220000_GeneralRequirements-PlumbingCOCA-COLA NORTH AMERICA JOB NO. 7588.20 ISSUED: 070910
LINE ADDITIONS
NORTHAMPTON, MASSACHUSETTS
GENERAL REQUIREMENTS - PLUMBING 220000 - 1 of 2
SECTION 220000
GENERAL REQUIREMENTS - PLUMBING
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. The other Contract Documents complement this Section.
B. Division 01 - General Requirements and Section 220000 govern all Work of
Division 22.
C. Other specification sections (Divisions 02-14, 21, and 23-26) may contain
requirements related to Division 22.
1.02 SUMMARY
A. Section provides general requirements related to all sections of Division 22.
1.03 QUALITY ASSURANCE
A. The Contractor shall employ only skilled craftsmen regularly engaged in the
appropriate trade.
B. Welding shall only be performed by welders specifically certified for each type of
welding required to be performed. All applicable welding certificates for each
certified welder shall remain on file on the project site during the duration of the
project construction. Welding certificates shall be presented upon request by Owner
or Architect/Engineer.
C. The Contractor shall be responsible for the quality of welding done by its
organization and shall repair or replace any work not in accordance with these
specifications.
1.04 DELIVERY, STORAGE, AND HANDLING
A. Delivery of all piping material and equipment as described in Division 22 specification
sections shall be to the job site in the original manufacturer's package and/or crating
with factory stamp or tag with the manufacturer's identification number along with
the owner's tag number if applicable. No piping, pipe components, or equipment
with visible rust scars will be used. Piping and pipe fittings must be received and
stored with plastic end caps in place.
COCA-COLA NORTH AMERICA JOB NO. 7588.20 ISSUED: 070910
LINE ADDITIONS
NORTHAMPTON, MASSACHUSETTS
GENERAL REQUIREMENTS - PLUMBING 220000 - 2 of 2
1.05 GMP/PROCESS AREA CLASSIFICATIONS
A. Refer to drawings for schedule of area classifications. Specific requirements for work
within classified areas are contained on the drawings and in individual specification
sections, as applicable.
PART 2 - PRODUCTS
2.01 GENERAL PRODUCT REQUIREMENTS
A. The Contractor shall obtain samples of such items as insulation and jacket systems,
factory finishes of materials, painting, piping, etc. for satisfactory review by Owner
prior to procuring.
B. Provide electrical utilization equipment that is “listed and labeled” by Underwriters
Laboratories Inc. (UL), or by an organization acceptable to the authority having
jurisdiction. For electrical utilization equipment that is not “listed,” provide
equipment that is “labeled.” Reference National Electrical Code Articles: 90.7, 100
and 110.3.
C. Provide control panels for equipment that comply with the requirements of the
National Electrical Code Article 409, Industrial Control Panels.
PART 3 - EXECUTION
3.01 EQUIPMENT INSTALLATION DETAILS
A. The Contractor shall provide for handling, setting, and alignment of all electric motors
which are delivered to the jobsite separate from equipment furnished as a part of
these specifications.
B. The Contractor shall arrange for the manufacturer to align on support frames all
motor and coupling connected compressors and pumps prior to shipment. After
installation, and prior to operation, field check alignment and correct the alignment as
required for proper operation.
C. Provide access panels in floors, walls, ceilings, partitions, etc. for access and
maintenance of valves, equipment, etc. Match access panels in appearance and
construction, to be compatible with the surrounding area. Location and style subject
to the approval of Owner. Utilize commercially manufactured frames and
doors/panels to the limit practical.
END OF SECTION