2013-03-26 - 10065 - Architect Field ReportM:\10065 - Gate House\Documents\CA\Field Reports\2013-03-26 - 10065 - Architect Field Report.docx Page 1 of 1
TIME: 1:30PM CONDITIONS: PARTLY CLOUDY TEMPERATURE: 40’s
PRESENT:
Charles Roberts, Brad Hutchison, (Kuhn Riddle Architects), Ryan Hellwig(Ryan S. Hellwig, PE) John Averill (WBI)
OBSERVATIONS:
x First floor core framing complete.
x North Stair framed and sheathed in gypsum board. South Stair partially completed.
x Exterior window trim, pilaster trim, horizontal trim and siding under construction.
x Second floor ceiling vapor barrier and gypsum sheathing under construction.
x East Entrance canopy roof framed and attached to side of building.
x Flash coat of closed cell foam insulation to be applied starting March 30.
Report by:
Brad Hutchison
Intern Architect
Kuhn Riddle Architects
TO Charles Miller DATE : 03/26/13
PROJECT: GATEHOUSE
cc: Jonathan Wright (WBI) PROJECT NO. 10065
Dan Dodge (Opal Development) SUBJECT: FIELD REPORT
FIELD REPORT #6