25A-179 (13) ARCHITECT'S OWNER ARCHITECT O • FIELD REPORT CONSULTANT ❑ AIA DOCUMENT 0711 FIELD ® Building Inspector PROJECT: Van Cort Instruments, Inc. FIELD REPORT NO: 7 CONTRACT: 09/15/87 ARCHITECT'S PROJECT NO: 10497 DATE 1/8/88 TIME 1230 p.m. WEATHER Cold-Snow TEMP. RANGE 250-50 EST. % OF COMPLETION 1.1 Mil = 69% CONFORMANCE WITH SCHEDULE (+, -) -4 weeks WORK IN PROGRESS HVAC installation PRESENT AT SITE Wayne Ortmann - Structural Systems drywall framing and placement of Erik Van Cort - Owner electrical features. OBSERVATIONS This report time, Ironworkers placed 5 roof curbs in warehouse and grouting of office steel columns is working. Electric transformer pad poured and Ironworkers are finishing up office erection. All rooftop units are set on curbs and ductwork installation is proceeding nicely. Drywall contractor started putting up metal studs and the electrician is finishing n:rough-in. Medintech flooring is being installed and-is approximately 50% complete. Gas piping is complete. a f �}f row" 29a ITEMS TO VERIFY None. INFORMATION OR ACTION REQUIRED Need to push contractors to complete;; work in a more timely manner. 1; � 0 _I /r At ATTACHMENTS None REPORT BY: G � Zz.-�!414 4L AIA DOCUMENT G711 • ARCHITECT'S FIELD REPORT OCTOBER 1972 EDITION AIA® • © 1972 THE AMERICAN INSTITUTE OF ARCHITECTS,1735 NEW YORK AVE., NW, WASHINGTON, D.C.20006 page of pages ARCHITECTS OWNER ❑ ` � /� FIELD REPORT ARCHITECT ❑ ` \ CONSULTANT ❑ AIA DOCUMENT G711 FIELD [2 Building Inspector (� PROJECT: Van Cort Instruments, Inc. FIELD REPORT NO: 8 CONTRACT: 9/15/87 ARCHITECT'S PROJECT NO: 10497 DATE 1/22/88 TIME 4:30 p.m. WEATHER clear TEMP. RANGE 410-300 EST. % OF COMPLETION 1.2 mil — 75% CONFORMANCE WITH SCHEDULE (+, —) —4 weeks WORK IN PROGRESS Drywall,',pltulibing PRESENT AT SITE --------- and ductwork being installed. Sprinkler piping is complete. OBSERVATIONS Unit heaters installed in warehouse are working as designed. Window wall frames are being set in office area. Roof curbs leaked and damaged 4500 s.f. of Medentech flooring. Floor installers were sent home until steel erector fixes roof leaks. Electrical transformers and switchgear are in place and permanent power is connected to building. Glazing being installed in office window walls. FEB c: 9 ' 88 ITEMS TO VERIFY None INFORMATION OR ACTION REQUIRED Carpeting needs to be ordered. RED q w► `t No. 069;3 rN- ST.LOJ1S, ATTACHMENTS Nnnp REPORT BY: G �z7r-T 'A DOCUMENT G711 • ARCHITECT'S FIELD REPORT OCTOBER 1972 EDITION AIA® • © 1972 ' AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW, WASHINGTON, D.C.20006 page of pages