31B-244 5.6 6/18/09 Gas Meter Location - Charlie to meet with the gas company about the possible relocation of the gas meter as Frank is concerned. 6/25/09 7/2/09 no update. Frank still working on it. 6.3 6/25/09 Powder coat on ext. railing. Peter would like a price on getting the ext. railing powder coated black vs. field painting. Owen to price the deduct. RBz to get the pricing from Accufab 7/2/09 Accufab planned for finish. Deduct coming from Owen. 7.10 7/2/09 New Stair - Per Peter, outside stringers and back channels to be 12" instead of 10 ". Peter discussed w /Jeff at Accufab. WB to confirm layout wall to wall including offset for brick. Next Construction Mtg: Thursday, July 9th Walk thru at 9:00 followed by the Job Mtg at 10:00 at Park House Room 101 The above is intended to be a record of meeting items. Please inform the writer of errors or omissions. 6/11/09 CO #1 is complete and will be included in June Pay Req. Revised CO Log distributed and reviewed. RBz working on pricing. Peter asked if there was any cost implications for closet move? Roger thought not, except maybe some cost from HFP? 6/18/09 Revised CO Log distributed and reviewed. All approved COP items to be incorporated into CO #2 and pencil req next wk. 6/25/09 Revised CO Log was distributed and reviewed. Pencil req to be sent out today or tomorrow. Peter and Charlie requested an update on the creep of scope on the plaster repair and additional framing work and materials. RBz to give an idea of the magnitude of it next week along with a weekly update. PL & Charlie would like to know for next week from the major subs of any anticipated changes. 7/2/09 Per RBz, Brian Johnson to do drywall. RBz to forward costs for CO items prior to next mtg. 1.11 5/21/09 Interior finishes - Peter discussed finishes w/Becky & Linda LaFlam. They confirmed all the wdw treatments in Liv Rrn are changing. Peter showed them preliminary carpet and vet color selections. WB to get a larger pc of carpet sample, color: "The Capital" (blue) and also the carpet submittals for the Corridor carpet. 5/28/09 Doug Mercier brought larger blue room carpet sample and 2 corridor carpet samples to the mtg. Charlie to bring them to Linda LaFlam for approval. Peter to complete color schedule after mtg w/Linda & Becky. Doug to resubmit on stair rubber material. 6/4/09 Doug resubmitted stair rubber. Peter is scheduled to meet w/Becky on Thurs, 611, after the job mtg. 6/11/09 Peter reviewing color /finishes w/Becky today. 6/11/09 Post mtg: Peter emailed Color Schedule. Paint colors to follow. Item closed. 6/18/09 Brett gave Peter samples of upholstery. Peter to get together with Becky to put together the paint schedule. 6/25/09 Paint schedule pending.Charlie requested pricing on additional sheers for the lvng rm using Haven house specs. RBz to work on the pricing to be tracked on the CO log. 7/2/09 Peter & Becky to meet. Charlie to look at spec for sheer supplier /manuf. 7/2/09 Charlie emailed sheer info to WB. 4.11 6/11/09 Submittals - some remaining still to be submitted: Steel reinforcement & conc mix at ramp Railing shop drwgs Acoustical ceiling tile Westek shop drwgs 6/18/09 some remaining still to be submitted. Acoustical ceiling tile Westek shop drwgs- per PL samples were dropped off to him by Westek but still no shop drawings. 6/25/09 Steel reinforcement & conc mix at ramp still to be submitted. 7/2/09 Ramp steel reinforcement & conc mix submitted today. SC paying for testing but Chet/WB to call Allied for testing of figs & walls. 7/2/09 Peter called WB w /approved as noted items on steel reinforcement drwgs. LG relayed nec changes to Barker Steel. 6/25/09 Ted to look at this and get the information to Peter. 7/2/09 Per Ted, light has been changed. No cost change. Item closed. 5.4 6/18/09 Moving of Conduit in trunk space discussions during the site walk through about moving the layout of the partition of the trunk space. Which would require removing the gas line that is intended for the laundry and then moving of the conduit that runs above this pipe. That is determined to be grounding. Charlie, Dino & Peter to look at the moving of it next week when Ted is here. 7/2/09 Charlie to talk to Bay State Gas for status. Meter to be moved outside. Peter said not moving grounding conduit. Grounding water services etc is approved. NE to do. 7.8 7/2/09 Color of devices & wall plates? - Per Peter, Baths are ivory w/brushed ss covers. New Student Rms - ivory. If replacing on brown basebd, plates to be brown. In Liv Rm & Front Entry on any brown woodwork, plates to be brown. Item closed. 7.9 7/2/09 Inverter of emergency power (on battery, no generator here) - Peter requested NE pick a location for inverter that can be enlcosed if Dino confirms it needs to be. ARCHITECTURAL P1.12 4/16/09 Structural site visit - See 6/4/09 & 6/25/09 minutes for history. 7/2/09 Roof structural pricing coming. P2.5 4/23/09 Masonry recon mission - See 6/4/09 minutes for history. 6/11/09 Peter reviewed w/Paul use of stainless strap anchors at roof/brick work and ss pins set in epoxy for cap stone. RBz to talk w/Paul about stone sample. 6/18/09 RBz to touch base w/ Paul again about the stone sample. 6/25/09 RBz to see Paul tomorrow. Hoping to have him back next week. 7/2/09 Paul ordered 4 pcs. ETA next week. If PL & CC think not a good color match, Paul will either re -order pcs or stain them for closer match. P3.5 4/30/09 Windows - see 5/28/09 & 6/25/09 minutes for history. 7/2/09 Peter & RBz rec'd sk on storm wdw system from Robin and discussed at mtg. Peter requested WB add a wood stop and attach the screen to the wood stop. Peter will review w /Chet. Windows to be delivered to site on 7/8/09. P4.5 5/7/09 Rich K concerns - See 5/7/09 & 6/25/09 minutes for history. 6/25/09 Found new hot spot on first floor in 102 and 100LA and is being abated now. Window removal to start 7/6. 7/2/09 Abatement in 102 and 100LA is done. BNB letter still pending. P5.9 5/14/09 CO Log - Revised CO Log distributed today. RBz to have to have pricing on open items by next job mtg. 5/21/09 - 5/28/09 Not discussed. 6/4/09 Revised CO Log was distributed and reviewed. Peter to prep CO #1 to include COP# 1- 5 & 7 to be included on June Pay Req. • 5.1 6/18/09- 3rd floor Mechanical room layou t- Chet and TJC had questions on layout of controls and the fan placement. Peter asked if a layout of the room is needed. All parties agreed. Dino to meet with Jay(SC) and Tom(TJC) 6/19/09 at 9 am onsite for coordination and to determine layout. Charlie to confirm meeting via email with Dino. 6/25/09 Layout to be done this afternoon. Item closed. 7/2/09 Work still needs to be done. Marvin to coordinate. 6.1 6/25/09 Marvin requested that the sprinkler air compressor be moved sooner than later so that work can continue to progress. Chet to address. Item Closed. 7.1 7/2/09 Sprinkler drwgs - need to be emailed asap to TJC for coordination. 7.2 7/2/09 Air handling unit - confitiued to be on concrete pad. Chet and TJC to coordinate. Item closed. 7.3 7/2/09 Radiators /chases - Chet requested radiator placement approval, one radiator size change to be confirmed and review of chases (location & size). 7.4 7/2/09 Utility Monitoring Meters - does SC want it or not? Charlie says yes. Marvin to relay to Yankee Tech. Jen/SC providing meters & TJC /YT to do install. Marvin to review w /Jen after mtg. Charlie requested deduct on conduit runs. Marvin to check on it. 7.5 7/2/09 New water meter - Charlie to talk w/Frank about request for new water meter. SPRINKLERS P2.1 4/23/09 Coverage - see 6/4/09 minutes for history. 6/4/09 Dino has forwarded drwgs & FPN to insurance provider. Two new heads are required. Dino will consolidate 2 new heads & other sprinkler changes and forward directive tomorrow, 6/5. 6/11/09 Dino relayed 2 new required heads to HFP, along w /other minor modifications at walk thru. HFP to revise drwgs and forward to Dion asap. 6/18/09 Dino talked to the office they should have the shop fabrication drawings by next week. 6/25/09 RBz to talk to Dino later today. 7/2/09 Neither Dino nor Chris /HFP were at mtg. Shop drwg status? 7.6 7/2/09 Mtg attendance - Chris/HFP to come to job mtgs. Item closed. 7.7 7/2/09 Daily safety procedure - Chet to call in daily to SC safety office 585 -2490. No longer nec to turn in slips. Item closed. ELECTRICAL 5.3 6/18/09 Light in corridor outside 313 - Peter wanted the ceiling light fixture to be smaller to match the rest of the fixtures. Dino to talk to Ted about changing it from a 21" fixture to a 14" one. R • Wright Builders, Inc. 48 Bates Street Northampton, MA 01060 Tel: 413 -586 -8287 Fax: 413 -587 -9276 Park House Renovation Meeting Minutes Date: 7/2/09 Re: Park House Renovation, Smith College Construction Meeting #7 - 7/2/09 To: Attendees - via email Present: Charlie Conant, Becky Shaw - Smith College (SC) Peter Lapointe - Archimetrics Design Studio (ADS) Roger Buzzell, Chet Mitchell, Linda Gaudreau - Wright Builders, Inc. (WB) Marvin Blakley - TJ Conway (TJC) Ted Forcier- Northup Electric (NE) Cc: Tony Patillo - Northampton Building Commissioner Ryan Hellwig - (RH) Chris Zurheide - HFP Sprinkler Contracting (HFP) Robin Sheldon - R &R Window Contractors (R &R) Jeff - Accufab Ironworks Fred Pazmino - Titan Roofing Doug Mercier - Mercier Carpet (MC) Mark Ledwell, Ann Ledwell - Wright Builders, Inc. (WB) Dino D'Angelo - Lindgren & Sharples (L &S) By: Linda Gaudreau - Wright Builders, Inc. Work Progress: Working towards rough inspections Framing to be complete by 7/6 Insulators & drywall scheduled for next week pending plumbing/electrical rough inspections Rainy weather slowing down progress on roofing and removal of scaffolding The following items were discussed: Mt a. Item MECHANICAL P1.6 4/16/09 Solar panel - See 6/25/09 minutes for history 7/2/09 Roger to forward pricing for roof structural pc on Mon, 7/6. Work to start soon after. Marvin to check on riser scope in contract/addendum and get temperature controls started in walls. WRIGHT BUILDERS, INC. - -,M44M OCR 4 QIMH 48 Bates Street NORTHAMPTON, MA 01060 2 /73 0244(( (413) 586 -8287 I DATE / /( 6 /6 9 JOB NO. 0 9f_ 9/6 0/1. FAX (413) 587 -9276 ATTENTION � �� TO 1 �. JA l0 RE. S // /1 69 (t // 'e ., ...._ Pal k HO C-e A;! -� �n ti / IU WE ARE SENDING YOU Attached ❑ Under separate cover via the following items: > ❑ Shop drawings ❑ Prints ❑ Plans Samples ❑ Specifications ❑ Copy of letter ❑ Change order 141 J - , // M / /1 0 / ± 2 COPIES DATE NO. DESCRIPTION in �q * /�i/I Ufe O �7 - 7 � � / 0 ) v THESE ARE TRANSMITTED as checked below: ❑ For approval ❑ Approved as submitted ❑ Resubmit copies for approval your use X'or ❑ Approved as noted ❑ Submit copies for distribution ❑ As requested ❑ Returned for corrections ❑ Return corrected prints > ❑ For review and comment ❑ ❑ FOR BIDS DUE ❑ PRINTS RETURNED AFTER LOAN TO US REMARKS COPY TO / SIGNED: : . (—. L_ 4 _4 If enclosures are not as noted, kindly notify us at once. 5/28/09 Doug Mercier brought larger blue room carpet sample and 2 corridor carpet samples to the mtg. Charlie to bring them to Linda LaFlam for approval. Peter to complete color schedule after mtg w/Linda & Becky. Doug to resubmit on stair rubber material. 6/4/09 Doug resubmitted stair rubber. Peter is scheduled to meet w/Becky on Thurs, 611, after the job mtg. 6/11/09 Peter reviewing color /finishes wBecky today. 6/11/09 Post mtg: Peter emailed Color Schedule. Paint colors to follow. Item closed. 6/18/09 Brett gave Peter samples of upholstery. Peter to get together with Becky to put together the paint schedule. 6/25/09 Paint schedule pending.Charlie requested pricing on additional sheers for the lvng rm using Haven house specs. RBz to work on the pricing to be tracked on the CO log. 4.7 6/11/09 Chimney cap - Charlie requested price to cap front chimney w /copper. 6/18/09 Fred onsite today. Peter to do a PR 6/25/09 RBz to email today also has pricing for siding from Monty. Item Closed. 4.10 6/11/09- 6/18/09 Roller shade resubmittal - distributed. Discussed request by SC for heavier duty spring on large window sizes. Peter to review. 6/25/09 Peter has them to be sent out today. Item Closed. 4.11 6/11/09 Submittals - some remaining still to be submitted: Steel reinforcement & conc mix at ramp Railing shop drwgs Acoustical ceiling tile Westek shop drwgs 6/18/09 some remaining still to be submitted. Acoustical ceiling tile Westek shop drwgs- per PL samples were dropped off to him by Westek but still no shop drawings. 6/25/09 Steel reinforcement & conc mix at ramp still to be submitted. 5.6 6/18/09- Gas Meter Location - Charlie to meet with the gas company about the possible relocation of the gas meter as Frank is concerned. 6/25/09 no update. Frank still working on it. 6.3 6/25/09 Powder coat on ext. railing. Peter would like a price on getting the ext. railing powder coated black vs. field painting. Owen to price the deduct. RBz to get the pricing from Accufab 6.4 6/25/09 Floor in 200P- Per Charlie, Dion to do T &M for sand and seal in 200P and to track in the c. o. log. Item Closed. Next Construction Mtg: Thursday, July 2nd Walk thru at 8:30 followed by the Job Mtg at 9:00 at Park House Room 101 The above is intended to be a record of meeting items. Please inform the writer of errors or omissions. 6/18/09 Post Mtg: Robin called RBz the eagle windows are to arrive in CT on 7/6/09 and to be delivered to Park House on 7/8/09 6/25/09 Removal of windows to start on 7/6 the install to begin on 7/8. Owen agreed to paint after new windows are in he will tape them off as long as he does not have to wash the windows.A11 agreed. Robin will be forwarding a sketch of the storm window system to RBz and Peter today. P4.5 5/7/09 Rich K concerns - See 5/7/09 minutes for history. 5/14/09 - 5/28/09 Only remaining open items: Charlie to mark up elevations of wdws to be abated and forward it to Rich K & WB. Titan to provide letter stating that roofing went to "peimanent solid waste landfill ". 5/28/09 Post mtg: BNB will provide letter of harzardous roofing to 'permanent solid waste landfill". 6/4/09 Charlie to scan & email mark up elevations of wdws to WB. BNB still to provide letter. Lower level Bath floor has been abated once. Does floor underneath also need abatement? Charlie to check w/Rich K. Lower level Hall - remove existing tile? Or go over w /carpet? WB to ask Doug Mercier. 6/11/09 BNB letter pending. Lower level Bath floor determined to still be "hot" and was abated. WB spoke w/Doug Mercier and carpet will be installed over lino in Lower level Hall. 6/18/09 Charlie to tell Rich it is looking like starting around 7/6- 7/13th. Roger to email and confirm dates by tomorrow. BNB letter still pending. 6/18/09 Post Meeting: Window installation beginning 7/8. Window removal starts 7/6 -7 6/25/09 Found new hot spot on first floor in 102 and 100LA and is being abated now. Window removal to start 7/6. P5.9 5/14/09 CO Log - Revised CO Log distributed today. RBz to have to have pricing on open items by next job mtg. 5/21/09- 5/28/09 Not discussed. 6/4/09 Revised CO Log was distributed and reviewed. Peter to prep CO #1 to include COP# 1- 5 & 7 to be included on June Pay Req. 6/11/09 CO #1 is complete and will be included in June Pay Req. Revised CO Log distributed and reviewed. RBz working on pricing. Peter asked if there was any cost implications for closet move? Roger thought not, except maybe some cost from HFP? 6/18/09 Revised CO Log distributed and reviewed. All approved COP items to be incorporated into CO #2 and pencil req next wk. 6/25/09 Revised CO Log was distributed and reviewed. Pencil req to be sent out today or tomorrow. Peter and Charlie requested an update on the creep of scope on the plaster repair and additional framing work and materials. RBz to give an idea of the magnitude of it next week along with a weekly update. PL & Charlie would like to know for next week from the major subs of any anticipated changes. 1.11 5/21/09 Interior finishes - Peter discussed finishes w/Becky & Linda LaFlam. They confirmed all the wdw treatments in Liv Rm are changing. Peter showed them preliminary carpet and vct color selections. WB to get a larger pc of carpet sample, color: "The Capital" (blue) and also the carpet submittals for the Corridor carpet. 6/25/09 Ted to look at this and get the information to Peter. 5.4 6/18/09 Moving of Conduit in trunk space- discussions during the site walk through about moving the layout of the partition of the trunk space. Which would require removing the gas line that is intended for the laundry and then moving of the conduit that runs above this pipe. That is determined to be grounding. Charlie, Dino & Peter to look at the moving of it next week when Ted is here. 6.2 6/25/09 Moving of electrical storage- Chet requested that NE temp. storage be moved to the 3rd floor. Agreed. Item Closed. ARCHITECTURAL P1.12 4/16/09 Structural site visit - See 6/4/09 minutes for history. 6/11/09 Ryan on site today. Structural items: 1. Peter will give directive for wall under steel beam 2. Ryan will issue SK for reinforcement of steel beam 3. Ryan will issue SK for reframing of 1st Fir stair opening 4. Roger Bz said layout of Bath toilets land right on joists. Carpenter to header off. Peter said to use salvaged existing framing to match dimensions. 5. Roof - structural changes - to stiffen roof for snow & solar panel load. 6/18/09 PR #5 was issued today by PL. PL mentioned the logistics on how to get the 22ft LVL into the roof. CM and RBz to work it out. RBz to get together with Monty and forward pricing for PR #5. Peter will issue another PR off Chet's list. 6/25/09 Ryan to talk to Accufab about cutting the steel beam or diverting around it. Per Chet - the footing is in going to drill holes and epoxy anchors. P2.5 4/23/09 Masonry recon mission - See 6/4/09 minutes for history. 6/11/09 Peter reviewed w/Paul use of stainless strap anchors at roof/brick work and ss pins set in epoxy for cap stone. RBz to talk w /Paul about stone sample. 6/18/09 RBz to touch base w/ Paul again about the stone sample. 6/25/09 RBz to see Paul tomorrow. Hoping to have him back next week. P3.5 4/30/09 Windows - see 5/28/09 minutes for history. 6/4/09 Peter reminded that brickmould to remain w /new caulking at dormers w /arch top wdws scheduled for new wood sash into openings. Peter requested confirmation that middle of arch top DH & top of 1/2 screens align. 6/11/09 Per Roger, Robin/R &R confirmed alignment of meeting rail of arch top DH. Charlie asked about schedule for removal of windows. Start wk of 6/29 at 3rd Floor. WB to get confirmation from R &R on window delivery date. Peter said powerwash to happen AFTER shingle patching. 6/18/09 PL emailed Robin for product data on the transom windows and possible gasketing & sealing issues. RBz talked to Robin about the lead time Robin is working on pushing it up by a week but as of now the delivery date is at 7/13. Roger to email and confirm dates by tomorrow. • 5.1 6/18/09- 3rd floor Mechanical room layou t- Chet and TJC had questions on layout of controls and the fan placement. Peter asked if a layout of the room is needed. All parties agreed. Dino to meet with Jay(SC) and Tom(TJC) 6/19/09 at 9 am onsite for coordination and to determine layout. Charlie to confirm meeting via email with Dino. 6/25/09 Layout to be done this afternoon. Item closed. 5.2 6/18/09- Louver Drawings- Marvin to give drawings of spec'd Louver elevations to Peter. Peter needs to see what elevation looks like so he can give direction on how to install. 6/25/09 Per Marvin Louver needs to be 38 *38. Peter said go for it. Marvin to order. Item closed. 6.1 6/25/09 Marvin requested that the sprinkler air compressor be moved sooner than later so that work can continue to progress. Chet to address. Item Closed. SPRINKLERS P2.1 4/23/09 Coverage - see 6/4/09 minutes for history. 6/4/09 Dino has forwarded drwgs & FPN to insurance provider. Two new heads are required. Dino will consolidate 2 new heads & other sprinkler changes and forward directive tomorrow, 6/5. 6/11/09 Dino relayed 2 new required heads to HFP, along w /other minor modifications at walk thru. HFP to revise drwgs and forward to Dion asap. 6/18/09 Dino talked to the office they should have the shop fabrication drawings by next week. 6/25/09 RBz to talk to Dino later today. ELECTRICAL P2.3 4/23/09 Submittals - Ted is working on both the light fixture and fire alarm submittals. Request made for Charlie to please supply NE w /cuts on SC provided light fixtures. Ted noted that he is submitting on an upgraded panel for fire alarm that interfaces w /future work required to be UL approved. 4/30/09 Ted still working on submittals. Charlie said fixtures are same as last yr therefore Ted said he doesn't really need cut sheets. Also, CC has the actual fixtures if the site electrician needs to see one. 5/7/09 Ted will have submittal pkg by Mon, 5/11. 5/14/09 Ted brought electrical submittals to mtg. LG gave to Dino. Only remaining submittal coming is Fire Alarm. Eta 5/15. 5/21/09 - 5/28/09 Fire Alarm submittal pending. 5/29/09 Post mtg: Ted emailed drwgs to Dino for preliminary review. Complete fire alarm submittals to be dropped at WB office on Mon, 6/1. 6/4/09 Fire alarm submittal was given to Dino today. Item closed. 6/11/09 Dino working on fire alarm submittal. Should be ready today for return to NE. 6/25/09 Submittals returned today via Peter. 1 to Peter and 2 to NE and WBI. Item Closed. 5.3 6/18/09 Light in corridor outside 313 - Peter wanted the ceiling light fixture to be smaller to match the rest of the fixtures. Dino to talk to Ted about changing it from a 21" fixture to a 14" one. • 4/23/09 Dino will issue SK by end of the wk. WB to price both options: 1) flat panel and 2) evacuated tube. Peter to go back & present to city for Elm St approval. 4/30/09 Dino is working on it. Closed. 5/7/09 Dino distributed SK today. Peter to issue PR after looking at structural & panel location w/Ryan. WB awaiting PR to price. Closed. 5/14/09 Dino to email Peter the cut sheet on panel showing how it is mounted. PL needs for flashing and point load details. PL said WB can go ahead and start pricing solar panels per Dino's SKs. Structural info to follow. Closed 5/21/09 WB working on pricing. Jay/L &S to email cut sheet to Peter. Peter will issue PR #2 for solar panels w/o structural. There will be a separate PR for the structural work. Closed 5/28/09 Peter issued PR #2. WB pricing. Closed. 6/4/09 Roger gave Peter, Dino and Charlie the load specs for solar panels. Dino to contact Yankee Tech for controls info. Peter to provide structural and mounting detail to roof. All reviewed proposals /costs for both flat panel & evacuated tube. Flat panel is preferable and easier technology. Roger to prepare and forward CO Proposal #6 with flat panel costs for approval by the College. 6/11/09 Per Dino & YT, the controls are compatible w /meters. RBz will include as option in solar CO. Closed. Peter working on structural. RBz working structural pricing solar panel pricing done. 6/18/09 Loads and Structural questions are covered in Architectural. CO Proposal coming. 6/25/09 RBz still working on pricing for structural piece. Monty looked at it last week will need to cut a hole in the roof and patch and use a crane for at least 1/2 a day. 3.1 6/4/09 Duct cleaning - Marvin would like to do sooner than later. Dino said wait until duct demo is done. In meantime, TJC to make sure fans are off to minimize construction dust accumulating in ducts. 6/11/09 Fan still running. TJC requested Northup Elec disconnect. Item closed. 6/18/09 Electric is disconnected. TJC is going to clean cap it in the next wk or 2. 6/25/09 Being done July 1st. Item closed. 3.2 6/4/09 Existing water lines in Lower Level - all to view 10' run from new Mech Rm to new Bath and decide whether to move it up higher? 6/11/09 Dino requested TJC price RFP for moving a section of water lines up. Scope of work also includes rerouting heating lines out of Corridor and thru Bathroom soffits. 6/18/09 Waiting on itemized pricing from TJC to be sent out early next week. 6/25/09 Pricing on COP 11- approved. Item closed. 4.1 6/11/09 Deteriorated, broken sewer line - Dino to issue SK including showing sewer line extended out about 5' beyond wall in planting bed. Decision made to not add additional lights in crawl space. Peter reminded that future access to everything in this crawl space area is required. 6/18/09- Per Charlie it is a go for sewer pipe repair & adding exterior cleanout exterior. RB to get it scheduled. 6/25/09 Excavation done. Back fill to start tomorrow. Item closed. - a 2 g4 Wright Builders, Inc. / 48 Bates Street Northampton, MA 01060 Tel: 413 -586 -8287 4 . Fax: 413 - 587 -9276 juN 2009 Park House Renovation Meeting Minutes �?tS !l '_,;10 Date: 6/25/09 Re: Park House Renovation, Smith College Construction Meeting #6 - 6/25/09 To: Attendees - via email Present: Charlie Conant, Hannah Durrant- Smith College (SC) Peter Lapointe - Archimetrics Design Studio (ADS) Roger Buzzell, Chet Mitchell, Ann Ledwell - Wright Builders, Inc. (WB) Marvin Blakley - TJ Conway (TJC) Owen Lococo - Lococo Painting Ted Forcier- Northup Electric (NE) Cc: Tony Patillo - Northampton Building Commissioner Ryan Hellwig - (RH) Chris Zurheide - HFP Sprinkler Contracting (HFP) Robin Sheldon - R &R Window Contractors (R &R) Jeff- Accufab Ironworks Fred Pazmino - Titan Roofmg Doug Mercier - Mercier Carpet (MC) Mark Ledwell, Linda Gaudreau - Wright Builders, Inc. (WB) Dino D'Angelo - Lindgren & Sharples (L &S) Becky Shaw- Smith College (SC) Ann Ledwell, Wright Builders, Inc. Work Progress: Roofing, masonry, framing ongoing. Hardwood Floors- 2nd floor in process of sand & seal Rough mechanical, Plumbing and electrical ongoing. Excavation on sewer line done back fill to be done tomorrow. The following items were discussed: Mtg. Item MECHANICAL P1.6 4/16/09 Solar panel - Per Peter, Dino will issue an SK on solar panel and how it interfaces in Basement. TJC to run pipes and connect. Railing shop drwgs Acoustical ceiling tile Westek shop drwgs 6/18/09 some remaining still to be submitted. Acoustical ceiling tile Westek shop drwgs- per PL samples were dropped off to him by Westek but still no shop drawings. 5.5 6/18/09 Hardware finish - Roger spoke with Jo -Ellen and 691 is closer to the other hardware finishes. Finish Changed to 691 from 696. Item Closed 5.6 6/18/09 Gas Meter Location - Charlie to meet with the gas company about the possible relocation of the gas meter as Frank is concerned. Next Construction Mt p: Thursday, June 25th, 9:00 Walk Thru with Job i Jtg to follow at 9:30 at Park House Room 101 The above is intended to be a record of meeting items. Plerse infoun the writer of errors or omissions. Revised CO Log distributed and reviewed. RBz working on pricing. Peter asked if there was any cost implications for closet move? Roger thought not, except maybe some cost from HFP? 6/18/09 Revised CO Log distributed and reviewed. All approved COP items to be incorporated into CO #2 and pencil req next wk. 1.11 5/21/09 Interior finishes - Peter discussed finishes w/Becky & Linda LaFlam. They confirmed all the wdw treatments in Liv Rm are changing. Peter showed them preliminary carpet and vet color selections. WB to get a larger pc of carpet sample, color: "The Capital" (blue) and also the carpet submittals for the Corridor carpet. 5/28/09 Doug Mercier brought larger blue room carpet sample and 2 corridor carpet samples to the mtg. Charlie to bring them to Linda LaFlam for approval. Peter to complete color schedule after mtg w/Linda & Becky. Doug to resubmit on stair rubber material. 6/4/09 Doug resubmitted stair rubber. Peter is scheduled to meet w/Becky on Thurs, 611, after the job mtg. 6/11/09 Peter reviewing color /fmishes w /Becky today. 6/11/09 Post mtg: Peter emailed Color Schedule. Paint colors to follow. Item closed. 6/18/09 Brett gave Peter samples of upholstery. Peter to get together with Becky to put together the paint schedule. 3.7 6/4/09- 6/11/09 Room #s - have been relocated per plan. Chet to get list of new #s needed to Charlie. 6/18/09 Chet has gotten the list of new room #'s together. He gave it to Charlie. Item closed. 4.6 6/11/09 May pay req - Charlie said req signed and in system on Tues, 6/16. Check cut on Thurs, 6/18. Item closed. 6/18/09 Per Charlie check to be cut next Thursday, 6/25. Item Closed 4.7 6/11/09 Chimney cap - Charlie requested price to cap front chimney w /copper. 6/18/09 Fred onsite today. Peter to do a PR 4.8 6/11/09 Flashing over dormer wdws - Charlie asked for confirmation that Titan was installing head flashing over dormer windows as originally planned. 6/18/09 Done. Chet mentioned the need to replace comer board as it was broken. Peter, Charlie and RBz discussed different material choices Azek was determind to be the most durable mat. Peter to do a PR. 4.9 6/11/09 Old stuff - Becky requested WB put glassware & misc Kitchen items in box and store in Basement. She said Ok to throw out any remaining Student stuff from Basement. SC will pick up any electronic items. Chet to set them aside for pickup. 6/18/09 Chet has put them by the backdoor. Charlie to have them picked up. Item Closed. 4.10 6/11/09- 6/18/09 Roller shade resubmittal - distributed. Discussed request by SC for heavier duty spring on large window sizes. Peter to review. 4.11 6/11/09 Submittals - some remaining still to be submitted: Steel reinforcement & cone mix at ramp RBz to get together with Monty and forward pricing for PR #5. Peter will issue another PR off Chefs list. P2.5 4/23/09 Masonry recon mission - See 6/4/09 minutes for history. 6/11/09 Peter reviewed w/Paul use of stainless strap anchors at roof/brick work and ss pins set in epoxy for cap stone. RBz to talk w/Paul about stone sample. 6/18/09 RBz to touch base w/ Paul again about the stone sample. P3.5 4/30/09 Windows - see 5/28/09 minutes for history. 6/4/09 Peter reminded that brickmould to remain w /new caulking at dormers w /arch top wdws scheduled for new wood sash into openings. Peter requested confirmation that middle of arch top DH & top of 1/2 screens align. 6/11/09 Per Roger, Robin/R &R confirmed alignment of meeting rail of arch top DH. Charlie asked about schedule for removal of windows. Start wk of 6/29 at 3rd Floor. WB to get confirmation from R &R on window delivery date. Peter said powerwash to happen AFTER shingle patching. 6/18/09 PL emailed Robin for product data on the transom windows and possible gasketing & sealing issues. RBz talked to Robin about the lead time Robin is working on pushing it up by a week but as of now the delivery date is at 7/13. Roger to email and confirm dates by tomorrow. 6/18/09 Post Mtg: Robin called RBz the eagle windows are to arrive in CT on 7/6/09 and to be delivered to Park House on 7/8/09 P4.5 5/7/09 Rich K concerns - See 5/7/09 minutes for history. 5/14/09 - 5/28/09 Only remaining open items: Charlie to mark up elevations of wdws to be abated and forward it to Rich K & WB. Titan to provide letter stating that roofing went to "permanent solid waste landfill ". 5/28/09 Post mtg: BNB will provide letter of harzardous roofing to "permanent solid waste landfill". 6/4/09 Charlie to scan & email mark up elevations of wdws to WB. BNB still to provide letter. Lower level Bath floor has been abated once. Does floor underneath also need abatement? Charlie to check w/Rich K. Lower level Hall - remove existing tile? Or go over w /carpet? WB to ask Doug Mercier. 6/11/09 BNB letter pending. Lower level Bath floor determined to still be "hot" and was abated. WB spoke w/Doug Mercier and carpet will be installed over lino in Lower level Hall. 6/18/09 Charlie to tell Rich it is looking like starting around 7/6- 7/13th. Roger to email and confirm dates by tomorrow. BNB letter still pending. 6/18/09 Post Meeting: Window installation beginning 7/8. Window removal starts 7/6 -7 P5.9 5/14/09 CO Log - Revised CO Log distributed today. RBz to have to have pricing on open items by next job mtg. 5/21/09 - 5/28/09 Not discussed. 6/4/09 Revised CO Log was distributed and reviewed. Peter to prep CO #1 to include COP# 1- 5 & 7 to be included on June Pay Req. 6/11/09 CO #1 is complete and will be included in June Pay Req. 6/18/09 PR E -1 recvd then COP 12.6 was issued. Approved. Item closed 2.3 5/28/09 Emergency lighting - Peter requested JoeJ/L &S issue Bulletin on emergency lighting and location of emergency power. Per Peter, remote battery type of emergency lighting preferred. 6/4/09 Dino to issue PR. 6/11/09 PR coming. NE to start pricing. 6/18/09 PR E -1 recvd then COP 12.5 was issued. Approved. Item closed 3.4 6/4/09 1st, 2nd & 3rd Floor elec panels - have exposed wires. Ted & Dino looked at them today. Dino to issue PR. 6/11/09 PR coming. NE to start pricing. 6/18/09 PR E -1 recvd then COP 12.4 was issued. Approved. Item closed 3.5 6/4/09 T12 light fixtures in 2nd & 3rd Flr Baths - at Charlie's walk thru with Danno /SC environmental, they noticed these existing fixtures and asked they be eliminated and replaced with standard fixture, possibly the Corridor fixture which is in stock. Dino to issue PR.. 6/11/09 PR coming. NE to start pricing. 6/18/09 PR E -1 recvd then COP 12.7 was issued. Approved. Item closed 4.3 6/11/09 Some energy lights - to be replaced in existing locations were fed w /romex - rewire? Ted to send locations to Dino and go ahead & price. 6/18/09 PR E -1 recvd then COP 12.5 was issued. Approved. Item closed 5.3 6/18/09 Light in corridor outside 313 - Peter wanted the ceiling light fixture to be smaller to match the rest of the fixtures. Dino to talk to Ted about changing it from a 21" fixture to a 14" one. 5.4 6/18/09 Moving of Conduit in trunk space- discussions during the site walk through about moving the layout of the partition of the trunk space. Which would require removing the gas line that is intended for the laundry and then moving of the conduit that runs above this pipe. That is determined to be grounding. Charlie, Dino & Peter to look at the moving of it next week when Ted is here. ARCHITECTURAL P1.12 4/16/09 Structural site visit - See 6/4/09 minutes for history. 6/11/09 Ryan on site today. Structural items: 1. Peter will give directive for wall under steel beam 2. Ryan will issue SK for reinforcement of steel beam 3. Ryan will issue SK for reframing of 1st Fir stair opening 4. Roger Bz said layout of Bath toilets land right on joists. Carpenter to header off. Peter said to use salvaged existing framing to match dimensions. 5. Roof - structural changes - to stiffen roof for snow & solar panel load. 6/18/09 PR #5 was issued today by PL. PL mentioned the logistics on how to get the 22ft LVL into the roof. CM and RBz to work it out. 5.1 6/18/09- 3rd floor Mechanical room layou t- Chet and TJC had questions on layout of controls and the fan placement. Peter asked if a layout of the room is needed. All parties Dino to meet with Jay(SC) and Tom(TJC) 6/19/09 at 9 am onsite for coordination and to deteiuiine layout. Charlie to confirm meeting via email with Dino. 5.2 6/18/09- Louver Drawings- Marvin to give drawings of spec'd Louver elevations to Peter. Peter needs to see what elevation looks like so he can give direction on how to install. SPRINKLERS P2.1 4/23/09 Coverage - see 6/4/09 minutes for history. 6/4/09 Dino has forwarded drwgs & FPN to insurance provider. Two new heads are required. Dino will consolidate 2 new heads & other sprinkler changes and forward directive tomorrow, 6/5. 6/11/09 Dino relayed 2 new required heads to HFP, along w /other minor modifications at walk thru. HFP to revise drwgs and forward to Dion asap. 6/18/09 Dino talked to the office they should have the shop fabrication drawings by next week. ELECTRICAL P2.3 4/23/09 Submittals - Ted is working on both the light fixture and fire alarm submittals. Request made for Charlie to please supply NE w /cuts on SC provided light fixtures. Ted noted that he is submitting on an upgraded panel for fire alarm that interfaces w /future work required to be UL approved. 4/30/09 Ted still working on submittals. Charlie said fixtures are same as last yr therefore Ted said he doesn't really need cut sheets. Also, CC has the actual fixtures if the site electrician needs to see one. 5/7/09 Ted will have submittal pkg by Mon, 5/11. 5/14/09 Ted brought electrical submittals to mtg. LG gave to Dino. Only remaining submittal coming is Fire Alarm. Eta 5/15. 5/21/09- 5/28/09 Fire Alarm submittal pending. 5/29/09 Post mtg: Ted emailed drwgs to Dino for preliminary review. Complete fire alarm submittals to be dropped at WB office on Mon, 6/1. 6/4/09 Fire alarm submittal was given to Dino today. Item closed. 6/11/09 Dino working on fire alarm submittal. Should be ready today for return to NE. 1.7 5/21/09- 5/28/09 Room 100D - No SDs shown on drwg. Ted & Peter think they are probably needed. Dino to give directive. 6/4/09 Per Dino - Yes - we need SD in Room 100D. Dino to issue PR. 6/11/09 PR coming. NE to start pricing. 6/18/09 PR E -1 recvd then COP 12.3 was issued. Approved. Item closed 1.9 5/21/09- 5/28/09 Exterior light - at corner of bldg where tree was removed - Peter thinking this light maybe should remain. Dino to confirm. 6/4/09 Dino to issue PR. 6/11/09 PR coming. NE to start pricing. P1.6 4/16/09 Solar panel - Per Peter, Dino will issue an SK on solar panel and how it interfaces in Basement. TJC to run pipes and connect. 4/23/09 Dino will issue SK by end of the wk. WB to price both options: 1) flat panel and 2) evacuated tube. Peter to go back & present to city for Elm St approval. 4/30/09 Dino is working on it. 5/7/09 Dino distributed SK today. Peter to issue PR after looking at structural & panel location w/Ryan. WB awaiting PR to price. 5/14/09 Dino to email Peter the cut sheet on panel showing how it is mounted. PL needs for flashing and point load details. PL said WB can go ahead and start pricing solar panels per Dino's SKs. Structural info to follow. Closed 5/21/09 WB working on pricing. Jay/L &S to email cut sheet to Peter. Peter will issue PR #2 for solar panels w/o structural. There will be a separate PR for the structural work. Closed 5/28/09 Peter issued PR #2. WB pricing. 6/4/09 Roger gave Peter, Dino and Charlie the load specs for solar panels. Dino to contact Yankee Tech for controls info. Peter to provide structural and mounting detail to roof. All reviewed proposals /costs for both flat panel & evacuated tube. Flat panel is preferable and easier technology. Roger to prepare and forward CO Proposal #6 with flat panel costs for approval by the College. 6/11/09 Per Dino & YT, the controls are compatible w /meters. RBz will include as option in solar CO. Peter working on structural. RBz working structural pricing solar panel pricing done. 6/18/09 Loads and Structural questions are covered in Architectural. CO Proposal coming. 3.1 6/4/09 Duct cleaning - Marvin would like to do sooner than later. Dino said wait until duct demo is done. In meantime, TJC to make sure fans are off to minimize construction dust accumulating in ducts. 6/11/09 Fan still running. TJC requested Northup Elec disconnect. Item closed. 6/18/09 Electric is disconnected. TJC is going to clean cap it in the next wk or 2. 3.2 6/4/09 Existing water lines in Lower Level - all to view 10' run from new Mech Rm to new Bath and decide whether to move it up higher? 6/11/09 Dino requested TJC price RFP for moving a section of water lines up. Scope of work also includes rerouting heating lines out of Corridor and thru Bathroom soffits. 6/18/09 Waiting on itemized pricing from TJC to be sent out early next week. 4.1 6/11/09 Deteriorated, broken sewer line - Dino to issue SK including showing sewer line extended out about 5' beyond wall in planting bed. Decision made to not add additional lights in crawl space. Peter reminded that future access to everything in this crawl space area is required. 6/18/09- Per Charlie it is a go for sewer pipe repair & adding exterior cleanout exterior. RB to get it scheduled. 4.2 6/11/09 Cost changes - Dino requested Marvin start pricing changes and have ready for Charlie next Weds, 6/17, for review and approval. Charlie is out Thurs & Fri, 6/18 -19. 6/18/09 Item closed. ?J3a 1- "' -- ' } Wright Builders, Inc. �� s _ y 48 Bates Street Northampton, MA 01060 juN 2 4 2009 Tel: 413 -586 -8287 Fax: 413 -587 -9276 c Nn 7 '' ` `. -- — ' � -- — ' Park House Renovation Meeting Minutes Dade: 6/18/09 Re: Park House Renovation, Smith College Construction Meeting #5 - 6/18/09 To: Attendees - via email Present: Charlie Conant, Hannah Durrant, Brett McGuinness - Smith College (SC) Peter Lapointe - Archimetrics Design Studio (ADS) Dino D'Angelo - Lindgren & Sharples (L &S) Marvin Blakley - TJ Conway (TJC) Roger Buzzell, Chet Mitchell, Linda Gaudreau, Ann Ledwell - Wright Builders, Inc. (WB) Mark Ledwell - Wright Builders, Inc. (WB) Cc: Tony Patillo - Northampton Building Commissioner Ryan Hellwig - (RH) Chris Zurheide - HFP Sprinkler Contracting (HFP) Robin Sheldon - R &R Window Contractors (R &R) Jeff - Accufab Ironworks Fred Pazmino - Titan Roofmg Owen Lococo - Lococo Painting Doug Mercier - Mercier Carpet (MC) Mark Ledwell - Wright Builders, Inc. (WB) Ted Forcier- Northup Electric (NE) - En Linda Gaudreau, Wright Builders, Inc. Work Progress: Roofmg, masonry, framing ongoing. Hardwood Floors- 3rd floor complete with 3 coats and 100% protected (except the suites) Start the 2nd floor next week. Rough mechanical and electrical ongoing. Rough plumbing to start next week. Excavation on sewer line to be done next week. The following items were discussed: Mtg. Item MECHANICAL gi; TA CwA C00.0.00.4vei&N 4 HJ4q4jj 1 I j �4e4 t!' A 13 1 \tar _ Y•s' °` r $,o x00., 1 01 0210$ -1615 P (617) 727 -3200 fM (617) 727 -S732 FINAL CONSTRUCTION CONTROL DOCUMENT (for Professional Engineers /Architects responsible for only a portion of a controlled project) Project Title: Park House Dorimitory Renovations Date: August 13, 2009 Project Location: Elm Street, Smith College Campus, Northampton MA Scope of Project: Fire Alarm System Replacement associated with building renovations In accordance with Section 127.0 of the Massachusetts State Building Code sixth edition I, Mark W Felgate Mass. Registration Number 47531 being a registered professional Engineer hereby CERTIFY that I have prepared or directly supervised the preparation of all design plans, computations and specifications concerning: [ ] Entire Project [ ] Architectural [ ] Structural [ ] Mechanical [ ] Fire Protection [ X ] Electrical [ ] Other (specify) for the above named project and that to the best of my knowledge, such plans, computations and specifications meet the applicable provisions of the Massachusetts State Building Code, all acceptable engineering practices and all applicable laws for the proposed project. I further certify that I have performed the necessary professional services and I or my Representative have been present on the construction site on a regular and periodic basis to determine that the work has proceeded in accordance with the documents approved for the building permit and shall be responsible for the following as specified in Secion 116.2.2. 1. Review for conformance to the design concept, shop drawings, samples and other submittals which are submitted by the Contractor in accordance with the requirements of the construction documents. 2. Review and approval of the quality control procedures for all code - required controlled materials. 3. Be present at intervals appropriate to the state of construction to become generally familiar with the progress and quality of the work and to determine in general if the work is being performed in a manner consistent with the construction documents. Pursuant to Secion 116.4, I have submitted progress reports together with pertinent comments to the Building Inspector. Upon completion of the work, I am submitting this Final Report as to the satisfactory completi• + pl work and readiness of the project for occupancy. � '" M '1616, MARK W. G . Signature and Seal of registered professional: - Z FELGATE f - ELECTRICAL I : No.47531 2 FQ /8�� SU: `CR,IBED ; ND S ORN TO BEFORE ME THIS ��.1 DAY OF ( ,/j. 20x9.. SOpq�: // � A ' / j / ,e' Y COMMISSION EXPIRES � 4..: � c :L' // 1 r r AR ' UBLIC TA Cosys.ittvividig M 44444+ A it D e t m# 1 0 , 4406 4 p at: , s4ast \ 1 .� o . F �,. 1301 A ,R 13 i g., Ho140444414 02109 P44 (617) 727 - 3200 fMe (617) 727-S732 FINAL CONSTRUCTION CONTROL DOCUMENT (for Professional Engineers /Architects responsible for only a portion of a controlled project) Project Title: Park House Dorimitory Renovations Date: August 13, 2009 Project Location: Elm Street, Smith College Campus, Northampton MA Scope of Project: Fire Alarm System Replacement associated with building renovations In accordance with Section 127.0 of the Massachusetts State Building Code sixth edition 1, Charles P Sharpies Mass. Registration Number 28940 being a registered professional Engineer hereby CERTIFY that I have prepared or directly supervised the preparation of all design plans, computations and specifications concerning: [ ] Entire Project [ ] Architectural [ ] Structural [ X ] Mechanical [ ] Fire Protection [ ] Electrical [ ] Other (specify) for the above named project and that to the best of my knowledge, such plans, computations and specifications meet the applicable provisions of the Massachusetts State Building Code, all acceptable engineering practices and all applicable laws for the proposed project. I further certify that I have performed the necessary professional services and I or my Representative have been present on the construction site on a regular and periodic basis to determine that the work has proceeded in accordance with the documents approved for the building permit and shall be responsible for the following as specified in Secion 116.2.2. 1. Review for conformance to the design concept, shop drawings, samples and other submittals which are submitted by the Contractor in accordance with the requirements of the construction documents. 2. Review and approval of the quality control procedures for all code - required controlled materials. 3. Be present at intervals appropriate to the state of construction to become generally familiar with the progress and quality of the work and to determine in general if the work is being performed in a manner consistent with the construction documents. Pursuant to Secion 116.4, I have submitted progress reports together with pertinent comments to the Building Inspector. Upon completion of the work, I am submitting this Final Report as to the sat' ?- a, -> . letion of the work and readiness of the project for occupancy. 4 CHARLES " Signature and Seal of registered professional: . / / � I P. / / S H ARPIES y �O � F C /ST E / i F SS1 N c ECG . S1J C' BED ND SWORN 'O BEFORE ME THIS /3 DAY OF �ti 119. f 1, ' A l' _ / Y COMMISSION EXPIRES 7 2 f C/ �� ► ARY P I BLIC a + ARCHIMETRICS DESIGN STUDIO EN 28 NORTH MAPLE UNIT B � • FLORENCE, MA 01062 August 25, 2009 Anthony Patillo, Building Commisioner Puchalski'Municipal Center 212 Main Street Northampton, MA 01060 Project: Renovations to Park House, Smith College, . Northampton, MA 01060 Scope: Renovation and Refurbishment of existing building. FINAL CONTROLLED CONSTRUCTION AFFIDAVIT In accordance with Section 116.0 of the Massachusetts State Building Code, 7th Edition, I, Peter E. Lapointe, Massachusetts Registration No. 5291, being a registered Architect, hereby certify that I have prepared or directly supervised the preparation of all design plans, computations and specifications for the above mentioned project. (further certify that'I have performed the necessary professional services during construction and have been present on the construction M ite on a regularand periodic basis to determine that the work is proceeding ir\accordance with the drawings and specifications approved for the building permit. ,yam RE ARC ;{,, V,. LAp t 44, , No. '- 291 S SA,eI , . w F,m, i Peter E. Lapointe PETER LAPOINTE, ARCHITECT PH 413 582 -9100 FAX 413 582 -9101 www.archimetrics.net /13 — .c71 Wright Builders, Inc. 48 Bates Street I U�U ( �(Hw JUL L Northampton, Ma 01060 Date 8/28/2009 'Job No. 09 -910 Attention: (413) 586 -8287 Re: Fax (413) 587 -9276 Park House Smith College To: Tony Patillo Northampton Building Dept. x \i 2 8 2UU9 We are Sending You 1 Attached Under Separate Cover via The Following Items: Shop Drawings r Prints r , Plans r Samples " Specifications Copy of Letter u. Change Order r- Copies Date No. Description 1 8/25/2009 Final Construction Control Affidavit - Architectural - Peter Lapointe 1 8/13/2009 Final Construction Control Affidavit - Mechanical - Lindgren & Sharples 1 8/13/2009 Final Construction Control Affidavit - Electrical - Lindgren & Sharples These are Transmitted as checked below: For approval r Approved as submitted 3 Resubmit copies for approval For your use r Approved as noted r Submit copies for distribution As Requested f` Returned for corrections 1 "" Return corrected prints For review and comment r FOR BIDS DUE E PRINTS RETURNED AFTER LOAN TO US Remarks Copy to Signed: )1€449,-.1.-4------- • zeOrg- s 7-9 1 , A/2,y o o,1 ...t.d 1.1 0 t _, 7 (3 r r E DO 1A4 4'‘lq C71153-) (%0/6214.0 oN137.1) y7y3 ■11qt■i. d >I ‘ 51< QQ .p "'oci Pir4 14/91,A15.SV? 2 to Ng 00>i if t 49/(C. 7 f l # c idiyvf-i; /pc^,fy clie/b Fn/c 2$.91,'D cyr//7 47.4 67 4'1 "rit 5471 ;LL7:417( 131171L}Thr‘;; --;1 ;;9t- tii;b1/1/1 ""-v-et 1 9 4 71 , .0 if: 1 ? • „1/ il / r 4 ( ..„ Pr? hi / 1/ /6. 146 ;1)4 4 gb/far -v1V3 4404°4 -- trlivy 134 ELM ST - PARK HOUSE w BP- 2009 -0935 GIS #: COMMONWEALTH OF MASSACHUSETTS Map:Block: 31B - 244 CITY OF NORTHAMPTON Lot: -001 PERSONS CONTRACTING WITH UNREGISTERED CONTRACTORS Permit: Building DO NOT HAVE ACCESS TO THE GUARANTY FUND (MGL c.142A) Category: renovation BUILDING PERMIT Permit # BP- 2009 -0935 Project # JS- 2009 - 001004 Est. Cost: Fee: $4998.00 PERMISSION IS HEREBY GRANTED TO: Const. Class: 5B Contractor: License: Use Group: R2 WRIGHT BUILDERS 84280 Lot Size(sq. ft.): 11151.36 Owner: SMITH COLLEGE OFFICE OF TREASURER Zoning: URC(100) / /EU Applicant: WRIGHT BUILDERS AT: 134 ELM ST - PARK HOUSE Applicant Address: ,Phone: Insurance: 48 Bates St (413) 586 -8287 Workers Compensation NORTHAMPTONMA01060 ISSUED ON:5/27/2009 0:00:00 TO PERFORM THE FOLLOWING WORK:DORM RENOVATION,SIDING,ROOF,WINDOW REPLACEMENTS,REM FIRE ESCAPE & NEW EXT ENTRANCE POST THIS CARD SO IT IS VISIBLE FROM THE STREET Inspector of Plumbing Inspector of Wiring D.P.W. Building Inspector Underground: °a Service: Meter: VM 6 1P reo ft '- Footings: Roughs) . 0 e , 'p:Rough:.Sw.fi3 - House # Foundation: 3Z/ y 't\ // Driveway Final: 444 Final: e -if 0 v [ � p Rough Frame: 01( 671 C 9 ` . Gas: Fire Department Fireplace /Chimney: Rough:7 16 ,(1 Oil Insulation: Final: d S mok� Final: // THIS PERMIT MAY BE REVOKED BY THE CITY OF NORTHAMPTON UPON VIOLATION OF ANY OF ITS RULES AND REGULATI S. Certificate of Occu•anc si. nature: FeeType: Date Paid: Amount: _. Building 5/27/2009 0:00:00 $4998.00 212 Main Street, Phone (413) 587 -1240, Fax: (413) 587 -1272 Building Commissioner - Anthony Patillo 10. Do any signs exist on the property? YES NO X IF YES, describe size, type and location: Are there any proposed changes to or additions of signs intended for the property? YES NO X IF YES, describe size, type and location: 11. Will the construction activity disturb (clearing, grading, excavation, or filling) gver 1 acre or is it part of a common plan of development that will disturb over 1 acre? YES NO IF YES, then a Northampton Storm Water Management Permit from the DPW is required. 12. ALL INFORMATION MUST BE COMPLETED, or PERMIT CAN BE DENIED DUE TO LACK OF INFORMATION This column reserved for use by the Building Department EXISTING PROPOSED REQUIRED BY ZONING Lot Size / Frontage //A.• / . N /a Setbacks Front / Side L: /� R: IJ � L: 1.11A. R: N /A L: R: Rear Building Height 1 as B rE- Building Square Footage 2 0, 391 20 , 39 I Open Space: (lot area minus building Et paved 1.1 /4. K1 A parking # of Parking Spaces /0 K\/A. # of Loading Docks Nla- �Oa Fill: (volume Et location) 13. Certification: I hereby certify that the information contained herein is true and accurate to the best of my knowledge. Date: ' / 0 c r Applicant's Signature _ . , . ' , ( G i / / NOTE: Issuance of a zoning permit does not relieve an applicant's burden to comply with all zoning requirements and obtain all required permits from the Board of Health, Conservation Commission, Historic and Architectural Boards, Department of Public Works and other applicable permit granting authorities. W:\Documents\FORMS \original\Buil ding - Inspector\ Zoning- Pennit- Application- passive.doc 8/4/2004 e. L�VJ File No. fPO g(o3 ZONING PERMIT APPLICATION ( §i o.2) Please type or print all information and return this form to the Building Inspector's Office with the $15 filing fee (check or money order) payable to the Ta' I City of Northampton I 1. Name of Applicant: E. TaUUTE S of TOE SMIT� COLLEGE Address: FAC.I LI T-I as M40,4GEMEL1T � 1∎ , AI 4 Telephone: 413 585' 2424 ec LEC E 2. Owner of Property: FICA LITIES M EUT, IT+ -1 CpL.Ll =r�1= Address: 12 - Le) WEST S I V_F__ET Telephone: 4r3• 5 86 2400 3. Status of Applicant: Owner X Contract Purchaser Lessee Other (explain) 4. Job Location: ROL - 1oUSE , ITO COLLEG -E , 134 ELM STZEET Parcel Id: Zoning Map# Parcel# District(s): In Elm Street District In Central Business District (TO BE FILLED IN BY THE BUILDING DEPARTMENT) 5. Existing Use of Structure /Property: STU DEL.1T DOa i IToa\f 6. Description of Proposed Use /Work /Project /Occupation: (Use additional sheets if necessary): IDILI 2EPa1 $ SL&TE HET41.._ 26oF EP1 A.C EM 16 kJDud QgpLAcEME,0T, LIMO► Na S I 4,12 &DDITI , 12E1-A NVI L. OF ECTE2IcQ I ZE ESCAPES 1.1EALI E. eat E IJTE4.1.1CCE 7. Attached Plans: Sketch Plan Site Plan Engineered /Surveyed Plans 8. Has a Special Permit /Variance /Finding ever been issued for /on the site? NO DON'T KNOW X YES IF YES, date issued: IF YES: Was the permit recorded at the Registry of Deeds? NO DON'T KNOW YES IF YES: enter Book Page and /or Document # 9.Does the site contain a brook, body of water or wetlands? NO X DON'T KNOW YES IF YES, has a permit been or need to be obtained from the Conservation Commission? Needs to be obtained Obtained , date issued: (Form Continues On Other Side) W:\ Documents \FORMS\ original\ Building- Inspector\Zoning- Permit- Application- passive.doc 8/4/2004 wr■ ,. File # MP- 2009 -0063 APPLICANT /CONTACT PERSON Trustees of Smith College ADDRESS /PHONE 126 West Street (413) 585 -2424 0 m: isi WcAi 4,5. . , y . ST ;PARKHs • I ' AP ti .+f.•< -' 44 011'' ONE URC(100UiEU THIS SECTION FOR OFFICIAL USE ONLY: PERMIT APPLICATION CHECKLIST ENCLOSED REQUIRED DATE ` ..O�I FILLED OUT e e Paid Building Permit Filled out Fee Paid Typeof Construction: - SIDING,ROOF,WINDOW REPLACEMENTS,REM FIRE ESCAPE & NEW EXT ENTRANCE New Construction Non Structural interior renovations Addition to Existing Accessory Structure Buildin. Plans Included: Owner/ Statement or License 3 sets of Plans / Plot Plan THE FOLLOWING ACT N HAS BEEN TAKEN ON THIS APPLICATION BASED ON INFORMATION PRE NTED: Approved _ j A dditional permits required (see below) PLANNING BOARD PERMIT REQUIRED UNDER : § Intermediate Project : Site Plan AND /OR Special Permit with Site Plan Major Project: Site Plan AND /OR Special Pei with Site Plan ZONING BOARD PERMIT REQUIRED UNDER: § Finding Special Permit Variance* Received & Recorded at Registry of Deeds Proof Enclosed Other Permits Required: Curb Cut from DPW Water Availability Sewer Availability Septic Approval Board of Health Well Water Potability Board of Health Permit from Conservation Commission Permit from CB Architecture Committee 1 Permit from Elm Street. J:nunission Permit DPW Storm Water Management ..'".‘ ZY i „ _____2 7 Signature of Building C fici.' Date Note: Issuance of a Zoning permit does not relieve a applicant's burden to comply with all zoning requirements and obtain all required permits from Board of Health, Conservation Commission, Department of public works and other applicable permit granting authorities. * Variances are granted only to those applicants who meet the strict standards of MGL 40A. Contact the Office of Planning & Development for more information.