08-021 (18) City of Northampton May 22, 2003 Page 2 2 . Installation of under slab rough in plumbing has now begun on the interior of the new building area and is approximately 50% complete. 3 . The Butler preengineered metal building system has not yet been delivered to the job site. 4 . Installation of corrugated plastic below grade storm drainage piping has now begun along the western line of the site at the base of the embankment. Ground water was observed at approximately the elevation of the bottom of pipe. Additional miscellaneous storm drainage plastic piping materials have now been delivered to the job site and installation is continuing. No other site utility installation has begun at this time. Please let me know if you have any questions or comments. Sincerely, f , le AM � do Gerald P. Berson, P.E. 6(7 ed T H E 111111111111111111111111111111111111111 ENGINEERING /1/4 O'LEARY CQNSTR CTIQN !IIIII11111111COM PAN Y SINCE 1955 May 22, 2003 City of Northampton It Department of Building Inspections 212 Main Street MAY 2 7 non Northampton, MA 01060 RE: New Building for Paradise Realty Partners 766 North King Street, Northampton, MA Construction Report No. 2 Gentlemen: Since my last report on May 5, 2003, the following construction has been completed and except as noted found to be in compliance with applicable codes and construction documents for this project : 1 . As previously reported, all site clearing and rough grading for the new building and parking lot area has been completed. Excavation and grading of the embankment at the rear of the site is also nearly complete at this time. At the northwest corner of the site, a method of stabilization for the embankment is being designed due to the slope of the embankment . It is my understanding that the site engineer is evaluating various stabilization methods . All reinforced concrete footings, foundation walls and column piers for the new building have now been poured and backfilled approximately up to grade. Styrofoam insulation has been placed on the interior side of all exposed perimeter foundation walls prior co backfill. All anchor bolts appear to be properly placed at column piers in preparation for structural steel erection. On the interior of the new building, the concrete base and a portion of the perimeter foundation walls for the elevator shaft have also now been poured. The site foreman has verified that all bottom of footing areas where clay material was encountered were undercut and a minimum of 6" gravel fill was installed and compacted up to bottom of footing level . It is anticipated that all reinforced concrete foundation work for the new building will be completed within the next week. No portions of the interior reinforced concrete slab on grade have been poured at this time. THE O'LEARY COMPANY, INC. <BUTLER> MAIL ADDRESS: P.O. BOX 377, SOUTHAMPTON, MA 01073 0377 OFFICE ADDRESS: 376 COLLEGE HIGHWAY, ROUTE 10, SOUTHAMPTON, MA 01073 BUILDER TELEPHONE 413 527-1360 FAX 413 527-2499 WEB SITE www.olearyco.com