25A-186 (2) 7 William V. DeFlavio, P.E. May 16, 2008 City of Northampton, Building Department the high roof where some rod bracing has not yet been installed. Two story portal frames were installed in both sidewalls of the building between column lines 4 and 5 as shown on the plans. Miscellaneous framing items such as base and rake angles were also observed. The west wall of the building is insulated with 6" of fiberglass blanket insulation and covered with 26 gage metal wall panels. Second floor decking was installed in preparation for the concrete floor slab. Some metal base trim and a pass door in the west wall were also noted to be installed. Two 2 1/z" drains were noted in place to serve the two sinks shown on the plans. A 4" clean out was installed towards the southeast corner of the building. Two additional 4" C.I. risers were noted in place, one of which will be roughed to the second floor. Variations from submitted plans None up to this time. i wr 1 3 i End of p MASSq WILLIAM Re qt Owit y .o .Q No.9081 Q Q 9a �GISTB¢ r� �FsS/CNAL Eat\ William V. DeFlavio, P.E. t CONSULTING&DESIGN WORK 508-799-6554 REG.PROFESSIONAL ENGR.#9081 William V. DeFlavio 13 CAMERON STREET WORCESTER,MASSACHUSETTS 01604 May 16, 2008 Mr. Anthony Patillo, Building Commissioner Northampton Building Department 212 Main Street Northampton,MAO 1060 RE: Ice Addition Project Microcal L.L.C. 22 Industrial Drive Northampton, Massachusetts 01060 Dear Building Commissioner Patillo, In accordance with Section 116 of the Massachusetts State Building Code (6a`Edition), I, William V. DeFlavio, as the Professional Engineer of Record, submit the following report: Date of inspection: The Engineer visited the site to record the progression of the building's construction and to inspect the pre-engineered steel framing system. Progress/Inspection The building's steel framing system is approximately 80% complete. The Engineer noted that the primary framing such as columns, both exterior and interior, main frame rafters, end rafters, and mezzanine carrying beam are in place. Secondary framing including roof purlins, bar joists for the second floor, and wall girts are installed. Wall girts in the east wall between column lines 1 and 3 have not been installed to allow entry of construction equipment. The Engineer observed that most of the required bracing is in place. Roof flange braces were noted as well as much of the roof rod bracing is installed. Exceptions were noted in y 2 William V. DeFlavio, P.E. June 6, 2008 City of Northampton, Building Department The interior stud walls are approximately 85% complete. 25 gage metal studs were installed to the bottom of the second floor framing or roof rafters in the lower portion of the building. The walls were located as per the drawing with the exception of the door into Shipping and Receiving, which was relocated around the corner to the adjacent wall. An office, the entry at the east stairs, and the sprinkler room were not framed as of yet. Door openings were in and verified as to locations including the doorway into the existing building from Quality Control. It was noted that the openings to the existing building in Shipping and Receiving as well as the interior window framing have not been installed. The north wall of the existing building had been prepared to accommodate the design of the new building. The existing horizontal windows were removed and the openings covered with framing and 1/2" gypsum wall board. Existing exterior metal wall panels at Shipping and Receiving were removed to prepare to open the new building to the existing space. Both stairways are framed and verified as to geometry and location. Tread and riser dimensions were verified to be the correct 7" (riser) and 11" (tread)as required. Channels that make up the stringers are 12" deep channels as shown on the plans. Variations from submitted plans Doorway into the Shipping and Receiving was relocated around the corner into the adjacent wall. End p&PAM 3� Res ` fUgYF'wp y No.9G81 by �oA ONAL�N6 William V. DeFlavio, P.E. CONSULTING&DESIGN WORK 508-799-6554 REG.PROFESSIONAL ENGR.49081 William V. DeFlavio 13 CAMERON STREET WORCESTER,MASSACHUSETTS 01604 June 7, 2008 Mr. Anthony Patillo, Building Commissioner Northampton Building Department 212 Main Street Northampton,MAO 1060 RE: 1'= rice Addition Project Microcal L.L.C. 22 Industrial Drive Northampton, Massachusetts 01060 Dear Building Commissioner Patillo, In accordance with Section 116 of the Massachusetts State Building Code (6a'Edition), I, William V. DeFlavio, as the Professional Engineer of Record, submit the following report: Date of inspection The Engineer visited the site to record the progression of the building's construction including the interior metal stud framing and stair construction. Progress/Inspection The metal building system is fully erected and insulated. The Engineer was informed that rod bracing in the upper roof was shipped to the wrong length. Corrective action will be taken, of which to be determined, to resolve the problem and insure the placement of the bracing. Some of the horizontal sliding windows are installed on the north and east walls of the building with the remaining windows to be placed. Both hollow metal pass doors are installed in the east and west sides of the building. I&, Transmittok 327 West Street Post Office Box 0327 North Hatfield,Massachusetts 01066-0327 2008 DATE: 14-Jul-08 i ADDRESS CORRESPONDENCE TO: i TO: Name Bob Bartlett Mr. Louis,,Hasbrouck,Building lnspeefsr City of NdrtttfiWpbn 212 Main Street Northampton, Massachusetts 01060 PHONE 413-247-5024 FAX# 413-247-3305 e-mail info(cD-hampshireconstruction.com We are Sending You: attached These documents are transmitted. for your files Remarks: RE: MICROCAL, LLC Building Addition Project BP-2008-0833 ITEM QTY DESCRIPTION 1 one William V.DeFlavio, PE, Inspection Report 13 May 2008 2 one William V. DeFlavio, PE, Inspection Report 06 June 2008 14-Jul-08 Signed Date File:Hampshire Transmittal Letter(Version 2.0).)ls Printed:7/14/2008