2013-01-10 - 10065 - Architect Field Report-1M:\10065 - Gate House\Documents\CA\Field Reports\2013-01-10 - 10065 - Architect Field Report .docx Page 1 of 1
TIME: 10:30 PM CONDITIONS: CLEAR TEMPERATURE: 30’s
PRESENT:
Brad Hutchinson, Charles Roberts (Kuhn Riddle Architects) John Averill, Tom Lucia (WBI)
OBSERVATIONS:
x Slab poured
x Slab under restaurant not yet poured
x Steel columns erected and fastened to footings at baseplate
x Utility roughs capped at slab.
x Framers will be on site later today to start wall layout.
x Sub surface site drainage work ongoing.
x Bi-weekly job meeting scheduled commencing on site Thursday January 18th.
Report by:
Charles Roberts, AIA
Project Manager/Architect
Kuhn Riddle Architects
TO Charles Miller DATE : 01/10/13
PROJECT: GATEHOUSE
cc: Jonathan Wright, T (WBI) PROJECT NO. 10065
Dan Dodge (Opal Development) SUBJECT: FIELD REPORT
FIELD REPORT #2