25A-190 (13) w UMTA Project No. MA-03-0129 PVTA Northampton Bus Facility Contract Date: April 30, 1986 PROJECT PROGRESS SUMMARY AS OF DATE: September 25, 1986 Completion Date 1/ Days Days Used Days Left Storage Area Secured 07-28-86 90 147 -0- Complete 09-27-86 150 147 3 Service Area 10-27-86 180 t47 33 Maint. Area Project Finish 01-30-87 275 147 128 'r 4r JUSTER POPE ASSOCIATES • ARCHITECTURE/INTERIORS/PLANNING September 23, 1986 UMrA Project No. MA-03-0219 _ k`. `, .....-_pa... PVTA Bus Facility, Northampton, MA 2 9 1 Job Meeting Number 11 DEFT,OF BLIlLUNC!" PRESENT: Robert Manz, Administrator Peter Jaskievic, Ciocca Construction, Project Manager Carl Longley, Superintendent, Ciocca Construction John Shevlin, PVTA Project Representative Jack Frazier, Juster Pope Associates 1) Reviewed minutes of previous meeting: a) GC will have heat in Storage Area by September 29th. b) PVTA accepts Storage Area for Phase I Occupancy as of September 11, 1986. See GC letter of 9-11-86. c) Product labels have not been installed. Product names will be stenciled on fill caps. Names to be furnished by Owner. 2) The General Contractor requested clarification of overhead and profit for change order preparation. 3) GC will resubmit change request proposal for "P" traps at lifts. 4) Architect questioned steel erection testing report of August 8, 1986. No action has been taken to date by GC to tighten nuts and weld items indicated. Retesting is required. This remedial work must be completed before painting is finished in Storage Area. 5) GC stated exhaust fans would be installed by September 29th. Sprinkler system and water will also be completed by that date. 6) GC requested permission to change drain to Schedule 40 pipe when line reaches rotary island. Architect will review with Site Engineer. 7) GC requested color of vinyl fencing. Guard rails should be as per Mass. DPW Specifications. 8) NNext meeting scheduled for October 7, 1986. J`T cc: All Present 5 BRIDGE STREET SHELBURNE FALLS. MASSACHUSETTS 01370 TELEPHONE 413.625-2572 NORTON JUSTERIEARL POPEIJACK FRAZIER JUSTER POPE ASSOCIATES • ARCHITECTURE/INTERIORS/PLANNING September 26, 1986 ..� Mr. Edward J. Tewhill 29EN Building Commissioner City of Northampton DEPT.Of BUILDING INSPECT10'NS City Hall NO i_TFdh e"PTt3it,h4A.010610 Northampton, MA 01060 RE: PVTA Bus Facility, Northampton Industrial Park Dear Mr. Tewhill: Enclosed are copies of Test Reports and Minutes of Site Meetings covering the period from July 25, 1986 through September 25, 1986 for the above referenced project. The following sum-nary of work is submitted in compliance with Article 127.2.3 of the Massachusetts State Building Code. Summary of Work The Bus Storage Area has been completed for Phase I partial occupancy. PVTA has not started storing buses in the space as of this date, but occupancy is planned on September 29, 1986. The maintenance area and service areas are scheduled for Phase II completion on October 27, 1986. Most of the below grade structures have been completed except for the wash water reclamation tanks below the slab of the Bus Washing Area. Framing is in place for the remaining unfinished portion of the building and roof deck is being installed over these areas. The pre-cast wall panels are all in place with the exception of panels on Administrative and Day Care areas. Site drainage piping and structures have been completed in the southwest portion of the parking area and work is scheduled to begin on the line to the Rotary in Industrial Drive in the next several weeks. This line has been relocated because of a conflict with the existing gas and water lines due to changes in inverts which were shown on Drawing Ir2. There is a possibility that the gas line will have to be lowered in order for the drain line to pass above the water line even at the revised locations. Sincerely _yours, ac FI `ire-r cc: Robert Manz, PVTA Penny Kim, City of Northampton 5 BRIDGE STREET SHELBURNE FALLS, MASSACHUSETTS 01370 TELEPHONE 413-625-2572 NORTON JUSTER/EARL POPE/JACK FRAZIER