25A-187 (2) GERALD P. BERSON, P.E. 5PT7F .35 Lee's Lane Longmeadow, MA 01106413-567-0793 2 5199 January 22 , 1994 �' '�INSPECTIONS City of Northampton :i;vt1GC
Building Department
212 Main Street
Northampton, MA 01061
RE: Mini Storage Buildings for Bob Foote - Northampton
Industrial Park
Construction Report No. 5
Gentlemen:
Since my last report dated January 9 , 1994 , the following
construction has been completed, inspected and except as noted
found to be in compliance with applicable codes and construction
documents for this project :
1 . As previously reported, all reinforced concrete work
including footings , foundation walls and slab on grade is
complete .
2 . Erection of the Butler pre-engineered metal mini-storage
warehouse buildings is continuing .
At building #1 , erection is basically complete . This
includes erection of all main framing members, interior and
exterior metal wall panels, standing seam metal roofing with
fiberglass insulation, exterior metal trim and exterior
metal roll-up security doors.
At building #2 , erection of metal framing members for walls
and roofing is approximately 60% complete. No exterior wall
panels or standing seam roofing has been installed at this
time . All Butler pre-engineered metal building components
have , however, been delivered to the job site . It is
estimated that erection of building #2 components will be
continuing over the next two weeks.
3 . Due to weather and snow covered conditions , no additional
site work has been completed since my last report . The last
time I observed the site , however, which was approximately
one month ago , no siltation, erosion control or site work
problems were noted.
Please let me know if you have any questions or comments .
Very truly yours,
Gerald P. Berson, P.E.
P. E. No. 32387
cc : The O'Leary Company, Inc .
GERALD P. BERSON, P.E. ;
35 Lee's Lane '
Longmeadow, MA 01106 FEB 91994
413-567-0793 55A�
€ �r S
February 5 , 1994
City of Northampton
Building Department
212 Main Street
Northampton, MA 01061
RE: Mini Storage Buildings for Bob Foote - Northampton
Industrial Park
Construction Report No . 6
Gentlemen:
Since my last report dated January 22 , 1994 , the following
construction has been completed, inspected and except as noted
found to be in compliance with applicable codes and construction
documents for this project :
1 . No additional concrete work or site work has been completed
since my last report . As noted, all reinforced concrete
footings , foundation walls and slab on grade is complete .
2 . As previously reported, erection of the Butler pre-
engineered metal mini storage warehouse building #1 is
basically complete including the installation of roll up
metal storage security doors .
Erection of building #2 is continuing . All main framing
members , interior and exterior metal wall panels and
standing seam metal roofing with fiberglass insulation has
been completed. Approximately 60% of the roll up metal
security doors have also been installed. No erection
problems were encountered or deficiencies noted.
It is anticipated that erection of remaining components for
this building will be completed during the next two weeks.
Site work, however, including dress-up of storm water
retention area and removal of siltation and erosion control
fencing will not be completed until weather and site
conditions permit .
Please let me know if you have any questions or comments .
Very truly yours,
Gerald P. Berson, P. E.
P.E. No . 32387
cc : The O'Leary Company, Inc .
y
ji
City of Northampton
February 19 , 1994
Page 2
4 . The owner has also taken responsibility for installation of
all electric service for these buildings.
5 . These buildings are now basically occupiable for dead
storage only.
This will be my final report on this project.
Please let me know if you have any questions or comments.
Very truly yours ,
Gerald P. Berson, P.E.
P.E. No . 32387
cc : The O'Leary Company, Inc .
GERALD P. BERSON, P.E.
35 Lee's Lane U
Longmeadow, MA 01106
413-567-0793
FEB 2 L .4 ,�/
February 19 , 1994 DEPT QFWJILOWCI;?Nc?PPOTION$
N. n r,
City of Northampton
Building Department
212 Main Street
Northampton, MA 01061
RE: Mini Storage Buildings for Bob Foote - Northampton
Industrial Park
Construction Report No. 7
Gentlemen:
Since my last report dated February 5 , 1994 , the following
construction has been completed, inspected and except as noted
found to be in compliance with applicable codes and construction
documents for this project:
1 . Erection of all remaining components for building #1 and #2
has now been completed including roll-up metal security
doors.
Butler metal gutters and downspouts are on the job site, but
have not yet been erected. All other Butler metal building
trim has been completed.
2 . As previously reported, all reinforced concrete work for
this project is complete. Some minor shrinkage cracking was
observed in the southeast corner of building #2 slab on
grade . Although this is not considered structural and no
vertical separation has occurred, this cracking should be
monitored over the next year and repairs made if necessary.
3 . All site work under the responsibility of the O'Leary
Company has been completed including installation of gravel
base and driveways between and around the perimeters of the
new buildings.
It is my understanding that soil and erosion control hay
bales and siltation fencing was installed by the owner under
the direction of the O' Leary Company. Since the entire site
is still snow and ice covered, I have not been able to
observe the condition of this area over the past several
months . It is my understanding that final dress-up of these
areas when weather and site conditions permit is the respon-
sibility of the owner and I will , therefore, not be
inspecting unless requested by the owner.