads and fans in bathroom and kitchen ceilings complete 9. 2nd & 3rd Floors: Corridors being closed and taped 10. 2nd & 3rd Floors: First coat of finish paint being applied in rooms GOALS 1. Windows: Confirmation of proposed solution to single hung failures and mobilization to implement fix for week of 10/23 2. Rain Screen: Receive first shipment of siding material, shake out and commence install 3. Rain Screen: Finalize dimensions and place order for nook & pinch point material, would like material week of 11/6 4. Mason: Finish final NE elevation and 2 South columns, goal to be off site by end of month 5. 4th Floor: Complete tape and finish West end, paint and ready for finishes 10/30 6. 4th Floor: Complete bathroom and kitchen ceiling framing, sprinkler, fans and insulation, load drywall on Thursday, all clear for close on 10/30 7. 1st Floor: Insulate, load drywall 10/26 8. Roof: Warranty sign off on seams, load solar panels, rack system and ballast 9. Sitework: Learn lead time on CE soil and granite, reorganize Pleasant Street and start grading 10. Design Team priorities a. All RFIs and submittals b. Window Testing c. 1st floor laundry WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 10.25.17 ACCOMPLISHMENTS 1. Rain Screen: First shipment received and being installed, order placed for nook and pinch point 2. Masonry: Completed and washed 1 of 2 remaining lifts at NE, set up to start 2 of 2 3. Windows: AD, SGH, LDa and PFRA all on site for double hung testing, results “mixed,” there is a plan in place that involves an alternate handle (Lynne B has details) 4. Roof: Seam inspection performed, clear to load solar panels and gear, PV Squared pre- delivering panels and ballast in preparation for crane on Saturday 5. Roof: Parapet vents drilled 6. 4th Floor: East end rough remains on pace for drywall load this Thursday, close Monday 7. 1st Floor: West end rough in and insulation on pace for drywall load this Thursday, close Monday 8. 2nd, 3rd and 4th Floors: Mud, tape, sand, prime and paint nearing completion and ready for finishes, unit entry door frames being installed GOALS 1. Windows: Approval of alternate handle, carry out retro-fit work and retest 2. Rain Screen: Continue with installation of panels on South Elevation, prepare to rcv next shipment 3. Mason: Finish final NE elevation and 2 South columns, off site by end of month 4. 4th Floor: Commence with bathroom waterproofing, water test end of next week, start mud set 5. 4th Floor: Laundry Room MEP rough 6. 4th Floor: Load drywall tomorrow, start closing and finishing West end Monday 7. 1st Floor: Load drywall tomorrow, start closing and finishing Monday 8. Roof: Load solar panels, rack system and ballast Saturday with crane 9. Sitework: Learn lead time on CE soil and granite, reorganize Pleasant Street and start grading 10. Design Team priorities a. All RFIs b. Window Testing Memo Updates c. Submittals for finishes with all color selections WEEKLY CONSTRUCTION ACTIVITY SUMMARY PROJECT: LIVE 155 ARCHITECT’S PROJECT #: 201420 DATE ISSUED: 11.01.17 ACCOMPLISHMENTS 1. Rain Screen: First shipment installation going smoothly, order placed for nook, pinch point & North side with anticipated delivery 11/7 2. Masonry: ½ way up last wing wall at NE despite multiple rain outs 3. Windows: AD completed installation of taller snubber tracks, retest scheduled for 11/9 4. Roof: PV Squared successful crane day on Saturday, installation underway 5. Roof: Lower metal complete on small parapets 6. Unit Tile: Waterproofing started on 3rd Floor 7. Elevator: Delivered, requirements for installation to begin being addressed 8. East End: Plumbing rough ahead of schedule on 2nd and 3rd floors 9. HVAC: Equipment on West and Center racks piped and brazed, on final 15 at East rack GOALS 1. Windows: Approval of alternate handle, retest scheduled next week 11/9 2. Rain Screen: Complete installation of panels on South Elevation, prepare to rcv 11/7 shipment 3. Mason: Finish final NE elevation and column at South canopy, off site by end of next week 4. 4th Floor: Continue with bathroom waterproofing, water test this week, start mud set 5. 4th Floor: Complete Laundry Room MEP rough 6. 2nd & 3rd Floors: Plumbing inspection Monday 7. 1st Floor: West end MEP rough, insulation and fire caulking 100% by end of week 8. Solar: Steady progress toward goal of installation complete for end of Nov 9. Sitework: Learn lead time on CE soil and granite, reorganize Pleasant Street and start grading 10. Design Team priorities a. All RFIs b. Submittals – grout, cabinet, appliances, sitework materials c. Bulletin 8