38-050 (36) COSTELLO DISMANTLING CO., INC. SHOP DRAWING TRANSMITTAL FORM
MAILING ADDRESS PROJECT
2 Rocky Gutter Street NORTHAMPTON STATE HOSPITAL
Middleboro, MA 02346 Demolition of Laundry & Boiler Facility. , SAN 2 3 2003
Ph : 508.946.0880 Northampton State 1 lospital Route 66
Fax : 508.947.3093 Northampton, MA e
Email: costello99@attbi.com ``
ATTN: Ms. Sarah Northrup P: 413.572.3279
Tighe & Bond F: 413.562.5317 TRANSMITTAL Number 5
53 Southampton Road
Westfield, MA 01085 DATE 1/22/03
Page 1 of 6
------------------------------------------------------------------------------------------------------------------------------------------------------------
PLEASE FIND ATTACHED FIVE (5) COPIES OF TI lE FOLLOWING DOCUMENTS:
Ck
ITEM SPEC. Para. No. DESCRIPTION Tighe & Bond Action
t
No. SECT. (for Engineer's Use)
CODE BY
A02220 1.2 B Blasting procedure for Stack
This certifies that the information transmitted herewith has been reviewed, checked and approved by Costello Dismantling �
to include [ield measurements, co-ordination with sub-contractors and suppliers and adherence to specifications. 'Cl
For Costello Dismantling Co., Inc.
ACTION CODES: 1 = Approved 2 = Approved as Noted 3 = Approved as Noted, Resubmission Required.
4 = Disapproved, See Notes, Resubmission Required.
. I
C O S T E L L O D I S M A M T L I N G C O I N C
January 22, 2003
ATTN: Ms. Sara Northup P: 413-572-3279
Tighe & Bond, Inc. F: 413-562-5317
53 Southampton Road email:senorthup@tighebond.com
Westfield, MA 01085
FROM: Robert Holmes P: 508-946-0880
Costello Dismantling Co, Inc. F: 508-947-3093
2 Rocky Gutter St. email:costello99@attbi.com
Middleboro, Ma. 02346
Project: Demolition of Laundry and Power Plant
Northampton State Hospital
TOPIC: BLASTING PROCEDURE FOR STACK
TRANSMITTAL
Please find attached our proposed Blast Plan (six copies) as prepared by our subcontractor,
Saunders Drilling & Blasting Co., Inc., which has been previously faxed to your office. Please note that the
Northampton Building Inspector has also requested a copy of this plan, with a request that the Mayor of
Northampton pull the final switch as a public relations event. In summary, a wedge will be removed from
the lower portion of the stack and the structure will fall to the rear of the property well away from the upper
Hospital Building.
In regards to our current schedule, we anticipate that the asbestos abatement services will now be
completed by January 31`/early February; Tunnel cut-off masonry walls are currently being installed;
remaining utilities to be terminated in late-January; Portico Change Order work to begin week of January
27`" in conjunction with ACT Abatement for handling asbestos disposal; with Boiler Building demolition
beginning thereafter.
Again, we have scheduled the Coal Tunnel and roadway repairs as the last project tasks so that we
will be installing the asphalt in the spring.
We do understand that the Laundry Building has been removed from our contract by Mass
Development.
2 R O C K v G U T i E R S T R E E T . M I D D L E H O R O . M A S S A C H U S E T T S O 2 3 4 6
5 0 8 - 9 4 6 - 0 8 8 0 1 - 8 0 0 - 3 2 5 . 6 5 6 9 F A x 5 0 8 - 9 4 7 - 3 0 9 3
JAN-22-2003 WED 08:37 AM SAUNDERS D&B 19785624650 P. 02
118 COTTAGE ST. � 4 978-568-9509
HUDSON, MA 01749 Fax:978-562-4&50
'The B/JI nq Exp�rtsn
Costello Dismantling Co., Inc. January 21,2003
2 Rocky Gutter St.
Middleboro MA 02346
Re: Northampton State Hospital Smokestack Demolition
Gentlemen,
Here is the Blast flan information you requested for the above referenced project:
A wedge shaped pattern of 13/4"diameter holes will be drilled horizontally into the stack
on both sides of the duct opening. Each hole will have an explosive charge and a separate
"millisecond delay"detonator.
The blast will be designed to fire sequentially,taking advantage of the duct opening as a
point of relief.
Upon detonation the stack will lean in the direction of the main hospital building. We
anticipate the stack to begin to break up and start collapsing at approximately 30 to 45
degrees from vertical.
As you know, from many similar past projects, it is not possible to precisely determine
the enact number of charges or total pounds of explosives needed until we begin drilling.
At that point we will get critical information with respect to the condition and actual
construction of the stack, i.e., competency of the brick,presence of concrete liner,
reinforcing etc.
At this point we anticipate approximately 40 individual charges of 1/2 lb. per charge,
Please refer to the attached pages, 1 thru 3 for additional information.
If you have any questions,please call.
Respectfully,
{
David K. Saunders
JAN-22-2003 WED 08:37 AM SAUNDERS D&B 19785624650 P. 03
Northampton State Hospital Smo4estack Demolition - BIdg. 28 South
Plan Vilew
NOT TO SCALE
Abandoned State Hospital Bldg.
304 ft.+
A
Bldg.27s Direction of Drop
75 ft. ----�
B B
Brick
Stack
Bldg.288
A
EARLE ST.
200 ft
Prepared by:
O'CONNELL QII.MAINT.BLDG.
"The Blasting Experu"
This material is the property of Saunders Drilling&Blasting Co.,
Inc. and may not be used copied or reproduced in any manner
Page 1 of 3
JAN-22-2003 WED 08:38 AM SAUNDERS D&B 19785624650 P. 04
Nothampton State Hospital Smgi kestack Demolition - Bldg, 28 South
Section A-Aj. View
NOT TO SCALE
n
Direction of Drop
115 ft.(+/,)
V
Explosives Charges to
be placed in this area
36 ft.
62 ft.(+/-)
V
Existing Ground Elevation
� EARLE ST.
Prepared by:
This material is the property of Saunders Drilling&Blasting Co., Inc. and AMEMSAUPW0
may not be used copied or rcproduced in any manner ' Blasting
Page 2 of 3
JAN-22-2003 WED 08:38 AM SAUNDERS D&B 19785624650 P. 05
Northampton State Hospital Smo�estack Demolition - Bldg. 28 South
Section BtB View
NOT TO SCALE
�-- Smokestack Diu.-Approx. i I ft.
(< r
6 ft:
DUCT OPENING
n u
n
Explosives Charges to be placed in these areas
ROOF LINE
Prepared by:
This material is the property of Saunders Drilling&Blasting Co.,Inc.
and may not be used copied or reproduced in any manner. AffmsAG/SM
'"The Blasting Experts"