36-294 (5) HVAC EQUIPMENT SIZING:
[ ] Rated output capacity of the heating/cooling system is
not greater than 125% of the design load as specified
in sections 780CMR 1310 and J4.4.
MISC REQUIREMENTS:
[ ] Refer to 780 CMR, Appendix J for requirements relating to swimming
pools, HVAC piping conveying fluids above 120 F or chilled fluids
below 55 F, and circulating hot water systems.
-- NOTES TO FIELD (Building Department Use Only)-------------------------
MAScheck INSPECTION CHECKLIST
Massachusetts Energy Code
MAScheck Software Version 2.0
DATE: 5-19-1999
Bldg.
Dept.
Use
CEILINGS:
[ 7 1. Raised Truss, R-38
Comments/Location
Insulation must achieve full height over the exterior wall.
WALLS:
[ ] 1. Wood Frame, 24" O.C., R-19
Comments/Location
WINDOWS AND GLASS DOORS:
[ 7 1. U-value: 0.35
For windows without labeled U-values, describe features:
# Panes_ Frame Type Thermal Break? [ 7 Yes [ 7 No
Comments/Location
DOORS:
[ ] 1. U-value: 0.08
Comments/Location
FLOORS:
[ 7 1. Over Unconditioned Space, R-19
Comments/Location
AIR LEAKAGE:
[ ] Joints, penetrations, and all other such openings in the building
envelope that are sources of air leakage must be sealed. Recessed
Lights must be type IC rated and installed with no penetrations
or installed inside an appropriate air-tight assembly with a 0.5"
clearance from combustible materials and 3" clearance from insulation.
VAPOR RETARDER:
[ ] Required on the warm-in-winter side of all non-vented framed
ceilings, walls, and floors.
MATERIALS IDENTIFICATION:
[ 7 Materials and equipment must be identified so that compliance can
be determined. Manufacturer manuals for all installed heating
and cooling equipment and service water heating equipment must be
provided. Insulation R-values and glazing U-values must be clearly
marked on the building plans or specifications.
DUCT INSULATION:
[ 7 Ducts in unconditioned spaces must be insulated to R-5.
Ducts outside the building must be insulated to R-8.0.
DUCT CONSTRUCTION:
[ ] All ducts must be sealed with mastic and fibrous backing tape.
Pressure-sensitive tape may be used for fibrous ducts. The HVAC
system must provide a means for balancing air and water systems.
TEMPERATURE CONTROLS:
[ ] Thermostats are required for each separate HVAC system. A manual
or automatic means to partially restrict or shut off the heating
and/or cooling input to each zone or floor shall be provided.
MAScheck COMPLIANCE REPORT
Massachusetts Energy Code I Permit #
MAScheck Software Version 2.0
Checked by/Date
CITY: Amherst
STATE: Massachusetts
HDD: 6614
CONSTRUCTION TYPE: 1 or 2 family, detached
HEATING SYSTEM TYPE: Other (Non-Electric Resistance)
DATE: 5-19-1999
DATE OF PLANS:
TITLE:
COMPLIANCE: PASSES
Required UA = 446
Your Home = 435
Area or Insul Sheath Glazing/Door
Perimeter R-Value R-Value U-Value UA
-------------------------------------------------------------------------------
CEILINGS: Raised Truss 1476 38.0 0.0 38
WALLS: Wood Frame, 24" O.C. 2222 19.0 0.0 130
GLAZING: Windows or Doors 525 0.350 184
DOORS 84 0.080 7
FLOORS: Over Unconditioned Space 1592 19.0 76
-------------------------------------------------------------------------------
COMPLIANCE STATEMENT: The proposed building design represented in these
documents is consistent with the building plans, specifications, and other
calculations submitted with the permit application. The proposed building
has been designed to meet the requirements of the Massachusetts Energy Code.
The heating load for this building, and the cooling load if appropriate
has been determined using the applicable Standard Design Conditions found
in the Code. The HVAC equipment selected to heat or cool the building
shall be no greater than 125% of the design load as specified in
sections 780CMR 1310 and J4.4. Q
Builder/Designer lJti Date l —