25A-153 (6) 5,3
4& 30 West Pomeroy Lane
Amherst, MA 01002
Phone: 413-835-5162
POWERHOUSE Email: matt.turcotte @gmail.com
Site Information
Date Of Test: 1/30/2014
Client: All Seasons Heating & Air Conditioning
Site Address: 39 - 41 Woodbine Ave
Northampton, MA 01060
Test Performed By: Matt Turcotte
Job#: DT-054
Pressurization Duct Results
Type of Test Performed: Post-Construction, total leakage (12%)
Duct System 1
Conditioned Floor Area: 1579 sq ft
Duct Flow at 25 Pa: 151 CFM
Duct Leakage: 9.56 CFM per 100 sq ft of conditioned floor area
TEST RESULT : PASS
Duct System 2 (if applicable)
Conditioned Floor Area: N/A sq ft
Duct Flow at 25 Pa: N/A CFM
Duct Leakage: N/A CFM per 100 sq ft of conditioned floor area
TEST RESULT: N/A
Notes on Area Tested and/or Testing Conditions:
119 IECC Minimum Requirements. per • 403.2.2
Mid-Construction Test, total leakage without air handler< 4 CFM per 100 sq ft of conditioned floor area
Mid-Construction Test, total leakage with air handler< 6 CFM per 100 sq ft of conditioned floor area
Post-Construction Test, leakage to the outdoors < 8 CFM per 100 sq ft of conditioned floor area
Post-Construction Test, total leakage< 12 CFM per 100 sq ft of conditioned floor area