32C-141 (2) Carlson&SchniiitArchftects,Inc.
FAX COVER SHEET
TO: Joanne Campbell, Valley CDC (413) 586-7521
Patrick McCafthy, Valley CDC (413) 586-7521
T*T=Lukas,-MBL Housing & Development (413) 747-8515
Bob Desrosiers, Desrosiers & Son, Inc. (413) 593-3335
Mike Talbot,O'Reilly Talbot& Okun (413) 788-8830
E.B. Holmberg &Associates (413) 529-2237
Steve Vukovich (413)587-0031
Anthony Patillo, Northampton Bldg. Com. (413) 587-1272
Engineering Design Associates (413) 788-0967
FROM: Kevin Rethschild-Shea
RE: Wlba-nk Affordable Housing
Job Meeting — 12/19/02
DATE: December 20, 2002 PAGES: 3
1 South End Bridge Qmle Agoworn,MoaeachuieW 01001 (413)7863556 telephone (413)786-6130 fax www.cadjon-echmitt.00m
09'0N 0£19 98L llli�H�S NOSla'd0 UH :'l ZOE .0�to
CS \
request. Desrosiers & Son to submit cost of work proposed by the Water
Department.
• Robert W. Hall Consulting Engineers to provide direction for 79 Michelman
additional fire alarm requirements.
• General Contractor to maintain winter protection precautions during all
cold weather construction.
• Shop drawings — Engineering Design Associates to forward pile shops to
O'Reilly Talbot & Okun for review ASAP.
Next meeting is Thursday, January 9, 2003 at 9:00 a.m.
M. Attendees
E.B. Holmberg &Associates
Steve Vukovich, PM Commercial Building Solutions
Anthony Patillo, Northampton Building Commissioner
Engineering Design Associates
2
E/E -d E6`09 '0N OE19-98L 111WH�S NOSIda� 4Vd6c l EOOZ OE �eQ
Carlson&Schmitt Architects,inc. ...._
Millbank Affordable Housing
Job Meeting #1
December 19, 2002
Present* Joanne Campbell, Valley Community Development Corporation
Patrick McCarthy,Vafley Community Development Corporation
Tilman Lukas, MBL Housing & Development
Robert A. Desrosiers, Desrosiers& Son, Inc.
Robert A. Desrosiers, Jr., Desrosiers & Son, Inc.
Mike Talbot, O'Reilly Talbot &Okun Associates
Kevin Rothschild-Shea, Carlson & Schmitt Architects, Inc.
Progress:
• Silt fence installed and approved.
Tree removal complete; stump removal underway.
• Small parking lot excavated;gravel instaflation underway.
• Excess fill/gravel moving off site.
General Notes:
• Job meetings: Thursday 9:00 a.m.
• Pencil requisition to be submitted last Thursday of each month.
• Tilman to email Architect's Requisition Certificate to Carlson & Schmitt
Architects.
• Mike Talbot to copy Environmental Report to Desrosiers & Son.
New Items:
• Poor soils (ash, dumping, etc.) to be stockpiled on site; O'Reilly Talbot &
Okun to review and coordinate with backfill.
• Carlson & Schmitt and Engineering Design Associates to review screw
pile inspection attendance.
• Drainage structure and associated PVC pipe discovered at small parking
area. Desrosiers to-submit disposal costs.
• Water Department indicates shutdown for tie-in cannot be scheduled until
spring. Partial loop affected by shutdown consists primarily of Millbank
residents. Joanne to contact the Water Department for possible
allowance to complete the tie-in in January. faitum to relocate the water
main will restrict excavation and pile installation for 34 Michelman.
• Water Department is requesting additional shutoff; Kevin Rothschild-Shea
has reviewed with E.B. Holmberg and they have no knowledge of the
1 South End Bridge Circle Agawam,hlassoeh"nM 01001 (418)786,5656 telephone (413)786-6130faz www.curtsonac*itt.com