Burts Pit Road stormwater excerpt.pdfBurts Bog Limited Development – Burts Pit Road April 18, 2017 (Revised June 6, 2017)
Northampton, Massachusetts Stormwater Management Report
The Berkshire Design Group, Inc. Page 1
The City of Northampton is proposing the construction of 10 single-family homes as part of a
Conservation and Limited Development project on Burts Pit Road in Northampton.
The Berkshire Design Group has prepared a Stormwater Management and Erosion and
Sedimentation Control Plan for the site, in compliance with the Massachusetts Stormwater
Handbook and the Code of the City of Northampton. This report documents the proposed
Stormwater Management Plan and that plan’s compliance with those standards.
I. Introduction
The proposed project will construct 10 single-family houses (including 2 zero-lot-line houses
separated by a party wall) on 10 newly-created residential lots. The project is located on Burts Pit
Road between Emerson Way and Woods Road, at the south end of the Burts Bog Greenway on land
currently owned by Tofino Associates. The project location is shown in Figure 1. The work includes
construction of the proposed buildings, as well as associated site, utility and stormwater
improvements.
The existing site is undeveloped, and primarily wooded, with a small amount of grass cover near the
street. A low point carries through the site on an east-west axis, creating a gradual swale sloping to
the east and west from a high point near the southeast corner of the site. A hillside extends from
the northern site limit, resulting in a significant volume of run-on from land outside the site
boundary.
Wetland areas exist outside the site limits to the east, west and north. None of these wetlands or
their associated buffer areas are impacted by the work.
There is an existing storm drainage system in Burts Pit Road; however, the southern edge of the site
generally slopes away from the street onto the site, and it appears that a negligible amount of
runoff from the site reaches Burts Pit Road.
Soil Data
NRCS Soil Survey
The NRCS Soil Survey reports that the soils at the site consist of fine sandy loam of Hydrologic Soil
Group C. The USGS Surficial Geology survey reports that the site is underlain by a relatively thin
(<10’ thick) layer of glacial till. The NRCS Soil Report for the site is attached in Appendix A.
Subsurface Exploration
A total of 4 test pits were conducted at the site in order to classify existing soils and determine the
relevant engineering properties. A summary of these explorations is included in Appendix B.
Soils were found to be highly consistent across the site. The typical test pit revealed 6-8 inches of
topsoil underlain by sandy loam subsoil. The site is underlain by a dense layer of red glacial till that is
classified as sandy loam. In general, all soils have a significant gravel content, and are dotted with
larger stones and cobbles, but soil texture becomes slightly more fine with depth.
Seasonal high groundwater was estimated to occur at a depth of 24-30” across the site.
Burts Bog Limited Development – Burts Pit Road April 18, 2017 (Revised June 6, 2017)
Northampton, Massachusetts Stormwater Management Report
The Berkshire Design Group, Inc. Page 2
Site Limits
Site limits were delineated for the purpose of establishing drainage areas within the site. Site limits
were based on property lines, as adjusted to account for up-gradient areas where stormwater is
expected to run on to the site.
II. Existing Conditions
An Existing Conditions Plan is shown on Figure 2. A plan of the Existing Hydrology is shown on Figure
4.
Drainage Areas
The existing site was divided into eight drainage areas. The majority of the site is collected by a
gentle swale traversing the site from east to west, which discharges at the western property line at
the point labeled CP1 (Control Point 1) on Figure 4. The remainder of the site is collected by a swale
sloping in the opposite direction, toward the east, which discharges at the point labeled CP2
(Control Point 2).
The overall drainage area flowing toward CP1 was divided into 7 sub-drainage-areas (A1 through
A7). Because the stormwater model can be affected by the way in which drainage areas are divided,
these sub-drainage-areas were drawn to match the approximate divisions that are created by the
proposed work, which allows for a more accurate comparison of the pre-development and post
development condition.
III. Proposed Conditions
The proposed site plan is shown on the Site Plan in Figure 3.
The proposed project will construct 10 single family houses on 10 building lots. Two of the houses
are constructed as zero-lot-line houses sharing a party wall (see Lots 5 and 7 in Figure 3). Seven
houses are planned to include an attached two-car garage, and each lot provides for the
construction of a shed or other accessory structure. Four paved, shared driveways are proposed to
serve the ten homes.
As the developer proposing the project, the City of Northampton directed Berkshire Design to
provide for stormwater management, to the greatest extent possible, through decentralized
systems to be maintained by individual homeowners. A series of rain gardens and swales are
proposed to attenuate peak runoff, improve water quality and promote groundwater recharge.
These features are shown on Figure 3, and highlighted on Figure 5.
It is notable that a significant portion of this attenuation is achieved by intercepting run-on
stormwater from the hillside above the site. Because of the large area and relatively poor soils, the
hillside produces a significant amount of stormwater runoff which enters the site in the existing
condition. Four large rain gardens are to be built along the northern edge of the site to intercept,
infiltrate, and redirect this runoff. The work of these rain gardens partially offsets the increase in
runoff created by development of the interior of the site.
The system has been designed to reduce peak runoff. The proposed detention basin is designed to
attenuate the 2, 10, and 100-year storms, and to produce a reduction in peak runoff from the site.
Burts Bog Limited Development – Burts Pit Road April 18, 2017 (Revised June 6, 2017)
Northampton, Massachusetts Stormwater Management Report
The Berkshire Design Group, Inc. Page 3
The prosed design is also designed to reduce both peak runoff and runoff volume that discharge to
adjacent properties to the east and to the west.
The soil evaluation revealed soils of marginal permeability and relatively shallow groundwater.
Nevertheless, opportunities for infiltration and groundwater recharge were maximized in the
design. Rain gardens will retain 9” of water, with an overflow weir built with crushed stone. The
bottom of each rain garden is proposed at an elevation 24” above the estimated seasonal high
groundwater at the nearest test pit. The soil evaluation revealed that surface soils are primarily
sandy loam, which has a standard “Rawls” infiltration rate of 1.02 inches per hour1, which would
allow the retained water to dissipate within the 72 hours required by the Massachusetts stormwater
handbook.
Rain gardens include an engineered outlet weir to reduce peak flow rates during intense rainfall. The
plans call for a weir to be carved out of the berm enclosing the rain gardens, which provides a 24”
wide opening for water to overflow from the rain gardens. The weir would be armored with 1” to 2”
crushed stone. The invert of the weir is set 9” above the bottom of the rain garden (which is 3”
below the crest elevation of the gardens).The rain gardens would be planted with a simple
woodland seed mix, which would require annual mowing to prevent the growth of woody plants.
Western Discharge Point
A critical location in the design is the discharge point at the western end of the site. In the existing
condition, approximately 75% of the site drainage areas collect at a point along the western
property line at a low point that is consistently wet, and appears to impound water during times of
high groundwater.
There is no obvious discharge location for this impounded water. The topographic survey shows that
surrounding land to the north, south and east is at least 6” higher than the low point. The
topographic survey does not show the elevations of the neighboring property (829 Burts Pit Road);
however, based on field observation, the grass lawn to the north of the house on that property
appears to be higher than the low point by 6-12” or more. Based on this information, it is likely that
this low area floods during intense rainfall, which ultimately forces water to flow to the north of the
lawn at 829 Burts Pit Road. According to GIS information, land north and west of 829 slopes more
steeply to the west, ultimately forming a small stream/drainage channel that is carried by a culvert
under Woods Road.
The Burts Bog development project proposes to leave this area undisturbed, and to allow existing
drainage patters to continue. The limit of disturbance on Lot 2 maintains a 30’ buffer at the western
edge of the site, which is extended to 70’ where water is carried under the Lot 1/2 common
driveway. The proposed stormwater management system has been designed to mitigate increases
in both peak flow rate and volume from the developed site verses the existing condition. The
stormwater calculations predict that the existing drainage condition in this part of the site will be no
worse in the proposed condition. Additionally, a portion of the run-on to the site from the hillside
above is discharged north of the proposed houses, where it can more directly enter the proposed
conservation land north and west of the site (see Rain Garden 2A on Sheet C-3).
1 For calculation purposes, the infiltration rate was reduced to a more conservative value of 0.25 inches per hour in
the stormwater model. The model is discussed further in Section IV.
Burts Bog Limited Development – Burts Pit Road April 18, 2017 (Revised June 6, 2017)
Northampton, Massachusetts Stormwater Management Report
The Berkshire Design Group, Inc. Page 5
near Burts Pit Road discharge to the road, with runoff from one drainage area entering the storm
drain system flowing toward the west, and the other entering the storm drain system flowing
toward the east.
IV. Calculations and Design
Water Quantity – Flow Rate
Drainage calculations were performed on Hydrocad Stormwater Modeling System version 10.0 using
Soil Conservation Service (SCS) TR-20 methodology. The SCS method is based on rainfall
observations, which were used to develop the Intensity-Duration-Frequency relationship, or IDF
curve. The mass curve is a dimensionless distribution of rainfall over time, which indicates the
fraction of the rainfall event that occurs at a given time within a 24-hour precipitation event. This
synthetic distribution develops peak rates for storms of varying duration and intensities. The SCS
distribution provides a cumulative rainfall at any point in time and allows volume-dependent routing
runoff calculations to occur. These calculations are included in the appendices.
The watershed boundaries for calculation purposes are divided according to the proposed site
grading and the natural limits of the drainage areas. The curve numbers (CNs) and times of
concentration for the existing and proposed subcatchment areas are based on the soil type and the
existing and proposed cover conditions at the site.
Calculations were performed for the 2-, 10-, and 100-year frequency storms under existing and
proposed conditions. The results of the calculations are presented in Table 1 below. Appendix C
presents the HydroCAD output reports.
Table 1. Runoff Summary Table for Individual Control Points
Condition &
Point of Analysis
2-Year Storm
3.00”
10-Year Storm
4.50”
100-Year Storm
6.40”
Peak Flow Rate(cfs) Peak Flow Rate(cfs) Peak Flow Rate(cfs)
Existing
To West Property Line
(CP1)*
2.54 6.92 13.49
Proposed
To West Property Line
(CP1)*
2.33 6.75 12.96
Existing
To East Property Line
(CP2)*
0.35 0.91 1.75
Proposed
To East Property Line
(CP2)*
0.34 0.80 1.68
Burts Bog Limited Development – Burts Pit Road April 18, 2017 (Revised June 6, 2017)
Northampton, Massachusetts Stormwater Management Report
The Berkshire Design Group, Inc. Page 6
Condition &
Point of Analysis
2-Year Storm
3.00”
10-Year Storm
4.50”
100-Year Storm
6.40”
Peak Flow Rate(cfs) Peak Flow Rate(cfs) Peak Flow Rate(cfs)
Existing
To Roadway, Flowing West
(CP3)*
0.05 0.11 0.20
Proposed
To Roadway, Flowing West
(CP3)*
0.13 0.27 0.47
Existing
To Roadway, Flowing East
(CP4)*
0.06 0.15 0.28
Proposed
To Roadway, Flowing East
(CP4)*
0.05 0.11 0.20
*Names in parentheses refer to HydroCad model and calculations.
Table 2. Runoff Summary Table For Total Site
Condition &
Point of Analysis
2-Year Storm
3.00”
10-Year Storm
4.50”
100-Year Storm
6.40”
Peak Flow Rate(cfs) Peak Flow Rate(cfs) Peak Flow Rate(cfs)
Existing
Total Runoff (CPT)* 2.91 7.91 15.41
Proposed
Total Runoff (CPT)* 2.78 7.77 15.07
The model predicts that peak flow rate from the total site will be reduced relative to the existing
condition under each design storm. The model also predicts that peak flow rate crossing the east
and west property lines will be reduced relative to the existing condition. Flow rate to the roadway
(CP3 and CP4) is predicted to increase. The drainage area to the roadway is small and this runoff is
primarily generated by driveway aprons, which must be sloped toward the road to maintain gutter
flow.
Water Quantity – Volume
The site is underlain entirely by soils belonging to Hydrologic Soil Group C. Therefore, the
Northampton Stormwater Ordinance requires only that stormwater infiltration be achieved to the
greatest extent practicable. Due to the use of rain gardens as a primary means of stormwater
management, the proposed system is anticipated to result in relatively high levels of infiltration. The
results of the HydroCAD model for stormwater runoff volume in the existing and proposed condition
are presented in Table 2 for the 2-year design storm.