25A-185 (35) .. . HIXSON 659 Van Meter Street Cincinnati Ohio 45202-1568 513 241 1230 FAX 513 241 1287 field memo NUMBER7 SUBJECT: Coca-Cola North America, Northampton, Massachusetts Hot Fill Line Addition JOB NO. 6788.40 DATE: 03/26/07 Site Visit: 03/14/07 Mike Meyer on site PAGE 4 OF 4 condition that is generally unacceptable to GMP criteria. 57. BOTTLING ROOM 136 (01/31/07) - The material used to seal the top of the concrete curbs appears to be clear silicone and generally unacceptable to GMP standards 58. BOTTLING ROOM 136 (01/31/07) - The exposed edge of the concrete curb on the east side of Door 138F is not acceptable to GMP standards. 59. BOTTLING ROOM 136 (01/31/07) - Gas pipe penetrations through the roof are not sealed from below. 60. BOTTLING ROOM 136 (01/31/07) - The 36" SST duct from cooling tunnel 3 is not sealed below the roof structure. 61. BREAK ROOM 165 (01/31/07) - The PA speaker has not been installed. 62. OFFICE 181 (01/31/07) - HP-4 is Carrier and not design basis Trane unit. 63. OFFICE 181 (01/31/07) - Window 181z has not been provided. 64. OFFICE 182 (01/31/07) - HP-3 is Carrier and not design basis Trane unit. 65. OFFICE 182 (01/31/07) - Window 182z has not been provided. 66. OFFICE 183 (01/31/07) - HP-2 is Carrier and not design basis Trane unit. 67. OFFICE 183 (01/31/07) - Window 183z has not been provided. 68. OFFICE 184 (01/31/07) - HP-1 is Carrier and not design basis Trane unit. 69. OFFICE 184 (01/31/07) - Window 184z has not been provided. MJM/kab38 H:\00678800\projxl FieldMemos\40fm007a_031507FM7.doc HIXSON 659 Van Meter Street Cincinnati Ohio 45202-1568 513 241 1230 FAX 513 241 1287 field memo NUMBER 7 SUBJECT: Coca-Cola North America, Northampton, Massachusetts Hot Fill Line Addition JOB NO. 6788.40 DATE: 03/26/07 Site Visit: 03/14/07 Mike Meyer on site PAGE 3 OF 4 is near Column Line H-8 as opposed to H-6.8. This information must be indicated on as-built drawings. 32. BOTTLING ROOM (1/10/07) - Gas piping penetration through the roof to MAU-5 has not yet been complete. 34. BOTTLING ROOM (1/10/07) - Pipe guards are made of steel pipe that is shop primed and not of stainless steel as specified. See 4/A3.1. 35. BOTTLING ROOM (1/10/07) - Closure trim at top of panel and steel beam along Column Line 13 on warehouse side has not yet been installed. See 4/A3.1. 36. BOTTLING ROOM (1/10/07) - The low-temp panel on southeast corridor by Door 136C is damaged. 37. BOTTLING ROOM (1/10/07) - There is exposed fiberglass roof insulation around SB-2 from MAU-5. 38. BOTTLING ROOM (1/10/07) - Raceway and switch box for lighting circuitry located near Column Line WJ-13 is not PVC coated rigid steel conduit. 39. GENERAL ITEMS (01/31/07) - There are stray marks, residual concrete paste, etc. on the structural steel columns that has not yet been removed. 40. GENERAL ITEMS (01/31/07) - Welded connections to structural steel have not been wire brushed and touched up. 41. GENERAL ITEMS (01/31/07) - Hose stations and eyewash stations were placed in coordinated locations that are different than shown on the documents. Several of these units have not yet been piped and insulated. The locations of this equipment must be accurately pin pointed on the as-built drawings. 42. EXTERIOR (01/31/07) - Honeycombs and voids in exposed concrete foundation have not been filled. 43. EXTERIOR (01/31/07) - Light switch (card reader) is not yet installed. 44. ROOF (01/31/07) - The material used to seal the joints around the roof curbs is cracked and separating from the metal roof. 45. ROOF (01/31/07) - Construction debris is scattered throughout the entire roof top. 46. ROOF (01/31/07) - The equipment curb for RTU-1 is not the prefabricated insulated component that was specified. 47. ROOF (01/31/07) - The packaged air handling unit for RTU-1 is manufactured by Carrier. Trane was the design basis. 48. FILLER/CAPPER ROOM (01/31/07) - Spot welds to galvanized metal deck have not been wire brushed and touched up. 49. FILLER/CAPPER ROOM (01/31/07) - Caulking of window wall framing behind structural steel tube at the bottom is incomplete. 50. FILLER/CAPPER ROOM (01/31/07) - Access ladder on south exterior is not per Section 11/A5.1. 51. FILLER/CAPPER ROOM (01/31/07) - Painting of the HSS tube on southwest corner is incomplete. 52. FILLER/CAPPER ROOM (01/31/07) - HS-1 was installed in the northwest corner of the Filling Room. Back flow preventers were not provided. 53. STAIR #2 (01/31/07) - HSS stair post is not yet installed. 54. STAIR #2 (01/31/07) - 12 gauge galvanized metal risers are not installed. 55. STAIR #2 (01/31/07) - Stair and grating is shop primed and not galvanized. 56. BOTTLING ROOM 136 (01/31/07) - The surface of the concrete curbs is not smooth and in a rough HIXSON 659 Van Meter Street Cincinnati Ohio 45202-1568 513 241 1230 FAX 513 241 1287 field memo NUMBER 7 SUBJECT: Coca-Cola North America, Northampton, Massachusetts Hot Fill Line Addition JOB NO. 6788.40 DATE: 03/26/07 Site Visit: 03/14/07 Mike Meyer on site PAGE 2 OF 4 PENDING ITEMS 1. SITE (09/26/06) - Footings and foundation for the Office Addition are in place. There are "fins" and "honeycombs" on the exposed face of the foundation walls particularly on the north and east walls. These should be ground smooth and the voids filled with cement mortar. 2. EXISTING BOTTLING ROOM (09/26/06) - Installation of various utility piping systems is in progress. Jerry Goodsell indicated that layout and routing of piping has been field modified from the construction drawings. It is important to note that all subcontractors must accurately record all modifications on as-built drawings for inclusion on future record drawings. 3. SITE (10/16/06) - Installation of FP piping is substantially complete. CCNA has opted to leave the existing fire line in place. This must be noted on as-built drawings. A credit for the work scope reduction has not yet been offered. 5. ROOF (10/16/06) - Prefabricated structural roof curbs for duct penetrations is in place. These components are not the specified products and were locally fabricated. The material appears to be welded aluminum of a gage thickness that is not readily apparent. The specified material is 18 gage galvanized steel. The liner material also appears to be aluminum and is not welded in the corners but is sealed with reinforced metal tape. It is not readily apparent that insulation was provided. 7. BOTTLING & FILLER CAPPER ROOMS (10/16/06) - Installation of underground process waste piping is in progress. Routing of piping and connection points to the existing main is being modified from what is currently shown on the drawing. Field changes should be accurately noted on as-built drawings for incorporation into record drawings at the completion of the project. 9. RECEIVING OFFICE & TRUCKERS LOUNGE (10/16/06) - Underground sanitary drain piping is in place. Fred Snyder of Forish Construction advised that the invert elevation of the sanitary pipe at the west wall is actually at 95'-0" and not 94'-0" as currently shown. This was raised in order to maintain 1% slope in the 6" sanitary sewer to the manhole. This also must be recorded on as-built drawings. 10. BOTTLING ROOM 136 (12/20/06) - Concrete curbs have been installed on south wall to Column Line 10.4. Embed for '/" caulk joint at top of curb was not provided. See Detail 9/A0.2. 19. OFFICE ADDITION (12/20/06) - Door 186a has been placed on the east side of the room leading to Employee Hallway 156. 26. GENERAL ITEMS (01/10/07) - Much of the equipment being supported from bar joists is not per section details as shown on 18/S3.1 and 19/S3.1. 27. BOTTLING ROOM (1/10/07) - Wall curbs along WK is in an unfinished rough condition. Curbs near WK-W2 are nearly flat on top. 28. BOTTLING ROOM (1/10/07) - The paint subcontractor pointed out that two bolted connections on the east side of Column Line 8.5 that is south of Column Line WJ are not fully torqued. 29. BOTTLING ROOM (1/10/07) - The low-temp wall panel east of Door 136F is gouged. 30. BOTTLING ROOM (1/10/07) - The duct penetrations to the SB-2 diffusers do not appear to be fully enclosed above the box but below the roof structure leaving exposed fiberglass insulation within the space. 31. BOTTLING ROOM (1/10/07) - The 3" compressed air piping connection was made at a location that HIXSON 659 Van Meter Street Cincinnati Ohio 45202-1568 513 241 1230 FAX 513 241 1287 field memo NUMBER 7 SUBJECT: Coca-Cola North America, Northampton, Massachusetts Hot Fill Line Addition JOB NO. 6788.40 DATE: 03/26/07 Site Visit: 03/14/07 Mike Meyer on site PAGE 1 OF 4 PUNCH LIST The contractor is responsible for all requirements of the contract documents, whether noted on this or any other Punch list. Included in the contract documents is the requirement for submission of all closeout requirements. GENERAL ITEMS GI-1 Hose station pedestals in the Bottling Room have not been grouted. GI-2 Piping insulation in the Bottling Room addition has not been fully enclosed with a PVC jacket and sealed. GI-3 Testing and balancing has not yet been complete. GI-4 There are welded connections for modified connection plates for girts at Column Line 9.5 that have not been painted. GI-5 Final electrical wiring terminating to MAU-5 is not complete. GI-6 There is a cover plate missing on electrical junction box on wall girt adjacent to exterior door on southwest exit. GI-7 Hot and cold water piping at Column Line WS-10.5 is inadequately braced. GI-8 Safety railing at the Filing Room mezzanine level on south side has not yet been installed. GI-9 Welded connections to platform framing above Filling Room have not yet been painted. GI-10 Condulet covers on all junction boxes have not been installed. GI-11 There are "bird baths" (ponding water) in several locations adjacent to the trench drain in the Bottling Room addition. GI-12 Grout for acid-proof brick in the Filling Room has delaminated from the flooring. GI-13 The wall curbs in the Bottling Room addition are cracked in numerous locations. GI-14 There is construction debris on the mezzanine above the Filler Room. SITE S-1 Final landscaping has not yet been completed. S-2 The sidewalk on the north side of the Lunch Room has settlement cracks. S-3 Ladder gate to the cooling tower platform has not been installed. COPY TO DATE REVIEW BY INITIAL SIGNED: Jerry Goodsell CAJ Gary Carlow TLS Michael J. Meyer, CDT, RRO Jeff Casey ACTION: Eric Forish Anthony Patillo