2013-04-17 - 10065 - Architect Field ReportM:\10065 - Gate House\Documents\CA\Field Reports\2013-04-17 - 10065 - Architect Field Report.docx Page 1 of 1 TIME: 11:00AM CONDITIONS: SUNNY TEMPERATURE: 60’s PRESENT: Brad Hutchison, (Kuhn Riddle Architects), John Averill (WBI), Tom Lucia (WBI) OBSERVATIONS: x Tenant fit-out framing 99% complete. x Flash coat of closed-cell spray foam applied at exterior walls x Gypsum ceiling at second floor partially installed. x Second floor ceiling vapor barrier taped and sealed to top plate. x Rough plumbing installed. x Gas piping installation under way. x Continuous 1” polyiso. concrete stem wall insulation installed and continuous sill framed. An additional 2” of polyiso. insulation will be added between framing members and the voids blown w/ dense pack cellulose. x Exterior siding and trim nearing completion. Report by: Brad Hutchison Intern Architect Kuhn Riddle Architects TO Charles Miller DATE : 04/17/13 PROJECT: GATEHOUSE cc: Jonathan Wright (WBI) PROJECT NO. 10065 Dan Dodge (Opal Development) SUBJECT: FIELD REPORT FIELD REPORT #7