32C-141 (13) Carlson&Schmitt Architects,Inc. Millbank Affordable Housing Job Meeting—July 11, 2003 Present: Joanne Campbell, Valley Community Development Corporation Patrick McCarthy, Valley Community Development Corporation Tilman Lukas, MBL Housing & Development Robert A. Desrosiers, Desrosiers & Son, Inc. Kevin Rothschild-Shea, Carlson & Schmitt Architects, Inc. Progress: • Concrete foundation walls at 100%, ready for basement slab. • Drainage structures 100%, large detention pond roughed in. 30-50 yards of concrete/bituminous rubble excavated; Desrosiers to dispose of site and price. • Rough grade at parking/roads 75% complete. Old News: • Carlson & Schmitt Architects to search files for Geotextile pricing, schedule for next change order—submitted by Desrosiers. • E.B. Holmberg submitted revised grading, layout with guardrail and attached letter addressing outstanding issues. 18 Michelman—Brick Repair at Basement • Architects/Millbank to meet with mason next Friday 9:00 a.m. to review scope. Carlson & Schmitt Architects to draft alternate vinyl shingle siding at gable end walls for pricing. 34 Michelman—Miscellaneous Site Issues • Carlson & Schmitt Architects to review parking needs; reduce one parking space if needed to allow for dumpster. • Desrosiers to price 6" reinforced concrete pad; Carlson & Schmitt Architects to size. • Fence/screen dumpster — Carlson & Schmitt to contact Hastie, review style with Millbank and specify for pricing. • Desrosiers & Son to notify Pat for temporary parking lot regarding; tenant parking restricted for at least one day for regrading. 1 South End Bridge Circle Agawam,Massachusetts W01 (413)78644 telephone (913)78661901Sax www-carloon-ach4itt.com 9/Z ' d 11I8 'QN H [9-98t iiIA OS � NOSidVO WdP:Z HE Ti ' Inl` 79 Michelman • Robert W. Hall Consulting Engineers to push on fire alarm investigation noted last meeting. Robert W. Hall to attend and invite Northampton Fire Chief to meeting on site next Friday at 10:30 a.m. General • Tilman questioned status of the construction schedule; Bob Desrosiers to revisit and update for 7/25/03 meeting. Next meeting: July 25"' at 9:00 a.m. Pencil Requisition cc: Attendees Anthony Patillo, Northampton Building Commissioner Andy Pavlica, Engineering Design Associates Derek Cavanaugh, MHIC Sandy Lake, Robert W. Hall Consulting Engineers Emily Holmberg, E.B. Holmberg &Associates Gregory Kereakaglow, E.B. Holmberg & Associates Karen Leveille, HAP, Inc. Steve Vukovich, PDSI Commercial Building Solutions 2 9/E 'd 1118 *0N 0x19-98( 11[WMS '8 NOSIdVD iNd6tl E00Z ' W inr N July 10,2003 Mr. Patrick McCarthy Valley Corn wnity Development Center Market Street Northampton,MA 01060 RE- Millbank Affordable Housing Dear Mr. McCarthy: This letter is to answer the three concerns that have recently been brought to our attention concerning the above referenced project. Also enclosed with this letter is a revised Site Layout Plan(Sheet L-2)showing the location of the recommended wood guard rail.along with Construction Details—3A(Wood Guard Rail Detail). 1. The rip rap stability during transfer of water between the 2 lobes of the detention basins through the narrow channel is adequate. The 1"to 4 " rip zap stone is sufficient. The water enters the basins from 2 different locations and the connecting channel between the 2 lobes isn't taking a full 100 year storm through it. The connecting channel is only to equalize flow. 2. A guard rail in the area directly to the west of 79 Michelman Ave along the outside radius of the road is recommended idea since there is a 3 foot drop and there is a vault there at the bend. The guard rail shall extend around the outside radius for approximately 60 linear feet. A Wooden Guard rail would be sufficient here. Mass highway guard rail(galvanized)is not recommended since the aesthetics are an issue and a wooden guard rail is sufficient for traffic safety in this location 3. Ponding at the vault shouldn't be a problem since the grading there is shedding water toward the back. Just make sure the contractor grades it back as shown. A spot grade of 117.5 can be held at approximately the northwest corner of 79 Michelman Ave and graded back around the building toward the transformer to the existing 117 contour. The contractor only 87 Union Street Easthampton,,Massachusetts 01027-0945 Telephone: ("413)529-1700 Facslmtle: (413)529-2237 e-mail:ebha@ebholmberg.com 9/t A 1118 'ON 0£ 19-98L iiIAHOS ' NOSIdVD k6bl CON I[ nr July 10,2003 VAey MWbank PartuenNp Page 2 of 2 needs to "crack a bubble" so that water will be shed off from the area. The area can be sloped from the 117.5 spot grade toward the transformer and the backside of 79 M.ichelman. If you have any other questions, feel free to contact Emily at 413-529-1700. Very truly yours, E. B. Ho &Associates Gre oglow,PE Emily B. Holmberg,PLS E. B. Holmberg &Associates Laud Surveyors 91i9 'd 1118 *ON QE19-98L 11fWS � NOSIdU k6tl HOZ - 11 - 1nr Desrosiers & Son, Inc. General Contractors 32 Champion Drive Chicopee, Massachusetts 01020-2826 (413) 593-5451 Fax(413)593-3335 May 21, 2003 Carlson & Schmitt Architects, Inc. Attn: Kevin I So. End Bridge Circle Agawam MA 01001 Re: Millbank Affordable Housing Dear Kevin: we are concerned with the discharge area of the south end catch basing. During a heavy rain the water will discharge into a narrow grass covered trench instead of a larger pond. This could cause erosion and and the .bank to collapse. I realize that there is Rip Rep to be installed at the outlet, but I am still concerned that there might be problems on a heavy rain. Could you check on this and let us know if our concerns are justified. Thank you, Robert A. Desrosiers RAD/rtm J 9/9 'd 11118 aN OOE19-981 IiMHOS NOSIHNO ndk6t E OEM Carlson&Schmitt Architects,Inc. FAX COVER SHEET TO: Joanne Campbell, Valley CDC (413) 586-7521 Patrick McCarthy, Valley CDC (413) 586-7521 Tilman Lukas, MBL Housing& Development (413) 747-8515 Karen Leveille, HAP, Inc. (413) 731-8723 Bob Desrosiers, Desrosiers & Son, Inc. (413) 593-3335 Steve Vukovich, PDS1 (413) 587-0031 Derek Cavanaugh, MHIC (617) 850-1106 Anthony Patillo, Northampton Bldg. Com. (413) 587-1272 Andy Pavlica, Engineering Design Associates (413) 788-0967 Emily Holmberg, E.B. Holmberg& Associates (413) 529-2237 Gregory Kereakaglow, E.B. Holmberg & Assoc (413) 529-2237 Sandy Lake, Robert W. Hall Consulting Eng. (413) 789-3295 FROM: Kevin Rothschild-Shea RE: Millbank Affordable Housing Job Meeting — 07/11/03 DATE: July 11, 2003 Pages: 6 1 South End Bhd8v 0m&- Agawam,Ma"och"wts 01001 (413)786.5556 tatephone (413)7864130fa: www.carba,"chmitt.com 9/1 d 1118'ON H19-98L llINKS I NOS1dU IUP E E00Z ' 11 ' Inr DIETZ&COMPANY ARCHITECTS,INC. To the best of my knowledge and belief, these meeting notes are considered to be a true and accurate record of all items discussed. The undersigned shall be notified, in writing, within ten days of the date below, of any corrections or additions; otherwise,these minutes shall be considered accepted as written. Respectfully submitted: DIETZ&COMPANY ARCHITECTS,INC. John H.Anderson ALA,CCS,CCCA July 23,2003 copies: emalled: Jon Hite,NHA Russ Gauthier,BCI Construction,Inc Dave Gour,NHA (by Jon Hite) Kerry Dietz,Dietz b Company Architects Tom Barthelette,DHCD Tom Baker,ICI Engineering Anthony Patillo,Northampton Building Commissioner Jim Scott,Envirosclence (also hard copy mailed). File r.\19848.hamphts108-construction adm1n\mtgnotes1072203mn2 Woc Page 3 of 3 DIETZ&COMPANY ARCHITECTS,INC. 14.3 5120/2003 -Additional Liv Rm/DR Flooring: Roy reports that BCI is proceeding with additional VCT flooring and plywood underlayment,per Owner's verbal instruction. [older items removed-see previous minutes] 6/17/2003 - Discussed unchanged floor unit prices #2 b #3. Dave will review which Phase II units might need additional flooring. Jon will review with Tom and DHCD. 7/112003-Dave has checked bldgs#7, 11,5 and 3: new IN rm floors needed at units#7A,7C, I I B, I I C. DbCo will include as part of CO#008. 7/8/2003-May be additional floors needed at remaining buildings. 7/22/2003- Roy believes some IN rms in bldg#6 may need complete flooring and underlayment. Dave will review when he returns from vacation next week. Item Ongoing. 20.1 7/8/2003—Plaster Patching. Roy has been recording actual SF patching on Phase I. He will contact sub-contractor to verify quantities to date and obtain unit prices for next Phase. 7/22/2003-DbCo received FAX dated July 15th from BCI reporting that they will be preparing unit prices. Jon understands that some extra existing areas in Phase 11 are currently being patched; Roy is recording quantities. Roy will contact Albany office to expedite unit prices. Item Ongoing. 20.2 7/8/2003—Phase I Door Replacement Roy reported that at some Phase I units basement door has been switched with a bedroom door-to compensate for existing door undercutting. Roy will provide revised list of new door locations for Dave's review. 7/2212003-Item Ongoing. 20.3 7/8/2003 — Bldg Numbers: Roy has numbers and letters on hand and will mount sample for Dave's approval. Screws required for mounting. BCI will submit credit for rear door numbers deleted. 7/2212003-Item Ongoing. 20.4 7/8/2003—Bldg Dept Sign Off: BCI to submit copies of individual permit sign off on each building as occupied. 7/22/2003- Bldg#17 final sign off not yet received by NHA. Roy believes that Dave has copies of all other Phase I sign offs. Item Ongoing. 21.1 7/2212003—Door Patching. Roy requested bldg#7 door patching by NHA so that painter can continue. Jon will check status. Item Ongoing. 21.2 7/22/2003—Additional Asbestos Abatement Additional ductwork asbestos has been uncovered at all units at bldg#6 and 2 units at bldg#5. Jon or Dave has signed off on additional unit price work. Item Ongoing. 21.3 7/22/2003—Mold: Discussed status of mold testing. Roy reports no areas of visible mold in Phase II bldgs. Item Closed. 21.4 7/22/2003—Next Meeting. Job meeting will be held next week. Following week,August 5th, anticipated that there will be no job meeting Roy and John will each be on vacation that week. Item Closed. SUMMARY OF ACTIONS REQUIRED: Dietz&Company Architects: • BCI Construction: • Plaster prices item 20.1 • Door list item 20.2 • Numbers credit item 20.3 • Bldg Dept sign off item 20.4 Northampton Housing Authority: • Review schedule • Door patching item 21.1 Next meeting will be held at 9:30 am Tuesday,July 29th,2003 at Hampshire Heights Field Office. Page 2 of 3 DIETZ V COMPANY ARCHITECTS,INC. 3 d "�/ qe 17 Hampden Street Springfleld MA 01 103 (413) 733-6798 Fax(413) 732-4385 v MEETING NOTES - .., (` c DATE: Tuesday,July 22,2003 PROJECT kill G NO.21 PROJECT- Northampton Housing Authority l: , J 3 Hampshire Heights Apartments _..__._..1 Kitchen and Bath Renovations ��Ri 1)11< , DHCD Project#214032 Project No: 19848 LOCATION: Hampshire Heights Apartments,BCI Field Office,adjacent to bldg#1,Northampton,MA,9:30 a.m. PRESENT: Jon Hite,Executive Director,NHA Daye Gown,Pr-ejeee Representateye,NH.A. Mike Benson,Pr-esident;13G'GeRswumuen Tom Barthelette,Construction Coordinator,DHCD Roy Fairlee,Project Superintendent,BCI Const. John Anderson,Dietz b Company Architects , • ("{.--1:e Ruges- M L Sehmiee LI_- -end AL FApeei g WEATHER: 80's,overcast Progress as reported by Contractor. Demolition complete in bldg#6,started in bldg#14. Asbestos abatement complete in bldg #6, including ductwork abatement at all 4 units. Electrical and plumbing rough in complete at bldgs#5 b 11; started in bldg#3• HVAC rough in complete at bldg#3;started at bldg#6. Insulation complete at bldg#5 & 11. GWB board complete at bldg#7 b 11;started at bldg#5. GWB taping complete at bldg#7;working on bldg#11. Painting starting at bldg#7. 1.6 1/21/2003—Schedule: BCI intends to set up field office next week and start submittals. Russ will submit progress schedule next week for review. [older items removed-see previous minutes] 7/8/2003 - BCI has submitted revised schedules for bldgs 7, 11, 3, 5, 6, and 16. NHA will review for dates of turn over procedure. [Revised schedule shows start of 30 day moving notice period as follows: Bldg#7-Aug 11; #1 1-Aug 18; #3-Aug 27; #5-Sept 4; #6-Sept 12; #1 6-Sept 23]. 7/22/2003-Reviewed progress. Roy reports that BCI is generally 2 to 3 days behind latest revised schedule for bldgs#7 b 11. Bldg#3 currently on schedule. Current problem is that excessively humid weather delays drying of finishing compound. Jon emphasized that there is not enough time in the revised schedule for NHA turnover procedures. Item Ongoing. 10.2 4/15/2003 - Change Orders: Reviewed status of all change orders. Some items to be revised slightly as discussed. Door repairs: patch door and frame, not needed. Patch floor at closets: use floor I unit price. Register build out price revised without caulking nail holes. Russ will review floor patching price at 17A bedroom, using Ardex. DbCo will prepare paperwork for Owner's signature. [older items removed-see previous minutes] 7/8 12003-Discussed summary list [Post meeting note: BCI has faxed remaining paperwork. DbCo will prepare CO#008]. 7/22/2003-NHA board has approved change order 008 and copies will be sent to Boston tomorrow. Item Ongoing. 12.1 5/6/2003 - Punch List Discussed punch list procedures for first two buildings. Roy will request punch list when all city inspections have been received, including building occupancy certificates. Floor washing and waxing and final cleaning will be done after punch list. Russ anticipates completing punch list items in 2 days. Jon reports he will need 2 days for housing authority work,lock changeover,and moving in tenants;may need more than 2 days for other buildings. [older items removed-see previous minutes] 6/17/2003-Dave has completed punch lists for bldgs#10& 12A b B(6112). Building Department sign off not yet received. 7/1/2003 - Bldg#12D being typed up. Two apartments in bldg#15 still to do. Jon reports that units#I C,813 and 12A are currently vacant 7/8/2003-Dave handed out lists for remaining units at bldgs#12 b 15. Units#86, 17C, 17D first floor being typed. 7/2212003 - Roy reports that BCI has completed punch list items for Phase I with exception of some flooring and electrical items. Dave will provide summary checklist of still outstanding counter and cabinet door replacements when he returns. Item Ongoing. Page I of 3