25A-190 (14) h lop P UMTA Project No. MA-03-0129 PVTA Northampton Bus Facility Contract Date: April 30, 1986 PROJECT PROGRESS SUMMARY AS OF DATE: July 22, 1986 Completion Date # Days Days Used Days Left Storage Area Secured 07-28-86 90 84 6 Complete 09-27-86 150 84 66 Service Area 10-27-86 180 84 96 Maint. Area Project Finish 01-30-87 275 84 lQl JUSTER POPE ASSOCIATES - ARCHITECTURE/INTERIORS/PLANNING July 22, 1986 777 F� as S UNTA Project No. MA-03-0129 PVTA Northampton Bus Facility SEP 9 i l Job Meeting Number 6 .�, � �?I� ' PRESENT: Robert Manz, Administrator Peter Jaskeivic, Ciocca Construction, Project Manager Carl Longley, Superintendent, Ciocca Construction John Shelvin, PVTA, Project Representative Andy Labbee, R.W. Hall Jack Frazier, Juster Pope Associates 1) Discussed General Contractor's expected date for completion of Phase I . The General Contractor indicated a target date of August 11 , 1986 for partial occupancy of Storage Bay. See GC 's letter dated July 21 , 1986. (Copy attached.) 2) GC has not received curb cut permit or permission for exploratory excavation on street to determine depth of water and gas lines. 3) Discussed gravel base details and requirements. GC will furnish a quote for gravel base as shown on drawings since on site pre-load material is not considered suitable for use with- out removal of stones over 3'' in diameter. 4) Discussed fuel dispenser 5) Next meeting scheduled for 8:30 AM, August 5, 1986. 1 ack Frazier cc: All Present 5 BRIDGE STREET SHELBURNE FALLS. MASSACHUSETTS 01370 TELEPHONE 413-625-2572 NORTON JUSTERIEARL POPE.'JACK FRAZIER UMTA Project No. MA-03-0129 P`!TA Northampton Bus Facilit7 Contrac� Date: April 30, 1986 PROJECT PROGRESS SUMMARY AS OF DATE: Completion Date # Days Days Used Days Left Storage Area Secured 07-28-86 90 98 -8 Complete 09-27-86 150 98 52 Service Area 10-27-86 180 98 82 Maint. Area Project Finish 01-30-87 275 98 177 JUSTER POPE ASSOCIATES • ARCHITECTURE/INTERIORS/PLANNING August 5, 1986 UMTA Project No. MA-03-0219 PVrA Bus Facility, Northampton, MA Job Meeting Number 7 PRESENT: Robert Manz, Administrator Peter Jaskievic, Ciocca Construction, Project Manager Carl Longley, Superintendent, Ciocca Construction John Shevlin, PVTA Project Representative Andy Labbee, R.W. Hall Consulting Engineers Jack Frazier, Juster Pope Associates 1) Discussed General Contractor's expected date for completion of Phase I. 2) Discussed location of water and gas lines in Industrial Drive. Storm drain can be installed as shown on C.T. Male Associates revised drawing dated 08-07-86. GC will proceed with installation. 3) Curb cut permit has been received and distributed. 4) Cost breakdown of replacement gravel base for paved area was discussed. GC was authorized to proceed with work on tine and material basis. Letter of authorization will be sent by Architect. Carl and John will determine extent of gravel contaminated by sitemor't and will monitor hours, loads and quantities of material and labor involved in extra work. Time extension to be based on actual time required to ccimwlete work. 5) Bollards have been installed but must be relocated to.e-xtend at least one inch into clear door opening. 6) Bob Manz approved use of temporary passage doors for Phase I occupancy. 7) Reviewed and approved rough pay requisition in the amount of $326,001.00. 8) Next meeting, scheduled for August 19, 1986 at 8:30 AM. Jack Frazier% cc: All Present 5 BRIDGE STREET SHELBURNE FALLS, MASSACHUSETTS 01370 TELEPHONE 413.625.2572 NORTON JUSTERIEARL POPEiJACK FRAZIER ..... . . -J ... , PVTA Northampton Bus Facility Contract Date: April 30, 1986 PROJECT PROGRESS SUMMARY AS OF DATE: August 19, 1986 Completion Date Days Days Used Days Left Storage Area Secured 07-28-86 90 112 -22 Complete 09-27-86 150 112 38 Service Area 10-27-86 180 112 68 Maint. Area Project Finish 01-30-87 275 112 163 9) Architect will send GC a letter of authorization to proceed with installation of hand hole for buried telephone line. 10) Discussed electrical conduit under slabs. 11) Next meeting scheduled for August 28, 1986 at 3:00 PM. OF— cc: All Present JUSTER POPE ASSOCIATES • ARCHITECTURE I INTERIORS/PLANNING f August 19, 1986 UMTA Project No. MA-03-0219 PVTA Bus Facility, Northampton, MA Job Meeting Number 8 PRESENT: Robert Manz, Administrator Peter Jaskievic, Ciocca Construction, Project Manager Carl Longley, Superintendent, Ciocca Construction John Shevlin, PVTA Project Representative Andy Labbee, R.W. Hall Consulting Engineers Jack Frazier, Juster Pope Associates John Cain, J.D. Contracting, Sitework Contractor 1) Architect instructed GC to remove damaged pre-cast panel from front corner of Bus Storage facia. 2) GC was asked to furnish a revised construction schedule for next meeting. 3) GC was asked to furnish required 8" x 10" photographs in plastic covers for three hole binders. 4) GC anticipated Phase I occupancer can be the first part of next week. 5) Discussed mounting height of bus storage lighting fixtures. Andy Labbee will check heights at Springfield facility and notify GC and Electrical Sub-Contractor. 6) GC will submit layout of proposed drain line re-routing to existing manhole in rotary. Northampton DPW must review and approve solution prior to proceeding with work. 7) GC will present breakdown for gravel replacement work for preparation of Change Order. 8) Discussed sign lighting. Location of sign to be reviewed by Bob Manz for compliance with Industrial Park guidelines and obtain sign approval from City of Northampton. 5 BRIDGE STREET SHELBURNE FALLS, MASSACHUSETTS 01370 TELEPHONE 413.625-2572 NORTON JUSTERIEARL POPEiJACK FRAZIER UMTA Project No. MA-03-0129 PVTA Northampton Bus Facility Contract Date: April 30, 1986 - PROJECT PROGRESS SUMMARY AS OF DATE: September 1986 Completion Date Days Days Used Days Left Storage Area Secured 07-28-86 90 133 -43 Complete 09-27-86 t50 133 17 Service Area 10-27-86 180 133 47 Maint. Area Project Finish 01-30-87 275 133 142 9) Mezzanine f loor shoring had been removed and replaced on west end to allow for installation of wall panels. High early yield strength concrete was not used as previously discussed. Questions were raised regarding the strength of concrete at time of removing shoring. G: has requested sample breaks for 7 and 9 day strength. No shoring is to be removed until concrete has reached 28 day strength. 10 ) Discussed location of bollards at vent stacks. Rcbert Manz approved proposed location. 11) Architect reviewed pencil pay requisition and reduced overhead door amount by $7,850.00 .for this period. 12) Ne.�ct meeting scheduled for 8:30 AM, September 23, 1986. Vic. W ' f ,Jack Frazier; cc: All Present JUSTER POPE ASSOCIATES • ARCHITECTURE/INTERIORS/PLANNING DUSTER POPE ASSOCIATES • ARCHITECTUREI INTERIORS/PLANNING September 9, 1986 U.MTA Project No. MA-03-0219 PVTA Bus Facility, Northampton, MA Job !Meeting Number 10 PRESr..^7r: Robert Manz, Administrator Peter Jaskievic, Ciocca Construction, Project Manager Carl Longley, Superintendent, Ciocca Construction John Shevlin, PVTA Project Representative Jack Frazier, Juster Pope Associates John Kane, J.D. Contracting, Sitework Contractor 1) General Contractor submitted a revised project schedule. 2) Discussed cutting and patching requirements. The General Contractor is responsible for cutting and patching. 3) Discussed t emocrary heat requirements. Heat is required to maintain working environment for PVTA Maintenance Personnel in bus storage area. 4 ) The General Contractor will have the Wayne Dalton Door Representative visit the site and approve door installation. 5) Grading of parxing lot questioned. The General Contractor will co of irm f in e grading. informs to elevations indicated cn site drawings. 6) Discussed occupancy requirrnents. F7-rA will accept storage bay when temporary lights are installed and doors are 100% installed except for elec~.;;c operators. One Hundred Fifty Day Completion Date is critical. PVTA must occupy all portions of Phase II construction on that date. 7) Robert Manz requested that all tanks have product labels installed on fill cans. 8 ) GC will provide a container for trash and clean site appropriately as required by Specifications. (Coaplaints were received from Industrial Part firms about construction trash and debris. ) 5 BRIDGE STREET SHELBURNE PALLS. MASSACHUSETTS 01370 TELEPHONE 413-625-2572 NORTON JUSTERIEARL POPE;JACK FRAZIER