Plan-Rocky Hill Rd.-319 new septic planOwner:
Scale: 1 : 20'
HOMESTEAD INC.
Thomas S. Leue R.S.
1664 Cape St.
Williamsburg, MA 01096
[413] 628-4533
Date:
Revision Date:
Except as Noted
Plan to Construct
New Septic System 11/15/2019 Stephen Theberge
319 Rocky Hill Road
Florence MA 01062
Main House
Septic Field
93
94
95
96
97
93
9899100
101
102103104105
106
107
92
91
90Reserve Area4'
System
Vent8'8'6'Inspection
Port Reserve AreaReserve Area4'
0 60 FTSCALE BAR
ROC
K
Y HILL ROA
D
NORTHPL
PL
PL
PL
Driveway
Main House
2-bedroom
Guest House
SYSTEM CALCULATIONS Leach Trench
Single Family Home 3 bedrooms
Sewage At Code Rate 330 gallons per day
Total Design Flow 330 gallons per day
Garbage Grinder not to be installed at this location.
Septic Tank Capacity 1500 gallons
Septic Tank Greater than 200% daily flow
Measured Perc Rate 3.3 min. per inch
Design Perc Rate 5 min. per inch
Soil Type Class I
Loading Rate 0.74 gallons/sq.ft./day
Leaching Area Required 445.9 square feet
40% Reduced Field Area 267.6 square feet
Infiltration Technology:Eljen GSF
Model Used:B-43
Length of Chamber:48 in.
Width of Chamber:36 in.
Overall height:7 in.
Invert height:7 in.
Effective Leach Area/Chamber:41.75 sq. ft./module
# Modules required:15
# Modules provided:15
# of Rows:3
# Modules per Row:5
C33 Sand Surrounding Rows:6 in.
Soil Beween Rows 72 in.
Total Width:24.0 feet
Total Length:21.0 feet
Total Effective Leaching Area:626.3 square feet
Net Calculated Capacity:330.0 gallons per day10"18"8"Inlet Outlet
Distribution Box Detail
6" washed stone
NOTES:
Inlet pipe capped with internal tee.
Riser to 6" or less below final grade.
Glue tee on inlet interior.55"52"67"130"
1500 gallon tank
Tees: Schedule 40, 6" above flow line, 10" min. below flow line on inlet, 14" on outlet. 10" airspace in tank. Manufacturer's tee-filter combination system
on outlet. Do not use outlet check valve.
Risers flush to final grade over all three access covers.
SEPTIC TANK PROFILE
SYSTEM REQUIREMENTS AND SPECIFICATIONS
1.General
Board of Health approval required before licensed contractor installs system. Obtain Disposal Works Permit. All construction to be in accordance with Title 5 (310 CMR 1500) of the State Environmental Code.
Contractor responsible for verifying all dimensions, elevations and conditions. Contact System Designer immediately if discrepancies are found. Alternatives to these specifications should be discussed with the System Designer, Tom Leue, in advance at (800) 285-4533.
Property lines are approximate, based on best available information. Any required tree cutting is the responsibility of the Contractor. All wells within 150' of system are shown on the drawing.
This septic system is not designed for a garbage grinder in the kitchen, do not connect one to the system or all implied warranties are voided.
The contractor selected is required to be certified in this technology before completion of the work. Arrangements for on-site Manufacturer's training can usually be made by arrangements with the company representative Eric Daniels at 800-444-1359.
2.Septic Tank
The septic tank for this project is to be Title 5 compliant. Install an outlet filter. Install plastic risers with sealed plastic covers to the final surface over all three access holes.
3.Piping
All piping from greywater and blackwater sources to be connected to building sewer in the basement. All piping from the septic tank to the end of the system shall be 4” diameter, SDR-35 or better, except as noted on the drawings. Joints are to be sealed water tight. Place magnetic
detectable warning tape pre-printed “Sewer Pipe Below” or similar wording approximately 6” above all new piping and other components installed on this project, other than leaching pads. Two feet out of distribution box pipe to be set dead level.
4.Leaching Facilities
All leaching facilities to be of the size, location and brand shown on the drawings. Do not substitue brands without notifying System Designer in advance to see if it affects systems size and design. All fill materials within 12" of the leaching pads to be C-33 certified sand. All other fill
within five feet horizontal of the leaching pads to be certified Title 5 sand. Do not excavate outside of the footprint of infiltration pads at the specified depth. Sand characteristics to be documented. Supplier provided Title-5 Sand Analysis shall be less than one year old. Sand suppliers shall
ensure that the analysis provided to the Septic Installer is representative by following a written Quality Assurance Plan (QAP) which documents the method(s) used to ensure that a sample report represents the actual material being supplied for use. The System Designer may analyze a sample
of the sand on-site to confirm Title 5 specifications.
5.Inspection
A minimum of two site inspections by the System Designer are required. Notify System Designer (800-285-4533) at least 24 hours in advance of completion of excavation and before addition of sand to certify site preparation. Notify System Designer at least 24 hours in advance of
completion of system construction and prior to backfill for final inspection. The System Designer shall verify the system was installed as designed and authorize the final grading. The Contractor responsible for notifying the local Board of Health for a final inspection. If the System Designer finds
the system is not ready for inspection after being called, or if serious deficiencies are discovered, the System Designer must be notified to return to the job site when it is complete. There will be a charge to the Installer of $50 for each return trip, payable directly to the System Designer at the
time of the reinspection. Inspection and project closeout forms are usually generated within 24 hours of final inspection by the System Designer, when all other requirements are met. Signed Certificate of Compliance forms and As-built Drawings are sent to the Installer for a signature and date.
One set of forms are then returned to the System Designer for final processing. The second set of forms are for the Contractor to keep as his project record.
6.Final Grading
At conclusion of work, loam and seed all disturbed areas to perennial grass mixture. Added loam may be required for adequate grass growth. Mulch slopes with hay, burlap or netting to minimize erosion. Surface over leaching facility shall be pitched so as to shed rainwater. Also pitch
surface over all tanks to shed rainwater from any exposed covers. Do not allow surface water to puddle over any tank or component. Systems built late in the year, where the grass cover does not have a chance to establish itself, requires the contractor to return after spring thaw and resurface
final grades and add grass seed cover as required to equalize and stabilize all disturbed areas.
Perc Tests Conducted 11/1/19
Conducted By Thomas Leue
Witnessed By Bri Eichstaedt
Depth of Perc Test 42 in.40 in.
Start Soak 9:37 9:51
End Soak 9:52 10:06
12" level 9:52 10:06
9" level 10:00 10:10
6" level 10:10 10:16
Time 9"- 6"10 6
Rate per inch 3.3 min/in 2.0 min/in
Soil Observation Results Conducted 11/1/19
Conducted By Thomas Leue
Witnessed By:Bri Eichstaedt
Test Pit 1
Depths Soil Horizon Color Texture ESHWT
0 to 8 Ap 10YR 3/6 FSL
8 to 18 Bw 10YR 5/6 FSL
18 to 30 C1 10YR 7/3 fine sand 28"
30 to 76 C2 10YR 7/1 fine sand 7.5YR 6/1
15% gravel, 10% stones 7.5YR 5/8
Test Pit 2
Depths Soil Horizon Color Texture ESHWT
0 to 8 Ap 10YR 3/6 FSL
8 to 18 Bw 10YR 5/6 FSL
18 to 36 C1 10YR 7/3 fine sand 26"
36 to 98 C2 10YR 7/1 fine sand 7.5YR 6/1
10% gravel, 15% stones 7.5YR 5/8
Test Pit 3
Depths Soil Horizon Color Texture ESHWT
0 to 8 Ap 10YR 3/6 FSL
8 to 22 Bw 10YR 5/6 FSL
22 to 29 C1 10YR 7/3 fine sand 28"
29 to 86 C2 10YR 7/1 fine sand 7.5YR 6/1
10% gravel, 15% stones 7.5YR 5/8
Test Pit 4
Depths Soil Horizon Color Texture ESHWT
0 to 8 Ap 10YR 3/6 FSL
8 to 18 Bw 10YR 5/6 FSL
18 to 30 C1 10YR 7/3 fine sand 26"
30 to 80 C2 10YR 7/1 fine sand 7.5YR 6/1
10% gravel, 15% stones 7.5YR 5/8 10'10'10'
36" height
above grade
System Low Vent
Ventilated cap
4" Sched. 40 ABS pipe
Leach modules
ground surface
Scale 1": 10'
12" bury depth
4" distribution pipe
Eljen GSF Model B43.
Number of Modules Required: 15.
Number of Modules Provided: 15.
Minimum 6" C33 sand underneath modules.
Manufacturer's filter fabric over all modules and distribution pipes.
Minimum 12" C33 sand surrounding modules.
Use 4" SDR-35 pipe in leaching area.
Cross-over pipes are not perforated.
Leaching Trench Configuration System Requirements
All other fill within 5 ft. of modules to be certified Title 5 sand.
INVERT ELEVATIONS and LENGTHS:
LEACH TRENCH CONFIGURATION
Letter Code Elevation
A House Outlet Invert 105.00
B Sched. 40 length 10 ft.
C Septic Tank Inlet 103.50
D Septic Tank Outlet 103.25
SDR-35 length 86 ft.
I SHWT Separation 4 ft.
Depth to Groundwater 26 in.
Excavation of Topsoil 10 in.
F D-box Inlet 98.13
G D-box Outlet 97.92
# of Modules Length 5 =21.0 ft.
Width 3 =12.0 ft.
Total Number of Modules 15
Step Between Trenches 8 in
Trench 1 Trench 2 Trench 3
Original Surface Contour 95.00 94.33 93.67
Groundwater Contour 92.83 92.17 91.50
Excavate Level 94.17 91.33 90.67
C33 Sand Base Level 96.83 96.17 95.50
Module Base 97.33 96.67 96.00
Module Top 97.92 97.25 96.58
Final Grade 98.92 98.25 97.58
O Membrane Top 97.00
P Membrane Base 93.00
PL
LOCUS PLAN
Work site
319 Rocky Hill Road
Existing 4" foundation drain
TBM: nail in base of 36" dia. oak.
Elevation: 100.00'
Electric pole
Buried power
1
2
3
410'Schedule 40
98
975'
Maintain shallow swale on upper
side to divert surface water.
Public water supply. No known
drinking water sources with 150 feet.
1,500-gallon Title 5 septic tank with outlet filter. Install plastic risers
with secured plastic covers over all three access covers to final grade.