2013-03-26 - 10065 - Architect Field ReportM:\10065 - Gate House\Documents\CA\Field Reports\2013-03-26 - 10065 - Architect Field Report.docx Page 1 of 1 TIME: 1:30PM CONDITIONS: PARTLY CLOUDY TEMPERATURE: 40’s PRESENT: Charles Roberts, Brad Hutchison, (Kuhn Riddle Architects), Ryan Hellwig(Ryan S. Hellwig, PE) John Averill (WBI) OBSERVATIONS: x First floor core framing complete. x North Stair framed and sheathed in gypsum board. South Stair partially completed. x Exterior window trim, pilaster trim, horizontal trim and siding under construction. x Second floor ceiling vapor barrier and gypsum sheathing under construction. x East Entrance canopy roof framed and attached to side of building. x Flash coat of closed cell foam insulation to be applied starting March 30. Report by: Brad Hutchison Intern Architect Kuhn Riddle Architects TO Charles Miller DATE : 03/26/13 PROJECT: GATEHOUSE cc: Jonathan Wright (WBI) PROJECT NO. 10065 Dan Dodge (Opal Development) SUBJECT: FIELD REPORT FIELD REPORT #6