2012-12-19 - 10065 - Architect Field Report (3)M:\10065 - Gate House\Documents\CA\Field Reports\2012-18 - 10065 - Architect Field Report .docx Page 1 of 1 TIME: 2:00PM CONDITIONS: OVERCAST TEMPERATURE: 40’s PRESENT: Brad Hutchinson, Charles Roberts (Kuhn Riddle Architects) John Averill (WBI) OBSERVATIONS: x Under slab insulation and reinforcing mesh being put into place under north section building. x Back fill and soil compaction on going at south end of building. x Slab haunch being poured at stair locations. x Under slab plumbing rough in is in place. x The slab is scheduled to be poured on Thursday, the 20th of December. The contractor reports that all under slab insulation will be in place by the end of the day. Report by: Charles Roberts, AIA Project Manager/Architect Kuhn Riddle Architects TO Charles Miller DATE : 12/19/12 PROJECT: GATEHOUSE cc: Jonathan Wright (WBI) PROJECT NO. 10065 Dan Dodge (Opal Development) SUBJECT: FIELD REPORT FIELD REPORT #1