25A-186 (2) 7
William V. DeFlavio, P.E.
May 16, 2008
City of Northampton, Building Department
the high roof where some rod bracing has not yet been installed. Two story portal frames
were installed in both sidewalls of the building between column lines 4 and 5 as shown
on the plans. Miscellaneous framing items such as base and rake angles were also
observed.
The west wall of the building is insulated with 6" of fiberglass blanket insulation and
covered with 26 gage metal wall panels. Second floor decking was installed in
preparation for the concrete floor slab. Some metal base trim and a pass door in the west
wall were also noted to be installed.
Two 2 1/z" drains were noted in place to serve the two sinks shown on the plans. A 4"
clean out was installed towards the southeast corner of the building. Two additional 4"
C.I. risers were noted in place, one of which will be roughed to the second floor.
Variations from submitted plans
None up to this time.
i wr 1
3
i
End of p MASSq
WILLIAM
Re qt Owit y
.o .Q No.9081 Q Q
9a �GISTB¢ r�
�FsS/CNAL Eat\
William V. DeFlavio, P.E.
t
CONSULTING&DESIGN WORK 508-799-6554
REG.PROFESSIONAL ENGR.#9081
William V. DeFlavio
13 CAMERON STREET
WORCESTER,MASSACHUSETTS 01604
May 16, 2008
Mr. Anthony Patillo, Building Commissioner
Northampton Building Department
212 Main Street
Northampton,MAO 1060
RE:
Ice Addition Project
Microcal L.L.C.
22 Industrial Drive
Northampton, Massachusetts 01060
Dear Building Commissioner Patillo,
In accordance with Section 116 of the Massachusetts State Building Code (6a`Edition), I,
William V. DeFlavio, as the Professional Engineer of Record, submit the following
report:
Date of inspection:
The Engineer visited the site to record the progression of the building's construction and
to inspect the pre-engineered steel framing system.
Progress/Inspection
The building's steel framing system is approximately 80% complete. The Engineer noted
that the primary framing such as columns, both exterior and interior, main frame rafters,
end rafters, and mezzanine carrying beam are in place. Secondary framing including roof
purlins, bar joists for the second floor, and wall girts are installed. Wall girts in the east
wall between column lines 1 and 3 have not been installed to allow entry of construction
equipment.
The Engineer observed that most of the required bracing is in place. Roof flange braces
were noted as well as much of the roof rod bracing is installed. Exceptions were noted in
y
2
William V. DeFlavio, P.E.
June 6, 2008
City of Northampton, Building Department
The interior stud walls are approximately 85% complete. 25 gage metal studs were
installed to the bottom of the second floor framing or roof rafters in the lower portion of
the building. The walls were located as per the drawing with the exception of the door
into Shipping and Receiving, which was relocated around the corner to the adjacent wall.
An office, the entry at the east stairs, and the sprinkler room were not framed as of yet.
Door openings were in and verified as to locations including the doorway into the
existing building from Quality Control. It was noted that the openings to the existing
building in Shipping and Receiving as well as the interior window framing have not been
installed.
The north wall of the existing building had been prepared to accommodate the design of
the new building. The existing horizontal windows were removed and the openings
covered with framing and 1/2" gypsum wall board. Existing exterior metal wall panels at
Shipping and Receiving were removed to prepare to open the new building to the existing
space.
Both stairways are framed and verified as to geometry and location. Tread and riser
dimensions were verified to be the correct 7" (riser) and 11" (tread)as required.
Channels that make up the stringers are 12" deep channels as shown on the plans.
Variations from submitted plans
Doorway into the Shipping and Receiving was relocated around the corner into the
adjacent wall.
End p&PAM 3�
Res ` fUgYF'wp y
No.9G81 by
�oA
ONAL�N6
William V. DeFlavio, P.E.
CONSULTING&DESIGN WORK 508-799-6554
REG.PROFESSIONAL ENGR.49081
William V. DeFlavio
13 CAMERON STREET
WORCESTER,MASSACHUSETTS 01604
June 7, 2008
Mr. Anthony Patillo, Building Commissioner
Northampton Building Department
212 Main Street
Northampton,MAO 1060
RE: 1'=
rice Addition Project
Microcal L.L.C.
22 Industrial Drive
Northampton, Massachusetts 01060
Dear Building Commissioner Patillo,
In accordance with Section 116 of the Massachusetts State Building Code (6a'Edition), I,
William V. DeFlavio, as the Professional Engineer of Record, submit the following
report:
Date of inspection
The Engineer visited the site to record the progression of the building's construction
including the interior metal stud framing and stair construction.
Progress/Inspection
The metal building system is fully erected and insulated. The Engineer was informed that
rod bracing in the upper roof was shipped to the wrong length. Corrective action will be
taken, of which to be determined, to resolve the problem and insure the placement of the
bracing. Some of the horizontal sliding windows are installed on the north and east walls
of the building with the remaining windows to be placed. Both hollow metal pass doors
are installed in the east and west sides of the building.
I&, Transmittok
327 West Street
Post Office Box 0327
North Hatfield,Massachusetts
01066-0327
2008 DATE: 14-Jul-08
i ADDRESS CORRESPONDENCE TO:
i
TO: Name Bob Bartlett
Mr. Louis,,Hasbrouck,Building lnspeefsr
City of NdrtttfiWpbn
212 Main Street
Northampton, Massachusetts 01060 PHONE 413-247-5024
FAX# 413-247-3305
e-mail info(cD-hampshireconstruction.com
We are Sending You: attached
These documents are transmitted. for your files
Remarks: RE: MICROCAL, LLC
Building Addition Project
BP-2008-0833
ITEM QTY DESCRIPTION
1 one William V.DeFlavio, PE, Inspection Report 13 May 2008
2 one William V. DeFlavio, PE, Inspection Report 06 June 2008
14-Jul-08
Signed Date