Loading...
1. Hospital Hill-Smith College engineering studio-2021 Feasibility Study of the Northampton State Hospital Shared Use Path Revision D: Archival May 14th, 2021 Smith College Picker Engineering Program Design Clinic 2020-2021 Ruth Penberthy, Barb Garrison, Christian Madrigal, Karena Garcia Sponsored by The Northampton Office of Planning and Sustainability NOPS Liaison Wayne Feiden MRGI Liaison Gabriel Immerman Technical and Liaisons and Advisors Catherine Mulhern, Aaron Rubin, Susannah Howe ii Executive Summary The following document reports on the work that was conducted during the 2020-2021 academic year. It provides the Northampton Office of Planning and Sustainability (NOPS) and the Mill River Greenway Initiative (MRGI) with a conceptual design for a bridge and a path along the Mill River. Background information on the project and a brief historical overview of the area is provided. The area as it currently exists is introduced with maps and photos. Stakeholders including NOPS, MRGI, and the greater Northampton community as well as their needs are discussed. These needs help guide the design considerations while more standardized design requirements are generated from relevant codes, standards, regulations, and laws. Field work at the proposed bridge location is presented and includes a preliminary geotechnical analysis and conclusions on soil strength. Other field work done for the path at large included site visits, collecting elevation data, and slope analyses. The major findings are found in the body of the report and the in-depth technical analyses are in the appendix. Further research was conducted on the bridge and path regulations from governing bodies and engineering disciplines. These findings are discussed and supplemented by geological information found from the site. The conceptual design process for the bridge began with concept generation, expanded to specific preliminary options, and concluded with more detailed work found in the appendices. These options included a steel, bowstring truss pedestrian bridge with a possible lookout, a steel Pratt truss with art along the structure, and a simple steel Pratt truss. The option that was ranked most highly was the bowstring truss pedestrian bridge. The lookout was not considered due to the final truss and railing design to be under or around eye level. CAD visuals and renderings for this selected option are in the body of the report while more detailed drawings are located in the appendix. A footing design for a shallow foundation is in the body of the report. Work completed on the shared use path design includes a grading and drainage analysis with possible solutions that follow the design requirements. In the report body, each area of concern on the path is presented as the current issue and the recommended solution using maps, renderings, and written findings. Additional detailed path visuals are located in the appendix. Additional research and completed work for all of the mentioned subjects as well as supplemental and detailed work that is left out of the body of this report is provided in the relevant section of the appendix. iii Acknowledgements Before recognizing those who helped us along the way, we would first like to acknowledge that this project is based on Nonotuck land. We would also like to acknowledge the neighboring Indigenous nations as well such as the Nipmuc and the Wampanoag to the East, the Mohegan and Pequot to the South, the Mohican to the West, and the Abenaki to the North.1 We would then like to thank all of those who helped make this project and experience possible, including but certainly not limited to our liaisons, Gaby Immerman, Catherine Mulhern, and Wayne Feiden, and our Design Clinic Teaching Team (DCTT), Susannah Howe, Aaron Rubin, and Mike Kinsinger. Gaby provided constant support and challenged our team to think about how we could bring the community together in this space, Catherine gave us a much needed crash course on structural design, and Wayne answered all of our many questions we ran into along the way. All of the DCTT members are incredible examples of engineers and their professionalism, confidence, and expertise were traits members of NOPS/MRGI tried to and will continue to try to emulate everyday. We would also like to give a special thanks to supportive faculty and staff on this project - Tracy Tien and Jon Caris from the Smith College Spatial Analysis Lab who helped us with essential GIS material, Sue Froelich who provided waders for important Mill River visuals, and Reid Bertone-Johnson who provided excellent guidance and feedback on said visuals. Last but not least, we would like to thank our friends, family, and peers for their support on this project. Their questions about what we were up to, encouraging words, and attendance at quarterly presentations meant the world to us. 1 https://www.fivecolleges.edu/natam/about-kwinitekw Last Accessed 4/28/21 iv Table of Contents Executive Summary ii Acknowledgements iii 1. Introduction 1 2. Background and Motivation 2 2.1 History 2 2.1.1 Northampton State Hospital 3 2.1.2 Wireworks Factory 4 2.2 Motivation 5 2.3 Existing Paths 6 3. Project Stakeholders and Needs 10 4. Design Requirements 10 5. Design Development & Refinement 12 5.1 Overall Process 12 5.2 Existing Information 14 5.2.1 Familiarization with Civil Design Process 14 5.2.2 Trail Accessibility Guidelines 15 5.2.3 Site Geology 15 5.2.4 Site Elevations 15 5.2.5 Bridge Span and River Geometries 16 5.3 Field Work 18 5.3.1 Geotechnical Work 19 5.3.2 Site Visits 21 5.4 Conceptual Design and Selection 26 5.4.1 Pedestrian Bridge - Initial Concept Generation 26 5.4.2 Truss Bridge - Options and Final Selection 30 5.4.3 Decking Material 33 5.4.4 Bridge Structure and Beam Sizing 35 5.4.5 Abutments and Footings 37 5.4.6 Shared Use Path - Concerns and Solutions 39 v 5.4.7 Shared Use Path - Bridge Connection 48 6. Final Design and Deliverables 49 7. Cost Analysis 57 8. Future Implementation 59 9. Summary 60 Appendix A: Gantt Charts 62 Appendix A1: Fall Gantt Chart 63 Appendix A2: Spring Gantt Chart 64 Appendix B: Traceability Matrix 65 Appendix C: Stakeholder and Design Requirement Development 66 Appendix C1: Stakeholder Development 66 Northampton Office of Planning and Sustainability 66 Mill River Greenway Initiative 67 Northampton community 67 Local environment 67 Appendix C2 Design requirement development 68 Appendix C2.1 Trail Accessibility Guidelines 68 Appendix D: Site Visit Photos 74 Appendix D1: February 28th 2021 74 Appendix D2: March 6th, 2021 77 Appendix D3 March 10th, 2021 79 Appendix D4: March 22nd, 2021 80 Appendix D5: March 29th, 2021 82 Appendix E: Preliminary Path Slope and Grading Analysis 84 Appendix E1: Problem Statement 84 Appendix E2: Methods 85 Appendix E3: Results and Discussion 87 Appendix E3.1: Section A 89 Appendix E3.2: Section B 90 Appendix E3.3 Section C 91 vi Appendix E3.4 Section D 92 Appendix E4: Discussion of Preliminary Analysis 93 Appendix E5: Conclusion 97 Appendix F: Refined Path Slope and Grading Analysis 99 Appendix F1: Problem Statement 99 Appendix F2: Entire Existing Path Elevation 99 Appendix F2.1: Methods 99 Appendix F2.2: Results and Discussion 101 Appendix F3: Slope Areas of Concern Analysis and Solutions 102 Appendix F3.1: Methods 103 Appendix F3.2: Results and Brief Discussion 103 Area of Concern A 103 Switchback Suggestion 105 Area of Concern B 107 Area of Concern C 110 Area of Concern D 113 Appendix F4: Overall Suggestions for Existing Path 116 Appendix G: Geotechnical Literature Review 117 Appendix G1: Bearing Capacity 117 Appendix G2: Settlement 121 Appendix G3: Scour 123 Appendix H: Geotechnical Analysis of Proposed Bridge Site 127 Appendix H1: Various Geotechnical Tests 127 Appendix H1.1: First Field Test, 10/4/2020 127 Appendix H1.2: Second Field Test, 11/14/2020 134 Appendix I. Footing Calculations 142 Appendix I1: Bearing Capacity 143 Appendix I2: Contact Pressure 145 Appendix I3: Retaining Wall 146 Appendix J. Truss Research 149 vii Appendix J1: The K Truss 150 Appendix J2: The Warren Truss 150 Appendix J3: The Pratt Truss: 154 Appendix J4: The Baltimore Truss: 154 Appendix J5: The Howe Truss: 154 Appendix J6: The Bowstring Truss: 155 Appendix K: Decking Material Research 158 Appendix K1 Wood: 158 Appendix K2: Steel 158 Appendix K3: Concrete 159 Appendix K4: Fiber Reinforced Plastic (FRP) 160 Appendix K5: Decking Selection - Matrix Scoring 163 Appendix L. Superstructure Concept Selection 164 Appendix L1: Bridge Concepts 164 Appendix L2: Initial Evaluation 164 Appendix L2.1: Reference Concept 164 Appendix L2.2: Rating Scales 166 Appendix L2.3: Weighted Criteria 167 Appendix M: Superstructure Design Analysis - Dimensional Calculations 168 Appendix M1: Loads and Hand Calculations for Beam Sizing 168 Appendix M2: Finite Element Analysis - Created by Technical Liaison Catherine Mulhern 179 Appendix N: Visuals - GIS Maps 190 Appendix N1: Current/Final Maps 190 Appendix O: Visuals - Footing CAD Designs 196 Appendix P: Visuals - Superstructure CAD Designs & Drawings 199 Appendix Q: Brief Ecological Impacts 205 Appendix Q1: Permitting 205 Appendix Q2: Wetlands Protection Act 206 Appendix Q3: Priority Habitat 207 Appendix Q4: Agricultural Land 208 viii Appendix R: Cost Analysis 210 Appendix S: Drainage Matrix 211 Appendix T: Legislative Presentation 215 1 1. Introduction The Northampton Office of Planning and Sustainability (NOPS) and the Mill River Greenway Initiative (MRGI) have partnered with Smith College Design Clinic to create a conceptual design for a bridge and shared-use path. The path will establish a connection from Village Hill/Hospital Hill to the nearby Bay State neighborhood as seen in Figure 1. As a whole, the project will allow safe access to and across the Mill River for pedestrians and bikers, provide a car-free route for commuting students of Northampton High School, and will move the city of Northampton closer to its net carbon neutral goals. Figure 1: Open street map view of existing trail from the Smith College athletic fields to where it ends near the abandoned Wireworks factory. This project is part of a greater mission within the Commonwealth of Massachusetts to connect shared-use paths across the state, spanning from Cape Cod to the Berkshires. Locally, the City of Northampton’s comprehensive Open Space, Recreation, and Multi Use Plan 2 includes trail extensions, modifications, and additions including culverts and bridges similar to this project. The city is eager to show the Commonwealth and the local community how this project will bring the community together and improve the quality of life in the Pioneer Valley. The project is many years away from construction. The work completed during the 2020-2021 academic year includes a conceptual design for the shared use path and pedestrian bridge as well as a presentation to give to NOPS to gain legislative support and aid in securing funding and 2 https://www.northamptonma.gov/DocumentCenter/View/1812 Last Accsessed 10/21/20 2 public approval for the project. The conceptual design includes an analysis of the current path conditions with suggestions on how to adjust grading to meet ADA standards, a pedestrian bridge designed to withstand various loading conditions, CAD drawings, substantiating calculations, photo illustration renderings, an environmental impacts report, and a preliminary cost estimate. The presentation for NOPS includes a description of what the process is to make this conceptual design a reality. It includes graphics that promote this project’s potential with the hopes of raising community interest and helping local government officials understand what needs to happen next. 2. Background and Motivation This section contains site history and discusses the communities impacted by this project. The stakeholders and their needs are identified and contextualized within the purpose of the project and design requirements. 2.1 History An important mission of MRGI and this project is to connect people to the history of the Mill River. The river, which provided water and power for early farmers and industry in Northampton, is a vital and necessary part of our local landscape. As seen in Figure 2, there are two historic sites at the east and west boundaries of the site: the Wireworks Factory to the east and Village Hill/Hospital Hill (previously home to the Northampton State Hospital) to the west. Figure 2: Historic and relevant sites, agricultural land, and the existing path near the Mill River. 3 Before European colonists arrived, the area around present-day Northampton was inhabited by the Nonotuck people. They lived in settlements on top of Fort Hill, Meetinghouse Hill, and Hospital Hill.3 They planted corn in the flat places between the hills, including on what is now the Smith Athletic Fields. In the 17th and 18th centuries, the Nonotuck were displaced by European colonists, who chartered the town of Northampton in 1654. The Mill River’s rushing waters powered textile mills, paper mills, and other industries making Northampton grow. The river flooded frequently, destroying mills and endangering lives. Flooding and its subsequent destruction were still issues well into the 20th century, which prompted the U.S. Army Corps of Engineers to divert the Mill River away from downtown Northampton to its present banks in 1940. 2.1.1 Northampton State Hospital In 1858, a hospital for the mentally ill was built on the outskirts of Northampton 4 (See Figure 4). It had luscious grounds and an innovative architectural design, meant to rehabilitate patients in the Moralist tradition. Due to under-resourcing and delays in responding to medical advances, the hospital became progressively larger and more crowded. Figure 3: Photograph3 (date unknown) of the early Northampton State Hospital buildings, which would become the core of a much larger complex as the hospital expanded. 3 http://millrivergreenway.org/the-river-2/a-short-history-of-the-mill-river-greenway/ Last Accessed 10/20/2020 4 https://northamptonstatehospital.org/ Last Accessed 10/23/2020 4 After the establishment of the Northampton Consent Decree, which declared that mental health patients at state hospitals had a right to receive care in the least restrictive environment possible,5 the hospital was ordered to reduce its patient load to 50 in 1978. After years of financial difficulties and changing medical models, the hospital closed its doors in 1993. The state hospital was surplused and made available for sale in 1994 by Chapter 86 of the Acts of 1994. In a nationwide search for developers, the Commonwealth received no economically viable sustainable reuse proposals and the core of the facility, Old Main, was demolished despite a significant community effort to save it in the summer of 2006 and 2007. Some of the administrative and residential buildings survived, and the area formerly occupied by the hospital is now a mixed-use development called Village Hill.6 2.1.2 Wireworks Factory The Wireworks is a semi-abandoned industrial complex on Federal Street next to the proposed bridge location. Local historian John Sinton reports that it started as a paper mill for the nascent Hampshire Gazette, which was founded 1786 in the wake of Shays’s Rebellion. The paper mill was built so the Gazette could spread its anti-rebellion agenda through the Pioneer Valley. Later, it became home to a wire factory, which gives the site its colloquial name. The facility has changed hands several times since then and is now owned by local landowner, Herb Berezin. The Wireworks currently houses a driving school, but large abandoned brick and concrete buildings and a vacant parking lot remain (see Figure 4). 5 https://www.mamh.org/advocacy/legal-advocacy/olmstead/rights-to-community-living Last Accessed 12/8/2020 6 https://valleyadvocate.com/2007/10/25/how-not-to-save-old-main-part-two/ Last Accessed 10/23/2020 5 Wireworks Parcel Plan View Isometric View Closer Isometric View Figure 4: Present-day Wireworks land parcel and aerial views 7. 2.2 Motivation The Commonwealth of Massachusetts and its Department of Conservation and Recreation have a vision to connect the state through a network of trails and greenways reaching from Cape Cod through Metropolitan Boston to the Berkshires 8. Many regions of Massachusetts, including Northampton, have begun to make this greenway a reality by building, expanding, and improving their trail networks. Part of Northampton’s trail network is a shared use path, accessible to bikers and walkers, which extends into parts of Easthampton, Southampton, and Hadley, as well as Village Hill, Florence, and Leeds, which are villages within Northampton. 7 https://quantumlisting.com/listings/the-wireworks-building Last Accessed 4/16/21 8 https://www.mass.gov/doc/commonwelth-connections-report/download Last Accessed 12/8/20 6 This shared use path network has connected 70% of Northampton residents 9 to shared use paths, which in some areas, runs right along the historic Mill River. The State Hospital Shared Use Path would provide a vital link to this network because it would expand use of the trail network by making the already popular river and adjacent open space more accessible. Just as important, it would reconnect the public with the outdoors, local history, and scenery of the Mill River. 2.3 Existing Paths The Pioneer Valley, consisting of Hampden, Hampshire, and Franklin counties, is home to an existing and expansive shared use path network 10. Looking more closely in Northampton, the project motivation becomes clear. In Figure 5, the red square approximately outlines the boundaries of the project. Figure 5: Pioneer Valley bike map with the project site contained in the red square. 9 https://www.northamptonma.gov/1346/BikeWalk-Trails Last Accessed 10/21/20 10 https://ma-northampton.civicplus.com/DocumentCenter/View/11125/Bicycle-Map-regional Last Accessed 4/27/21 7 From Figure 5, it is important to observe that there are shared use paths (purple lines) around the red box but there are none inside the box. However, although it is not considered a shared use path, there is a trail that does exist in this area. That existing trail can be seen in Figure 2. There are multiple access points to this existing trail. For consistency, the trail’s starting point will always be at the Smith College Athletic Fields entrance. Figure 6, provides a visual of this entrance as well as its location on the map. The yellow box highlights the rusty, chain link fence that exists at this entrance. Figure 6: The Smith College entrance to the existing path. Moving west along the existing path, the next marker indicates the Village Hill asphalt connection to the existing path. Figure 7 shows what this entrance currently looks like. To the left of the caution sign is the Village Hill residential community. In front of the sign where the photographer was standing is where the existing path lies. The caution sign indicates the end of the asphalt path. 8 Figure 7: The entrance to the existing path from Village Hill. Moving further west past the first agricultural field, the historic Ice Pond is visible from the existing path. The yellow circle in Figure 8 highlights the historic infrastructure. Figure 8: The historic Ice Pond. When moving past the Ice Pond and continuing north, pedestrians pass a second agricultural field which indicates the Wireworks factory is near. Figure 9 provides visuals for that view. 9 Figure 9: Point of view while facing north towards the Wireworks factory. Here the photographer is standing north of the Ice Pond but still south of the second agricultural field. The end of the existing path is near the Wireworks factory. Figure 10 shows both the approximate proposed bridge site, and the Wireworks in one image. Figure 10: Visual of the approximate bridge site to the left and the Wireworks boxed in blue on the right. Wireworks 10 While the existing trail currently provides users with a scenic view of the river, the purpose of the proposed shared use asphalt path is to increase this area’s accessibility for not only more people to enjoy recreationally, but to also provide carbon-free transportation options. Paving the path and building a bridge will allow a broader demographic of community members to engage with the river. People with mobility challenges will be able to witness the flow of the river. A paved, drainable, and plowable surface will invite pedestrians to use this route any time of the year without worrying about mud or snow. This public works project puts the needs of the community and their comfort first while keeping the preservation of the landscape at the forefront. 3. Project Stakeholders and Needs The major stakeholders in this project are the Northampton Office of Planning and Sustainability (NOPS), the Mill River Greenway Initiative (MRGI), the greater Northampton community, and the local ecology. In depth details about each of these stakeholder needs can be found in Appendix D, but Table 1 below summarizes them. Table 1: Summary of the project’s stakeholders and their needs. Stakeholder Needs NOPS ● Existing agricultural land and ecosystem is not disturbed ● Americans with Disabilities Act Compliance (10’ minimum path width, 5% grading) ● Emergency vehicle path access ● ~$4 million budget MRGI ● Historic sites are preserved ● Project alignment with mission statement Northampton Community ● Trail accessibility and safety Local Ecology ● Minimize scour, erosion, and water contaminants 4. Design Requirements The project summary provided to the team in the beginning of the academic year stated several key design requirements. The team conducted additional research to address all the requirements that state regulators, federal regulators, and the community would have for this project. It is important to note that bridge construction and construction on wetlands or near farmlands are highly regulated in Massachusetts (see Appendices C2.1 and Q). 11 Key design requirements 11 for the trail include: ● Durable surface: The trail should be paved in a durable material which permits easy biking, wheelchair access, and walking. The city prefers an asphalt surface. ● Grade: The trail must maintain a grade of 4.5% or below, as specified in the Americans with Disabilities Act (ADA). Short sections of the trail can go up to 8% grade, but this should be avoided if possible. ● Cross Slope: The trail tread should be outsloped (sloped away from the hillside) by 2%. This will allow water that comes on to the trail to flow off downhill and not be channeled down the trail. ● Width: The path must be at minimum ten feet wide, and may decrease to eight feet if ten feet is physically impossible. The following design requirements are necessary for trails, however due to the landscape and grading around our region, these requirements were satisfied purely by the natural landscape. No further design work was needed to satisfy these requirements. ● Grade Reversals: While the trail will generally follow the contour of the land, it will also most likely either be climbing or descending slightly. However, a sustainable trail should also reverse its grade often (from down to up and vice versa, “surfing the hillside”). This will reduce the watershed of any given section of trail, prevent water from collecting and running down the trail, and reduce any erosion potential. Most trails should include grade reversals every 20 to 50 feet. ● Half Rule: A trail’s grade (percent slope) should not be any greater than half the grade of the hillside that it contours along. For example, if the slope of the hill the trail runs along is 16%, then the grade of the trail should be no more than 8%. This will allow water to flow across the trail, off the trail and continue down the slope. This is especially important along gentle slopes. The key requirements for the bridge are heavily impacted by the loads it will potentially experience which can be grouped into dead loads and live loads. A dead load includes any load permanently attached to the bridge including its own weight and its abutments. A live load is the weight of people, vehicles, and other moving objects on the bridge. The live loads considered are 11 https://www.mass.gov/doc/dcr-trails-guidelines-and-best-practices-manual/download LastAccessed 10/21/20 12 those from the Strength I scenario referenced in the AASHTO LRFD Bridge 12 Design Specifications, (“AASHTO Highway”) which are: ● Pedestrian Live Load: The bridge must withstand the weight of a tightly packed bridge, up to 90 psf as specified in the AASHTO LRFD Manual for Pedestrian Bridges. ● Vehicular Live Load: The bridge must withstand the weight of an ambulance or maintenance vehicle at any point along the bridge. ● Dead load: The bridge must withstand its own weight. Strength I is the main scenario being considered because it is the load combination that is appropriate for a design in its conceptual phase such as this one. It is a conservative enough approach to make an educated attempt at structural design. The bridge must also consider flooding conditions in the region to understand any further design constraints or requirements. Considering the 100-year flood is adequate for a conceptual design. The analysis will ensure there is free-board over that flood elevation. 5. Design Development & Refinement This section aims to demonstrate the process of how the conceptual designs of the bridge and path reached their final designs. The section begins with an overview of the work done throughout the year then moves into more details about that work. Existing conditions are investigated and that information along with field work helped inform decisions made for the conceptual designs of both the bridge and the path. 5.1 Overall Process The academic year was split into five periods - quarters 1 and 2 in the Fall 2020 semester, J-term, and quarters 3 and 4 in the Spring 2021 semester. Table 2 lays out the general workflow process by section. Due to the COVID-19 pandemic, most of the work for quarter 1, quarter 2, and J- term was done remotely. Ruth Penberthy was the only team member on-site during Fall 2020. All four team members were on campus for quarters 3 and 4 during the spring. This impacted the way in which work was done since it was not feasible for all team members to visit the site until February 2021. 12 American Association of State Highway and Transportation Officials, LRFD Guide Specifications for the Design of Pedestrian Bridges, December 2009, Last Accessed 4/28/21 13 Table 2: Summary of work by quarter. The four cells on the top of the matrix point to the four quarters of the year with their respective task directly below. Quarter one heavily focused on research and information gathering. Learning more about the site, its history, and stakeholder needs was prioritized. Preliminary points of concern on the path were identified and information was sourced on the civil design process and pedestrian bridges. Understanding what potential soil analyses were needed was also underway. This quarter heavily focused on creating organized project structure and developing a loose plan and schedule for the quarter two, J-Term, and quarter three. In quarter two, more specific work on the type of river crossing was completed, the fundamentals of geotechnical analyses were reviewed, and a plan to test the soil near the proposed bridge site was drafted. The preliminary points of interest identified in quarter one were explored more, and it was discovered that the major concerns were due to noncompliant grading and a drainage concern. By the end of quarter two, it was concluded that a prefabricated truss pedestrian bridge would be used. During January recess, the data collected from the geotechnical testing in quarter two was analyzed. The conclusion that resulted from the analysis was that the soil was mostly cohesionless, which led to the conclusion that there would be no major issues with construction 14 in the area. This is discussed more thoroughly in section 5.3. Field Work, and a full report on all geotechnical work conducted is in Appendix H. Additionally, Preliminary 2D and 3D versions of the bowstring truss and parts of the path began to be created with best guesses for many of the dimensions. In quarter three, the structural analysis of the bowstring truss began and visuals using CAD SketchUp, and ArcGIS Pro were created. For each identified area of concern on the existing path, solutions were explored and brought back to the liaisons for feedback. Based on that feedback and the research done by team members, solution recommendations were made. These solutions included switchback routes, drainage options, and cut and fill. The end of quarter three marked the end of any large scale technical design changes for either the bridge or the path. At the end of the quarter, all visuals that would be used for final deliverables were near complete. Quarter four’s focus was to finish the final designs for the bridge and the path based off of the feedback received from the two design reviews from quarter three. The final designs are in section 6. Final Deliverables. The end of quarter four was dedicated to documentation of the ecological impact, cost analysis, and all other general documentation needed to fully represent the work completed throughout the academic year. The final deliverables that were completed include this final written report, a final presentation delivered on May 5th, a presentation for the project liaisons to have for legislative and funding purposes (found in Appendix T), a poster, and an additional archival report. 5.2 Existing Information This section describes the work needed for the bridge and path design and starts with an understanding of the general civil design process used to shape the year’s work. It discusses the existing requirements for designing an accessible shared use path, existing soil conditions found with preliminary field work, an analysis of the site’s current elevation data, and the present-day river conditions. 5.2.1 Familiarization with Civil Design Process There are approximately four phases of a civil engineering project from the perspective of an engineer: conceptual, design development, construction documentation, and construction. It was made clear that this project is the first conceptual phase. Since this is preliminary design work, basic soil data is collected and a rough structural layout for the bridge is developed. The structure’s footprint is laid out, path routes are decided, and systems within the project are defined. Understanding the extent of the project’s work helped narrow the scope of the project as it allowed for more flexible design and less strict detailed work. Where applicable, educated attempts and assumptions were made and details such as joint connections for the bridge or exact construction drawings for the path were not included in the project scope. 15 5.2.2 Trail Accessibility Guidelines With a project receiving funding from the federal, state, and local governments, it is expected that this activity follows specific guidelines that these organizations must uphold. This stipulation directly applies to this project as it is receiving funding from the federal, state, and local levels of government. In order to comply with these gubernatorial standards, research was conducted on what guidelines would be impacting the design of the trail and bridge. There are many guidelines at each level of government when it comes to the accessibility of shared use trails and bridges. Appendix C2.1: Trail Accessibility Guidelines discusses the key guidelines from each level of government respectively. Table C1 in Appendix C2.1 includes (but is not limited to) links to resources that contain guidelines and provides more detail than this section. The information in Appendix C2.1 can be summarized by the following bullet points: ● The United States Forest Service Trail Accessibility Guidelines (FSTAG) legally pertains to trails within National Parks. ○ This project is not in a National Park, but the FSTAG does provide reasonable technical provisions acceptable to the state and local levels. ● The main two guidelines to consider for trail accessibility are its surface and its slope. ● State guidelines legally pertain to trails in state parks. ○ This project is not in a state park but should follow the state guidelines, which closely resemble, if not completely adopt, the national guidelines. ● Softer technical provisions on sustainable trail design are provided in the Department of Conservation and Recreation’s Trail Guidelines and Best Practices Manual. 5.2.3 Site Geology According to ArcGIS data, the soil at the proposed bridge site on the eastern bank of the river near the Wireworks Factory was categorized as Pootatuck fine sandy loam whereas the western bank of the river near the agricultural fields was said to be made up of both Rippowam fine sandy loam and Pootatuck fine sandy loam. This meant that the western side, where one of the bridge abutment foundations would be located, consisted of granular soils that were well drained year-round. It is important to note, once again, that this information was obtained from ArcGIS data. These soil characteristics were checked and discussed further in section 5.3 Field Work. 5.2.4 Site Elevations The path elevations were obtained using ArcGIS Pro software. These elevations were relevant for redesigning areas with poor drainage, finding a route to pave, and ensuring the path was compliant with ADA grading. A preliminary analysis of elevation began with identifying the location of areas that exceeded an ADA compliant grade. This analysis is detailed in Appendix E. This general elevation analysis was quickly refined using the existing path which is depicted in Figure 1 in section 1. Introduction and the elevation profile in Figure 11 was used to 16 identify major areas of concern. This figure is not in true scale in order to better visualize the elevation variation. The true scale elevation profile is located in Appendix E along with other details on how this figure was produced. Figure 11: Elevation profile that details the variation of the existing path as one travels from the Smith Athletic Fields towards the proposed bridge site. As mentioned, this elevation profile was used to identify specific areas of concern. The details on the exact areas of concern are provided in section 5.4.5 Shared Use Path. 5.2.5 Bridge Span and River Geometries In Fall 2020, the bridge span was estimated to be 100 feet by visually examining the slope of the riverbed in ArcGIS online. This preliminary measurement did not reflect the exact location of the bridge or abutment placements, but it did provide a rough estimate of the bridge length. 17 Figure 12 is a preliminary visual from ArcGIS online that depicts the measurement process. The topographic basemap map is overlaid with an orange-and-white slope data layer. The dark orange seen on either side of the river represents an area of relatively steep slope compared to the lighter colored regions. By drawing a line that spanned the regions of steep slope, the team estimated that the bridge was 100 feet long. Figure 12: ArcGIS Online map depicting the bridge location. Bridge must span river banks, which are the two, dark orange parallel lines crossing the map diagonally. Saturation levels denote change in elevation. In quarter three, a more detailed look at the river’s cross section was taken, which revealed the span of the bridge needed to be 130 feet. Figure 13 shows a map with similar topographic lines as seen in the previous figure. Similarly to Figure 12, the topographic lines are quite dense on either bank. The light blue line that crosses the river and a portion of the land on either side was used to create a stack profile of the river. Then, a cross-section of the river was extracted from the profile. The resulting elevation profile from the extracted data is visualized in Figure 14. 18 Figure 13: A map of the proposed bridge site with light grey contour lines and a light blue line used to complete the Stack Profile of the river cross section. Figure 14: Complete stack profile of the river cross section with a box highlighting the riverbed cross section. The span of the bridge must comply with Massachusetts River and Stream Crossing Standards and the Massachusetts Department of Transportation (MassDOT) span of 1.2 times the length of bankfull river. The abutments can be placed in the floodplain of the river as long as they are designed to withstand possible forces they may encounter as a result (i.e. 100 year flood event). 5.3 Field Work This section discusses the field work conducted on the existing path and proposed bridge location including geotechnical testing, path concern investigations, and visual data collection. 19 5.3.1 Geotechnical Work The soil characteristics from ArcGIS were confirmed by a preliminary geotechnical analysis conducted on the west side of the river. “Introduction to Geotechnical Engineering” by Holtz and Kovacs 13 was used as a reference for the soil testing protocols and procedures. Using the samples collected, a sieve analysis was conducted and with the necessary calculations, grain size distribution graphs were created as seen in Appendix H, Figures H5 and H8. This analysis allowed the team to conclude that the soil is well graded and on the cusp of being classified as SP, gravelly sands with little or no fines, or SM-SW, sand with silt. The bridge site’s soil conditions were further analyzed during a site visit on November 14, 2020. A team used a DGSI standard hand auger and a dynamic cone penetrometer to collect soil samples and data to use for further analysis on soil strength. Five soil samples were collected, bagged, and sealed for future experimental testing. From this site visit more information was known about the conditions than the first soil test. Initial observations suggested possibilities of glacial deposits or large boulders around 8.5 feet below the ground and showed no signs of significant clay deposits. The GSD graphs for two of the deeper soil samples, C and E, are seen in Figure 15 and 16, respectively. Based on this information, the preliminary soil classification assumption of SP was confirmed for these deeper soil samples as well. With this cohesionless, dense soil assumption, there were no major concerns about the feasibility of construction. 13 Holtz, Robert D. and Kovacs, William D. “Introduction to Geotechnical Engineering.” Chapters 1, 4, 8, 9, and 10. 20 Figure 15: The grain size distribution curve for sample C. Figure 16: The grain size distribution curve for sample E. A CAD drawing of the concluded soil profile is also provided by Figure 17. Further details about this specific site visit is in Appendix H1.2. As mentioned before, this soil profile is an 21 approximation of the west side of the Mill River closest to the agricultural fields. Since it was prohibited to enter the other side of the property near the Wireworks factory, it was assumed that both sides of the river would have the same soil profile. This is a large assumption, and it is recommended that more thorough geotechnical tests be conducted on both sides of the river to ensure all existing soil information is known and accurate. Beginning in early 2021, the soil samples from the November 14th site visit were analyzed to determine soil strength and friction. With this information, bearing capacity calculations were conducted and used to make conclusions on the necessary foundation design that is further explained in Appendix I. Figure 17: CAD drawing of the approximate soil layers on the west side of the river closer to the agricultural fields. 5.3.2 Site Visits Aside from the site visits dedicated to the geotechnical field work, additional visits were conducted. One included a visit after a heavy rain storm event on the afternoon and evening of October 16, 2020. Ruth Penberthy walked the path the next morning on October 17th to see where there were any drainage or flooding issues. Most of the path was still damp but was easily walkable. There was only one area that was flooded. Its location is seen in Figure 18. 22 Figure 18: Topographical map of drainage concern area, outlined in pink, next to Village Hill. The area was flooded with approximately three inches of storm runoff that extended for approximately one-hundred feet as seen in Figure 19. This area currently has stone pavers that act as a small drain to channel water down slope, however with serious storm events this infrastructure is not suitable to manage heavier rain events and flooding. A possible solution to this issue is presented in section 5.4.6 Shared Use Path - Concerns and Solutions. 23 Figure 19: Image of flooded path with approximately 3” of rain water. Photograph by Ruth Penberthy. A similar site visit was conducted to determine important access points to the existing path. The most important gateways are those located around the Village Hill residential development and the entrance that connects the existing path to the Smith College athletic fields. There is another connection between the Northampton Community Gardens and the existing path, but they are both not immediately connected so that connection is not prioritized. In Figure 20, the start of the shared use path connection to Village Hill has been paved with asphalt. This is the same picture shown in Figure 7 in section 2.3 Existing Paths as a standalone image. In Figure 21, the Smith gateway will need development and signage to make the shared use path inviting and welcoming to pedestrians. This is also the same picture used in Figure 6 in section 2.3 Existing Paths. 24 Figure 20: Image of the Village Hill residential community connection, facing Village Hill. Photograph by Ruth Penberthy Figure 21: Image of the Smith College athletic fields gateway connection, in need of development. Photograph by Ruth Penberthy Most of the other site visits were conducted with the purpose of understanding which parts of the path are not ADA compliant due to steep grades. These visits consisted of collecting geospatial data to later analyze in ArcGIS. This field work in combination with the ArcGIS analysis helped identify the exact areas of concern and quantify how these areas were noncompliant with the 25 necessary 4.5% ADA grade. More detailed work on this is in Appendices E and F. Appendix E includes the preliminary path slope and grading analysis which was completed with approximate geospatial data provided by NOPS. Appendix F includes the refined path slope and grading analysis on the new and more accurate geospatial data collected by the team. These areas of concerns are discussed in section 5.4.6 Shared Use Path - Concerns and Solutions. Figure 22 depicts all identified areas of concern which are labeled in red as A, B, C, and D. Each section is covered individually in 5.4.6 Shared Use Path - Concerns and Solutions. Figure 22: After field work and site visits, these are the areas of concern due to grading in all parts and one drainage issue in “B.” Several hours of field work were dedicated towards resolving the first slope concern, “A.” The preliminary work for this solution is presented here because it took more experimentation during the site visits to arrive at the final solution presented in section 5.4.6 Shared Use Path - Concerns and Solutions. New paths and possible switchbacks were walked and the geospatial data were recorded using a gps smartphone app. Figure 23 demonstrates the experimental switchbacks that were walked in order to refine the final switchback. 26 Figure 23: Preliminary switchback solutions to propose for slope concern “A.” Final visits to the path and proposed bridge site were mainly done to obtain images of the site for photoshop work and using SketchUp. These images and additional site photos are in Appendix D. 5.4 Conceptual Design and Selection This section aims to clearly lay out the conceptual design and selection process for both the bridge and the path. The bridge’s process will go first, followed by the shared use path. 5.4.1 Pedestrian Bridge - Initial Concept Generation This section discusses the process of designing the pedestrian bridge. It outlines concept generation, discusses concept selection, and touches on calculations for the final product. 27 This project requires a bridge to allow pedestrians, cyclists, and the occasional vehicle to cross the Mill River. Literature review indicates that there are several bridge superstructures that could be employed in this project: cable-stayed, arch, girder, and truss. The non-bridge option for spanning the river is to lay several box culverts side-by-side (Figure 24). Figure 24: A real life example of what these side-by-side culverts would potentially look like. Bridges can vary in height, width, span, and structure, and are usually used when impeding the flow of a waterway is not an option. Culverts are similar in purpose but different in design than a bridge as culverts are typically embedded in the soil and only span about 20 feet. See Table 3 below for a summary of options. 28 Table 3: A table summarizing the initial crossing conceptual design with incompatible options in red, possible options in yellow, and best option in green. Bridge Type Diagram Appropri ate? Limiting Attributes Description Cable No Cost Expensive and optimized for longer spans. Creates higher long term maintenance needs. Arch No Height and Arch Proportional ity Arch height may become excessive after designing in ice flow clearance. Girder/ Precast Concrete Maybe Span and Aesthetics Single unit precast bridges are for short distances (<50’) without middle support and are not used as style pieces. Truss Yes Span Many different variations and appropriate span limits. Culvert No Aesthetics and Environment al Impact Large environmental impact, specifically on the river flow. All of these options, except for the truss bridge, can be ruled out because they are incompatible with basic requirements of the project. The culvert was suggested as a significantly lower-cost option for crossing the river. It is unsuitable, however, because it does not meet the environmental standards set out by partnering organizations. The Mill River Greenway Initiative and NOPS are not interested in solutions that obstruct the river, as these would harm the ecosystem and might be dangerous in river-icing conditions, and such solutions would probably not receive the necessary permits. The river 29 crossing is about 100 feet wide from bank to bank, which would require about five box culverts to cross. The more likely solution is two or three box culverts with infill to meet the road. Both solutions add hard interruptions to the flow of the river and might be dangerous in flood conditions. The appearance of the bridge is one of the major concerns for NOPS and MRGI, and the culvert option does not mesh aesthetically with the natural scenery of the path, nor the historic Wireworks site. Girder bridges can be ruled out for the same reasons as the culvert: cost and aesthetics. A precast concrete bridge would require a support in the middle of the river, which is unacceptable because it impedes flow, not to mention that a foundation in the middle of the river would greatly increase cost. A girder bridge with a girder stiff enough to support a 130 foot span would be quite deep, possibly deep enough that the bridge would be at more risk for damage from flooding or ice flow. Cable-stayed bridges are too expensive to consider, and they are not appropriate for the type of crossing in this project. Cable-stayed bridges are more economical at lengths of 200-400 feet, which is far longer than the current crossing 14. Arch bridges that place the arch below the bridge would require a very high arch for a span of 130 feet, which would result in either the feet of the arch dipping below the waterline or a very tall bridge, both of which are not good uses of money. In addition, if the arch is too low, seasonal ice blocks that flow down the river could damage the bridge. The aesthetics appeal of the arch can be captured with an arched bowstring truss. The remaining appropriate bridge option was the truss bridge. Truss bridges are common in New England, so a new truss bridge would fit aesthetically into the landscape. They are a moderate- cost option and stiff without being overly tall at the 130-foot required span. There is also significant flexibility in the arrangement of the members for achieving different aesthetic aims. This allowed for multiple truss designs to be considered as the bridge’s aesthetics and cost could be altered by manipulating these design elements. The next section will summarize the different types of truss structures being considered, pros and cons associated with them, and ultimately, the truss shapes that will be used moving forward. 14 http://www.roseke.com/types-of-pedestrian-bridges/ 30 5.4.2 Truss Bridge - Options and Final Selection A truss bridge can be made with a variety of truss layouts. Research was done on trusses for pedestrian bridges to determine which were appropriate for this project. A detailed writeup of this research can be found in Appendix J. A brief summary is provided in Table 4, below. Table 4: A summary of several truss shapes and their pros and cons. Truss Type Pros Cons K Truss Appropriate span, aesthetically unique Increased complexity, and thus, cost and time Warren Truss Simple, appropriate span, works well with distributed load Not very unique Double Intersection Warren Appropriate span, works well with distributed load Increased complexity Lattice Appropriate span, works well with distributed load Increased complexity Pratt Truss Appropriate span, commonly used, strength, statistically determinant Not very unique Howe Truss Appropriate span, commonly used, strength, statistically determinant Not very unique Bowstring Truss Appropriate span, aesthetics, commonly used Increased complexity relative to Pratt, Howe, and Warren Baltimore Truss Appropriate span, strength Common for railroads These truss types appear to be the most popular selections when it comes to trail and pedestrian bridges. The Warren, Pratt, Howe, and Bowstring Trusses were the recommended types of truss based on the presented research. The truss list was simplified further into just the Pratt and Bowstring trusses. This was done because the Warren and Howe trusses were very aesthetically and functionally similar to the Pratt truss. 31 Three main conceptual designs were generated, focusing on aesthetics and public engagement with the bridge. They varied in structural material, which truss was used, where a lookout would be, and where art could be installed. Each considered option had the following variables: ● SUPERSTRUCTURE: Bowstring truss or Pratt truss. ● STRUCTURE MATERIAL: Steel or wood. ● LOOKOUT LOCATION: Middle (see Figure 25) or Abutment (i.e. a bench or placard). ● ART LOCATION: Sides of bridge over the water, railings near abutments Figure 25: A bowstring bridge with a lookout, or “bubble”, in the middle. These three options and their combinations of variables are summarized by the following table: Table 5: The three main concepts considered for the bridge component of the project. Bowstring Option Pratt Option #1 Pratt Option #2 Superstructure Bowstring Pratt Pratt Structural Material Steel Steel Steel Lookout Location Middle Abutment None Art Location Railing near abutments Sides over water Railings near abutments These options were then placed into a concept scoring matrix of important factors and scored to quantitatively compare them, which is documented in detail in Appendix L. The selection criterion in the matrix were abutment impact, carbon footprint, construction cost, maintenance cost, visual weight, and interactive potential. ● Abutment Impact measures abutment expense. Heavier bridges or bridges that catch more wind require larger, more expensive abutments. ● Carbon Footprint is the environmental impact of bridge materials, construction process, and maintenance; this is a direct design consideration from NOPS and MRGI. 32 ● Construction Cost is the cost of initial installation, including material transportation. Budget requirements require costs that will total to less than an anticipated $4 million dollar budget per project statement. ● Maintenance Cost is the expense required to ensure upkeep of the bridge superstructure and other necessary costs to ensure longevity of the project. NOPS would like to minimize maintenance costs. ● Visual Weight subjectively considers how bulky the bridge is. Stakeholders including NOPS and MRGI value a bridge with minimal visual impact on its surroundings, so it’s important to make a bridge that is as visually “light” as possible. Lightness means slender beams and small superstructure - smallness of superstructure was prioritized over slender beams. ● Interactive Potential subjectively considers whether the bridge contains interactive elements that encourage people to spend time on or near the bridge. Showcasing the beauty of the site and getting people to spend time in nature are some of the stakeholders' priorities. Table 6: Concept Scoring Matrix Bowsting Pratt Option 1 Pratt Option 2 Selection Criteria Weight Rating Weighted score Rating Weighted score Rating Weighted score Abutment Impact 0.25 3 0.75 2 0.5 3 0.75 Carbon Footprint 0.075 3 0.225 2 0.15 3 0.225 Construction Cost 0.2 2 0.4 2 0.4 3 0.6 Maintenance Cost 0.2 4 0.8 4 0.8 4 0.8 Visual Weight 0.2 4 0.8 3 0.6 3 0.6 Interactive Potential 0.075 5 0.375 2 0.15 4 0.3 Sum Total 1 3.35 2.6 3.275 Rank 1 3 2 According to the matrix, the options from ranks first to third are Bowstring, Pratt Option 2, and Pratt Option 1. See Figure 25 (above) for a sample bridge that illustrates the chosen option. With superstructure chosen, the next steps were to decide on the decking material, structural beam sizing, and abutments. 33 5.4.3 Decking Material There are five common decking materials for pedestrian bridges: wood, steel grid, concrete, fiber reinforced plastic (FRP), and ballast. The research done on each type of decking material can be found in Appendix K. Ballast and steel grid were not viable because they prevented snow removal. The advantages and disadvantages of each viable material. are summarized in Table 7. Table 7: The different decking materials and their pros and cons. Decking Material Pros Cons Wood Rustic/natural look Inexpensive Simple/Common Longevity Maintenance Hazardous chemical pretreatment Susceptible to rot, warp, insects Concrete Simple/ Common Strength Aesthetics Environmental Impacts Maintenance FRP Lightweight Low Maintenance Non Corrosive Non Conducive Relatively Expensive Uses different tools Inexperience in industry With these pros and cons in mind, a final matrix for comparing the different decking materials was created. 34 Table 8: A weighted matrix for comparing the different decking materials. Decking Material Environmental Hazard Maintenance Impact Resistance Weight (Heaviness) Cost Aesthetics Total Wood 3 3 3 1 5 5 4.1 Concrete 2 2 5 2 5 2 2.9 Asphalt 2 2 5 2 5 2 2.9 FRP 4 5 5 5 2 5 4.05 Weight .2 .1 .05 .05 .25 .35 - The design criteria in this matrix include Environmental Hazard, Maintenance, Impact Resistance, Weight (as in heaviness), Cost, and Aesthetics. Environmental Hazard is whether the material is hazardous to the environment. Maintenance is how much upkeep is necessary. Impact Resistance is how much the material will deform permanently on impact. Weight is how heavy the material is. Cost is how much the material costs. Aesthetics is how well the material works with the natural space of the area and how well it aligns with stakeholders’ wants. ● Environmental Impact comes from both MRGI and NOPS because these stakeholders want to minimize the negative impact on the environment this bridge will have in the area. It is also the responsibility of engineers to consider the impacts their work has on the environment, so it is important to acknowledge how the decking material contributes to impacts on the environment. ● Maintenance is considered because the City of Northampton will be responsible for the maintenance of the bridge once it is installed. NOPS is an entity of the City and a major stakeholder in this project, so ensuring that maintenance will not be a cause of extra cost and annoyance is important. ● Impact Resistance comes from the fact that the bridge will experience a variety of traffic from pedestrians, bicycles, and even vehicles at times, so on a concentrated impact, the decking material should not permanently deform. The material should also be plowable, so blades from a snow plow should not damage the material. ● Weight would be a concern as far as installation goes. Heavy materials are going to need heavier equipment for hauling and installation. Lighter materials may make transportation and installation easier. 35 ● Cost is always a concern on any project and ways to minimize costs are always desirable. This project is being funded by MassDOT and other governmental funds which means there is a limited amount of money for the project. ● Aesthetics is a concern for MRGI, NOPS, and the community, and the decking color and material will contribute to the overall aesthetic of the bridge. The bridge should not seem out of place in the natural area. Ideally, the bridge will not take away from the river and the natural scenery. The rating scale chosen was a 1-5 scale for each criterion. Table K3 summarizes the 1 and 5 scores. Based on the total scores of the matrix and discussion with stakeholders, wood and FRP decking are the two ideal materials that also align with the wants of MRGI and NOPS. After further discussion with NOPS, wood was decided to be the final chosen material because of cost and the prevalence of wood decking for existing pedestrian bridges in Northampton. 5.4.4 Bridge Structure and Beam Sizing During J-term, research was done on how the floors of pedestrian bridges were structured. The goal was to practice the process of selecting beam sizes on the simple-to-analyze floor before moving on to the more complex truss. The structure for the floor was chosen from a conversation with liaison Catherine Mulhern and a visual analysis of existing pedestrian bridges. A large beam connecting each truss and on top of this, stringers in the other direction; on top of the stringers lie the deck planks. More specific details on how these structures are joined together are out of the scope of the conceptual design phase. AASHTO Highway Bridges and technical liaison Catherine Mulhern were consulted to build an understanding of the Load Resistance Factor Design methodology used by professional bridge designers. In LRFD, loads are multiplied by factors that account for uncertainty of analysis and material variability, among other things. These factored loads are added together in different combinations such as Strength I, Service IV, and Extreme Event II that simulate situations the bridge might need to withstand. From these load combinations, force effects such as shear, moment, and buckling are calculated for each component. Due to time and scope constraints, the single load combination considered was a pared-down version of Strength I that included dead load, vehicular live load, and pedestrian live load. Strength I is a standard load combination that simulates the everyday loads a structure must bear, and is appropriate for a conceptual design. Per AASHTO Pedestrian, simultaneously analyzing 36 the pedestrian and vehicular loads was not necessary, so the live load (vehicular or pedestrian) that created the greater force effect for each piece was selected. It was assumed that if the bridge could withstand these conservative loads, then this would align with the amount of information needed in the conceptual design phase. In quarter three, the components of the truss were sized. A truss has several pieces - the top and bottom chords, the vertical and diagonal cross-pieces. A truss bridge also includes the deck planks, stringers, and foot beams that comprise the floor. Hand calculations were done to determine the sizes of each floor piece, following the LRFD process. For each piece: 1. A mechanics problem was set up with a certain load, aiming to calculate a certain force effect such as shear. The load was placed to create the maximum force effect in the piece. (A truck will be in a different place to create maximum shear than maximum bending.) 2. The force effect was calculated using mechanics methods. Equations for maximum shear and moment in certain beam loading scenarios were referenced from AISC 8th ed. 3. This was repeated for other loads. 4. The force effects from dead load and the greater live load were multiplied by factors and added together to create the nominal resistance that the beam must have. 5. The factored resistance required was calculated by multiplying nominal resistance by a final factor, phi. 6. Required beam section modulus was calculated from factored resistance. 7. This process was repeated for the other force effect, and the larger of the two calculated section moduli was taken. 8. A beam with a conservative section modulus was chosen from a table of structural steel shapes. From this analysis, sizes for the floor beams were chosen. Hand calculations were laid out for the truss, but the analysis was sufficiently complex that it was deemed time-inefficient to attempt to analyze the entire truss by hand. To solve this, a finite element analysis of the truss was created by liaison Catherine Mulhern, which took loads as inputs and confirmed the sizes of each beam. See Appendix M2. Final beam sizes are given in Table 9 below. 37 Table 9: Summary of Superstructure Component Sizes Component Material Nominal Size Deck plank Douglas Fir Select Structural grade 5x10 Plank Stringer Steel C4x7.25 Floor Beam Steel W6x16 Truss Top Chord Steel HSS 12x6, 1/2" wall Truss Bottom Chord Steel HSS 10x6, 1/2" wall Truss Vertical Steel HSS 3x3, 1/4" wall Truss Diagonal Steel HSS 3x3, 1/4" wall 5.4.5 Abutments and Footings The overall process of the abutment design is discussed here, but the calculations that were necessary for the exact geometry deduction are in Appendix I. “Soils and Foundations” by Liu and Evett 15 was consulted and used as a reference throughout every step of the design process including the initial research phase, calculations, and sizing process. After it was confirmed that the project would be moving forward with a truss pedestrian bridge, work on the design of the bridge abutments and footings began. Similar to the bridge itself, the abutments and footings needed to be able to withstand the same loads, vehicular and pedestrian. A load unique to the abutments and footing especially was the load the soil imposed on the structure. Before exploring the soil loading, more information was needed on what kind of soil was present. It is important to note that the side of the river closest to the Wireworks was not accessible, so a large assumption that it shares roughly the same soil characteristics as the other side of the river was made. After collecting and analyzing geotechnical data on the site soil, it was decided that a shallow foundation would be best. Furthermore, according to the text, a continuous footing would be most appropriate for this project. Before moving on to the geometry of the footings, the approximate location for both needed to be determined. This prompted a more detailed look at the profile of the riverbed because there were two main options: have the footings closer to the river embankment, exposing the footing or further from the embankment, leaving nothing but the tops of the footing partially visible. The first option kept the span of the bridge closer to 100ft 15 Liu, Cheng and Evett, Jack. “Soils and Foundations.” Seventh Edition. Chapters 7, 13, 9. 38 which would be cheaper, but also disturbed the river embankment. The second option would lead to a longer span of the bridge, increasing cost, but would leave the river embankment virtually undisturbed. With our stakeholders in mind, disturbing the river bank was not an option, so it was decided that the footings would be further from the bank. Knowing the type of footing and general location of each footing, an initial design was drafted. This initial design was heavily based off of Soils and Foundations because in order to make adjustments, a preliminary geometry was needed. This initial footing design attempt, however, ended up being too shallow, too narrow, and technically impossible to construct. After conversations with Professor Rubin and consulting Chapter 13: Retaining Wall Structures of Soils and Foundations a more reasonable abutment design was reached. The table below summarizes the geometries of both the initial and final footing designs. It is important to notice the drastic differences in the depth and base dimensions. Figure 26 shows the detailed CAD drawing of the final design. Table 10: Summary of initial and final footing design geometries. Design Depth (ft) Base (ft) Thickness (ft) Toe (ft) Heel (ft) Initial 7 5 1 2 2 Final 24 12 2 2 8 39 Figure 26: The CAD detail for a possible footing design. 5.4.6 Shared Use Path - Concerns and Solutions The following section outlines the major concerns of the path and their subsequent solutions. These concerns and solutions are supplemented by respective maps and real pictures of the site. There are three primary issues with the trail that prevent it from being converted to a shared-use asphalt path as-is: several sections of the trail are too steep (>5% grade), there is a drainage issue on a flat portion of the site at Hospital Hill, and there is major erosion near the historic ice pond. Refining the preliminary analysis of the proposed shared use path resulted in the identification of four major regions of concerns that can be visualized by Figure 27. 40 Figure 27: Path overview with relevant markers for important landmarks along the proposed path. These sections were chosen as a result of field work on the existing trail that further confirmed these sections held potential for improvement. The main cause for concern of these path segments were rooted in suspicion that they had non compliant ADA grading. As addressed by the analyses of the four major sections of concern along the path, it was concluded that all of these sections were candidates for cut and fill. The process is as intuitive as it sounds; sections of the path that are steep would be either cut and/or filled to level the ground of the path segment resulting in a grading change that would be most compliant with ADA. On the other hand, a switchback for Slope Concern - A was explored to serve as an alternative for cut and fill. This suggested switchback would cut across as shown in Figure 29 and is about 155 meters in length. This switchback is simply an iteration of a path alternative that could be used to meet ADA compliance. It was shown as part of analyzing this switchback option, it had reduced the average grading of Area of Concern A from 7.6% to 5.5% (details in Appendix F). While the improved grading percentage did not entirely fall below the 4.5% threshold it does hold promise in reducing the average grade of this path segment significantly. Therefore, this option could be further explored when paving the shared use path. 41 Figure 28: Area of Concern A and its location along the proposed shared use path. The solution recommendation for this area of concern is a switchback. Figure 29 shows this switchback on the map in blue. This switchback option was investigated and it was concluded that a 4.5% grade would be possible. This switchback will allow pedestrians and cyclists to safely traverse down the hill to the rest of the path, but it does not mean that the concerning part of the existing path will cease to exist. Pedestrians and cyclists may still use that path; this is simply a recommendation for an ADA compliant alternative. 42 Figure 29: Area of Concern Solution - A which is a switchback that complies with ADA grading. The second region of concern was Area of Concern - B (Figure 30) which was also analyzed due to the suspected noncompliant ADA grading that was experienced as data was being collected. The analysis that is summarized in Appendix F3.2 confirms that this section of the path does not comply with ADA requirements and sits at an average grading of 6.3% across the 60 meter section. Figure 30: Area of Concern B and the location of this section along the proposed shared use path with a real-life visual for context. 6.3% 43 The drainage concern addressed in 5.3.2 Site Visits is an additional concern in section B as well. The recommended solution for this slope concern (and the following slope concerns) is to use a cut and fill methodology to reach ADA compliance (other details in Appendix F). Figure 31 provides a conceptual look as to what this area could look like if it were cut, filled, and paved. Figure 32 shows what a typical cross section of what this pavement could look like for the entire path. Figure 31: Conceptual visual of the solution for section B. 4.5% 44 Figure 32: A typical cross section of the path pavement theoretically applied to all parts of the proposed path. As far as the solution for the drainage concern, advantages and disadvantages of a culvert, permeable pavement, a cross-slope, and a vegetated swale/rain garden were reviewed (Appendix S). An overview of the pros and cons of each solution led to the conclusion that this drainage concern might be best addressed by implementing a combination of a cross slope and a vegetated swale/rain garden. This is simply a preliminary suggestion as a result of brief analysis, but this drainage concern would be better addressed with a thorough investigation of the site in future work. The third section of major concern labeled Area of Concern - C was a path section that occurs after the drainage concern and is about 100 meters in length (Figure 33). This path section was further analyzed, and it was found that the total path section had an average grading of 3.6% (Appendix F3.2). This average value is deceivingly compliant as it is below the 4.5% threshold permitted by ADA, but it is important to note that there was a 10 meter section within this path segment that had a grading average of 6.1%. Like Area of Concern - B cut and fill is suggested 45 and details are in Appendix F. Figure 33. This a map that displays the location of Area of Concern C along the proposed shared use path. Moreover, there is a steep dropoff on the left side of the path closest to the agriculture fields. A fence along this steep dropoff is thought to be an important safety measure. On the less technical side, this part of the path offers an expansive view of the agricultural fields which could be a prime location for signage that informs passersby of the importance and history of the land. Figure 34 shows what this design solution could potentially look like. 6.1% 46 Figure 34: A possible rendering of the solution for part C. The last section of concern was located near the historic Ice Pond and is pinpointed by Figure 35. This section is known as Area of Concern - D, a 60 meter long section along the path closer to the site for the proposed pedestrian bridge. For this portion of the path it was also confirmed that the 4.5% ADA grade requirement was not met and had an average grading of 4.8% (Appendix F3.2). In addition to the slope concern here, there is also an erosion issue (Figure 36) as well as some existing infrastructure near the area. These two issues are not explicitly addressed in this report, but a fence would be ideal near the erosion concern; not to control the erosion, but to provide a safe barrier from the steep slope that is near this area. Overall cut and fill is suggested for this region and details on a suggested profile are in Appendix F. 47 Figure 35. The final area of major concern along the proposed shared use path highlighted on the map of the proposed trail. Figure 36: The erosion issue near the Ice Pond. Figure 37 shows what this path could possibly look like once properly graded and paved. There is also some signage present on the bottom right hand corner that could serve as a place where pedestrians can learn more about the historic Ice Pond. 4.8% Erosion 48 Figure 37: Paved and graded solution to the Ice Pond area with signage informing the public on this site’s history. 5.4.7 Shared Use Path - Bridge Connection The final part of the path not yet covered is how it connects to the bridge. Figure 38 shows what the path could look like as it rounds the corner toward the bridge, but not quite close enough to see it. Here, it is important to notice the signage that should be posted that indicates which way the bridge is. Figure 38: Possible shared use path headed toward the bridge. 49 Rounding the corner of this path, the bridge becomes visible and the approach comes into view. A scaled rendering of this is presented in Figure 39. Figure 39: The front view of the bridge with its connection to the shared use path in view. 6. Final Design and Deliverables The final design for the shared use path is pictured below in (Figure 40). The route generally follows the existing footpath from Smith College to the Wireworks Factory. The new design solves Slope Concern - A by avoiding a piece of the existing path with a new, less steep switchback section. The design solves slope issues B, C, and D by regrading the trail at those locations. 50 Figure 40: Map of Proposed Shared Use Path Route. Map shows final path route, bridge, and landmarks over an OpenStreetMaps basemap to highlight how the project fits in to the existing trail network. Connection to Smith College is highlighted in purple. This section includes a summary of the final deliverables for both the path solutions and the bridge design. The process of how these solutions and designs were created was covered in the previous sections of the report thus far, and even more detailed notes on individual steps can be found in the appendices. That being said, most of this section will include finished renderings of proposed design solutions created in SketchUp. Per the Project Summary, it was expected that at the end of the year, the team would provide the following: ● Conceptual bridge design that details aesthetics of the bridge along with chosen materials and truss type. ● Conceptual trail design summarizing points of major concern alongside suggested methods of addressing them. ● Computer Aided Design (CAD) drawings of the bridge abutments and trail ● Calculations to substantiate engineering decisions made on bridge and trail ● Compelling renders of both the bridge and trail for public consumption ● Presentation to pitch the project to funding agencies and community 51 Going bullet-by-bullet, the conceptual bridge design, its truss type, materials, and thus, aesthetics, were covered in section 5.4 Pedestrian Bridge but is summarized again under the bridge visuals provided. Figure 41: The final conceptual bridge design. Similarly, section 5.4.6 Shared Use Path - Concerns and Solutions summarized the major concerns and solutions to the trail, but the specific SketchUp visuals for each solution are presented below. Pictured below is the cut and fill solution to part B. This rendering was done in SketchUp and includes an example of what the path could look like with asphalt pavement. The design calls for a two foot shoulder on either side of the path, but in this perspective, only the shoulder on the left side of the path can be seen. 52 Figure 42: Solution for part B of the path, cut and fill to correct grading and an asphalt pavement. The next image is a SketchUp rendering of the solution to part C of the path. As mentioned previously, although the average grade along this part is 3.6%, there is a portion that is 6.1%, so some cut and fill will be needed. Also, a possible wooden fence was added to this area because on the side of the path with the fence, there is a steep drop off that users should keep a safe distance from. This fence provides a physical safety barrier and doubles as future erosion control. Something that should also be noticed is the signage added to the fence. This area provides a possible location for users to not only stop and look out onto the agricultural fields, but also learn about what land they are looking at exactly. 53 Figure 43: Solution to part C with shoulder, asphalt pavement, wooden fence barrier, and possible signage concepts shown. Continuing down the path, the first part of the next solution shown is for the erosion issue near the start of part D. Similar to the solution for part C, a wooden fence is added to keep pedestrians safe from the steep slope that drops off to the river and also to provide some erosion control. 54 Figure 44: Part of solution D with the asphalt pavement and fence pictured. The rest of solution D includes more wooden fencing that follows the slope’s edge, a continuation of the asphalt pavement, and an area for possible signage to relay the important historical information about the Ice Pond to pedestrians. Figure 45: Solution D with less steep asphalt pavement, a wooden fence along the slope’s edge, and a possible area for signage indicating the historical importance of the Ice Pond. 55 The rendering below is the path nearing the approach of the bridge. Notice the two foot shoulder on either side of the path as well as the signage that clearly marks which way is for the bridge and which way is for other path activities. Figure 46: Path (width of 10 ft.) near bridge approach. 56 Continuing along to the bridge itself, the following image shows a view looking down the decking of the bridge. Figure 47: Front view of the bridge. An important part of this final deliverable section is a discussion on design verification. In a typical civil engineering project, most of the design verification would be part of later phases but before construction. For the conceptual phase this project is working in, most of the verification happened in the form of the drawings and rendering that were created. Looking at the specific path design requirements in the Traceability Matrix in Appendix B, all of these were verified by dimensions included in the drawings. For the three specific design requirements for the bridge, all of these were verified by considering them when doing the structural analysis of the bridge. 57 Figure 48: Traceability matrix with path and bridge requirements and verifications sources shown. 7. Cost Analysis An initial cost estimate was created using resources available to the group. A second, higher set of estimates were established from a conversation with our liaison Wayne Feiden. A breakdown of the group’s initial cost estimate is in Figure 49. 58 Figure 49: An estimate of the initial estimated cost of the shared use path, bridge, and total cost of the project. Since this project is only a conceptual design, not all factors were priced. The cost for the shared use path is roughly $680k. To account for future changes in pricing and miscellanea, a 25% contingency is added to this cost, bringing it to $850k. Similarly, since the bridge is $1.06M, a 25% contingency added to it brings the cost of the bridge to about $1.4M. The total costs the team estimated are near $2.1M, which were rounded conservatively to $2.5M. More details on how these prices and quantities were estimated are in Appendix R. 59 Liaison Wayne Feiden provided rough estimates from his experience as a city planner for the cost of these types of projects. His estimates were higher than what the group estimated. Table 11: Initial and Final Estimated Costs for the Northampton State Hospital Shared Use Path project. Initial Estimated Cost Final Estimated Cost Path $850k $1-2m Bridge $1.4m $1.5-2m TOTAL (Rounded) $2.5m $2.5-4m This demonstrates that the project is feasible to complete within the projected $4m budget. 8. Future Implementation A significant amount of work was completed for this project over the course of the academic year, yet this work only covers about 10% of the entire civil design process. Moving forward, the next steps would be to move into the design development phase, or reaching the 25% mark. A significant amount of time goes into preparing for construction documentation, or reaching the 75% mark. The last stage is the construction process. Additional next steps include presenting this work to legislators and using it for grants. Both of these steps are part of the process for applying for funding for the project. At this point, there are additional tasks to be completed but due to time and access they are unable to be completed this year. The first suggestion is to conduct a geotechnical analysis of the footing location near the Wireworks factory. Assuming that side of the river we completed field work on has a similar soil profile as the other side near Wireworks is a large assumption in this project. Performing another geotechnical analysis of this side would narrow down or completely eliminate this assumption. The team recognizes the next geotechnical field work that would be completed in the future would also be much more comprehensive than the tests we were able to complete and we anticipate this work done by certified engineers and technicians. An additional recommendation is for another investigation of the drainage and erosion issues near or on the path. These two issues were not the central design challenges of this project, which meant these concerns were only addressed at a general level. The bridge would benefit from higher-resolution analyses. The next phase of structural analysis would be to analyze the bridge for horizontal loading conditions such as wind. Since these horizontal loads were not included in the team’s analysis, the superstructure was built conservatively, so a more thorough study could potentially refine the bridge dimensions to get the light and airy look NOPS and MRGI would like. Addressing these next steps would lead to a more detailed path and bridge design proposal and more accurate visuals. It would also be good to formally analyze the bridge’s resistance to the 100- and 500-year flood events. This would involve calculating the freeboard space between the 60 bridge and the water level for each flood, modeling the forces placed on the bridge, and estimating the bridge’s resistance to scour. 9. Summary The history of the Northampton State Hospital and the Wireworks Factory’s revolutionary importance was researched early on in this project. The site history situated the project space and provided a clear understanding as to why the Mill River Greenway Initiative wanted to convey the importance of the land to the people of the Pioneer Valley. Design requirements were extrapolated from the research done to satisfy the needs of the project and the stakeholders alike. With the aid of stakeholders, NOPS and MRGI, the necessary regulations needed to be considered when building the bridge and the path were made clear; one of these regulations being that this area contains wetlands and other natural habitats that are protected under law and should, thus, not be touched. These spaces, along with their corresponding regulation, are necessary components of the design process. They are subsequently used as constraints during the permitting process that is to be implemented near the construction phase of the project. Another major component used to determine next steps of the conceptual design requirements was increasing familiarity with the geology of the region. Analysis of regional soil near the proposed abutment location for the bridge confirmed data readily available on ArcGIS about the composition of the soil. It was concluded that the region contains cohesionless, granular soil which indicates moderate drainage in the area. This soil information was used to further aid in the design of the abutment foundations. Moreover, elevation profiles were used to visualize any regions were a concern when it came to grading compliance of the path. The elevation models in tandem with the data compiled on soil in the region provided a basis to continue the conceptual design of the path and bridge. A preliminary structural analysis was completed for the conceptual design that included the most pertinent loads that are pedestrian, vehicular, and dead loads. This work helped narrow down steel member sizes and eventually lead to a finite element model that showed that there were no structural issues with the current conceptual design. Lastly, final visualizations for path solutions and bridge concepts were created to reflect design requirements. Some of these visuals were used in a legislative presentation that could be shown to local government officials and other funding agencies to provide a general idea of feasibility and benefit to the community. Appendix A: Gantt Chart Design Clinic 2020-2021 PROJECT TITLE DC-NOPS/MRGI COMPANY NAME Design Clinic PROJECT MANAGER Q1: Ruth Penberthy Q2: Karena Garcia Q3: Christian Madrigal Q4: Barb Garrison DATE 4/30/21 SHEET PURPOSE Track work progress throughout the academic year. Quarter Project Tasks / Deliverables TASK OWNER START DATE DUE DATE Task Status Quarter 1 Quarter 2 J-Term Quarter 3 Quarter 4 9/21 9/28 10/5 10/12 10/19 10/26 11/2 11/9 11/16 11/23 11/30 12/7 12/14 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12/21 4/19/21 4/26/21 5/3/21 5/10/21 M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F 1 Q1 Presentation Q1 Report Objective 1 Collect historical data 9/17/20 Completed Obj. 1 Task-Independent historical overview research Barb Obj. 1 Task-Speak to John Sinton for area history overview Barb Obj. 1 Task-Gather info from Gaby for second opinion Barb Objective 2 Conduct research on path and bridge guidelines and regulations 9/17/20 Completed Obj. 2 Task-locate necessary permits, organize into table Karena Obj. 2 Task-AASHTO Research Barb Obj. 2 Task-Bridge Legislation Research Christian Obj. 2 Task-Wetlands Preservation Research Karena Objective 3 Formulate questions and areas of concern to prepare for Q2/Q3 work 9/17/20 Completed Obj. 3 Task- Compile into Doc Group Obj. 3 Task- Deliverable 1 Trail/Bridge Site History: Map Layer 9/22/20 10/16 (Aim for 10/14)Completed Del. 1 Task- GIS layer with important sites marked Barb Del. 1 Task- Deliverable 2 Trail/Bridge Technical Background: Map Layer 9/30/20 10/16 (Aim for 10/14)Completed Del. 2 Task- GIS layer with soil Issues marked Christian Del. 2 Task- GIS layer with river Issues marked Christian Del. 2 Task- GIS layer other technical issues marked Ruth Deliverable 3 Presentation (Presentation Slides)Ruth 10/8/20 10/16 (Aim for 10/14)Completed Deliverable 4 Team Q1 Report 10/13/20 10/23 (Aim for 10/21)Completed Quarter Project Tasks / Deliverables TASK OWNER START DATE DUE DATE Task Status 2 Objective 1 Geotechnical Analyses Completed Q2 Report Draft Q2 Presentation Obj. 1 Task- Determine which two geotechnical analyses should happen in Q2: scour, bearing, settlement, retaining Group 10/24/20 10/26/20 Obj. 1 Task-Geotech 101 subject learning Group 10/24/20 11/14/20 THXGVN BREAK Obj. 1 Task-Determine what geotechnical tests can be done in the field Group 10/23/20 10/25/20 Obj. 1 Task-Determine what variables are needed to make bridge and abutment decisions Group 10/24/20 11/14/20 Obj. 1 Task-Meet with Professor Rubin for guidance on all of the above Group 10/27/20 10/27/20 Obj. 1 Task-Carry out the tests decided upon Ruth 11/14/20 11/14/20 Objective 2 AutoCAD-Civil 3D Completed Obj. 2 Task- Make sure everyone has access to the software whether remote or local Group THXGVN BREAK Objective 3 Bridge Research Completed Obj. 3 Task-Research types of bridges in general Karena 11/12/20 11/14/20 Obj. 3 Task-Research selected bridge type (Truss)Karena 11/15/20 11/21/20 Obj. 3 Task- Research decking material (wood, steel, FRP, concrete)Karena 11/12/20 11/21/20 THXGVN BREAK Obj. 3 Task- Create a matrix to compare the research results Group 11/21/20 11/21/20 Obj. 3 Task- Select 3-5 bridge options to move forward with Group 11/23/20 11/23/20 Obj. 3 Task- Justify the 3-5 bridge options in a write up that can go into the report and Q2 memo Karena 11/21/20 11/30/20 Obj. 3 Task-Add to the options to the report Karena 11/21/20 11/30/20 Objective 4 Path Completed Obj. 4 Task-Point out the path's steepness issues Christian and Barb 11/18/20 Obj. 4 Task- Determine how best to categorize the troublesome sections Christian and Barb 11/19/20 11/23/20 Obj. 4 Task- Clean up graph of trouble sections to present Christian and Barb 11/20/20 11/30/20 Obj. 4 Task- Write up path solutions (cut+fill, switchbacks, reroute Christian and Barb 11/30/20 Deliverable 1 Q2 Report Completed Del. 1 Task-Implement Wayne's comments Karena 10/26/20 11/19/20 Del. 1 Task-Implement Gaby's comments Karena 11/19/20 11/19/20 Del. 1 Task-Implement Professor Rubin's comments Karena 11/3/20 11/5/20 Del. 1 Task-Update Table of Contents Karena 11/12/20 11/14/20 Del. 1 Task-Submit Draft for Review Group 11/30/20 Del. 1 Task-Make necessary edits and submit for grading Group Deliverable 2 Q2 Presentation Del. 2 Task-Create presentation deck Karena 11/12/20 11/12/20 Del. 2 Task-Add slides about bridge selection Del. 2 Task-Add slides about path Quarter Project Tasks / Deliverables TASK OWNER START DATE DUE DATE Task Status J-Term: Objective 1 Geotechnical Engineering Completed Obj. 1 Task Perform Geotechnical Lab tests on site samples if Professor Rubin/Ford is available Group 1/20/21 1/21/21 Obj. 2 Task Analyze Geotechnical Results Ruth, Karena 1/21/20 2/10/21 Objective 2 CAD Drafting Completed Obj. 2 Task Define bridge site in AutoCAD Karena 1/4/21 1/15/21 Obj. 2 Task Define path site in AutoCAD Karena 1/4/21 1/15/21 Obj. 2. Task Work on modeling bridge structure in Fusion 360 Karena 1/19/21 1/29/21 Objective 3 Bridge Loading Completed Obj. 3 Task Define assumptions regarding loading Barb 1/18/21 2/15/21 Obj. 3. Task Begin bridge loading calculations Barb, Karena 1/18/21 2/15/21 Deliverable 1 CAD Drafts of Path-Bridge Connection and Bridge Structure Completed Del. 1 Task AutoCAD Drawing of Path and Bridge Karena 1/4/21 1/15/21 Del. 2 Task Fusion 360 Scaled model of the Bridge Structure Karena 1/19/21 1/29/21 Quarter Project Tasks / Deliverables TASK OWNER START DATE DUE DATE Task Status 3 Objective 1 Refine Geotechnical Calculations Completed Obj. 1 Task Complete any geotechnical lab tests that were not completed over J-Term Ruth 2/16/21 2/23/21 Objective 2 Begin Abutment/Footing Design Completed Obj. 2 Task Define Assumptions for the footing design Ruth, Karena 2/23/21 2/26/21 Obj. 2 Task Retaining Wall Calculations Ruth, Karena 2/26/21 3/3/21 Obj. 2 Task Footing/abutment bearing capacity Ruth, Karena 2/26/21 3/1/21 Obj. 2 Task Footing/abutment sizing Ruth, Karena 3/1/21 3/12/21 Obj. 2 Task Determine footing /abutment contact pressure Ruth, Karena 3/1/21 3/3/21 Obj. 2 Task Determine significance of relevant factors of safety Ruth, Karena 3/8/21 3/10/21 Objective 3 Structural Analysis Completed Obj. 3 Task Compile list of loads to be considered Barb 2/17/21 2/24/21 Obj. 3 Task From the list of loads, come up with reasonable values in Newtons or psf Barb 2/24/21 2/26/21 Obj. 3 Task Create a shear and moment diagram Barb 3/3/21 3/5/21 Obj. 3 Task Understand which members would be in tension or compression in all bridge option Christian, Barb 3/8/21 3/10/21 Obj. 3 Task Sizing the truss members accordingly 3/17/21 3/24/21 Objective 5 PR Package Completed Obj. 5 Task Complete cartoon set for local stakeholders Group 3/1/21 Q4 Objective 6 Path Grading and Drainage Completed Obj. 6 Task Walk the path in person as a team hopefully Group 2/28/21 3/29/21 Obj. 6 Task Identify areas of grading and drainage concern in person.Group 2/28/21 3/3/21 Obj. 6 Task Make sure that these spots correspond to the data and graphs we made in Q2 (Validation protocol) Christian 2/28/21 3/1/21 Obj. 6 Task Use the GPS Logger to create two or three possible routes to resolve grading issues as the path currently exists. Christian, Karena, Ruth 3/3/21 3/10/21 Obj. 6 Task Collect data on the entire path to ensure accurate path/trail Christian, Karena 3/10/21 3/10/21 Obj. 6 Task analyze the whole path elevation to check for areas of concern Christian 3/10/21 3/19/21 Obj. 6 Task determine candidate locations for cut and fill and identify amount of needed cut/fill Christian 3/19/21 3/19/21 Deliverable 1 Project Visuals Completed Del. 1 Task Bridge superstructure visuals Karena 3/1/21 Q4 Del. 1 Task Path design visuals Karena 3/1/21 Q4 Deliverable 2 Cartoon Set for Stakeholders Completed Del. 2 Task Put together a rough draft for comment Group 3/1/21 3/17/21 Quarter Project Tasks / Deliverables TASK OWNER START DATE DUE DATE Task Status 4 Objective 1 Ecological Impacts Completed Obj. Task 1 Create a general ecological impact write up Christian 4/14/21 4/26/21 Objective 2 Cost Analysis Completed Obj. 2 Task Compile prices and quanitites for a preliminary cost estimate Ruth, Karena 4/16/21 4/27/21 Deliverable 1 REVISION C Report Completed Del. 1 Task All hands on deck for edits from feedback Group 4/23/2021 4/30/21 Deliverable 2 Q2 Presentation Completed Del. 2 Task-Create presentation deck 4/23/21 5/5/21 Del. 2 Task-Add slides about bridge selection 4/23/21 5/5/21 Del. 2 Task-Add slides about path 4/23/21 5/5/21 Del. 2 Task-Practice, Adjust, Present 5/5/21 5/5/21 Deliverable 3 Cartoon Set for Stakeholders Continued Completed Del. 2 Task Finalize based on feedback Group 4/20/21 5/14/21 Appendix B: Traceability Matrix TRACEABILITY MATRIX NOPS/MRGI Date:4/29/2021 Ruth Penberthy, Karena Garcia, Christian Madrigal, Barb Garrison Revision:C1 The Norhampton Office of Planning and Sustainability and Mill River Greenway Initiative are hoping to build a bridge to cross from the corn fields down from Commuity Gardens to Federal Street. In adddition, they are hoping to make the existing trail more accessible by paving it and ensuring that it follows state and federal trail accessibility guidelines. Design Requirements (DRs) Path or Bridge Stakeholder Need Statement DR ID Design Requirement Statement Design Requirement Specification Design Requirement Source Verification Protocol for DR Path MassDOT will not fund a trail that has a grade greater than 5%. DR-01 Grading should not exceed 4.5%.Grading < 4.5% 11.3 Accessibility of Shared-Use Path, MassDOT Mass Highway (2006). https: //www.mass. gov/files/documents/2016/08/nq/ch- 11.pdf AutoCAD and GIS Data MassDOT will not fund a trail that is not at least 10' wide or 8' if absolutely necessary.DR-02 The path should be at least 10' wide.Width = 10' 11.4.1.1 Path Width, Shared Use Paths and Greenways, MassDOT Mass Highway (2006). https://www.mass. gov/files/documents/2016/08/nq/ch- 11.pdf AutoCAD and Conceptual Drawings are drawn with 10' wide path The trail must be accessible to those that fall under the American Disabilities Act (ADA) DR-03 The trail should be an asphalt paved, 10' wide trail. Width = 10' Material = Asphalt MassDOT Mass Highway (2006). https: //www.mass. gov/files/documents/2016/08/nq/ch- 11.pdf AutoCAD and Conceptual Drawings are drawn with 10' wide path The trail should provide stopping and resting areas off the path, allow for snow storage, help to prevent root damage, and to allow passing and widening at curves DR-04 The trails shold have shoulders at least 2- feet wide Shoulders = 2 ft 11.4 Shared Use Path Design, MassDOT Mass Highway (2006). https://www. mass. gov/files/documents/2016/08/nq/ch- 11.pdf AutoCAD and Conceptual Drawings are drawn with 10' wide path Bikers and pededstrians along the trail should have a clear path without obstructions near their head. DR-05 The trail should have a vertical clearance of at least 8 ft. Vertical clearance = 8ft 11.4.1. 3 Vertical Clearance AutoCAD and Conceptual Drawings are drawn with 8' vertical clearance The trail should not have drainage issues.DR-06 The trail should have a maximum cross slope of 2%Cross Slope <= 2% 11.4.14 Drainage, MassDOT Mass Highway (2006). https://www.mass. gov/files/documents/2016/08/nq/ch- 11.pdf AutoCAD and Conceptual Drawings Bridge The bridge needs to be able to withstand pedestrian traffic.DR-07 Pedestrian bridges shall be designed for an evenly distributed live load of 90 pounds per square foot .LL = 85psf AASHTO Guide Specification for the Design of Pedestrian Bridges Structural Analysis The bridge needs to be able to withstand an emergency vehicle DR-08 Bridges will be designed to withstand a moving vehicle load which weighs 1000 pounds per foot of width (up to 10,000 pounds) of bridge. This concentrated load is in addition to a 20 pounds per square foot evenly distributed live load. The vehicle load shall be distributed such that 80% of the load is on the rear axle.H-10 Loading AASHTO Guide Specification for the Design of Pedestrian Bridges Structural Analysis The bridge should have safety railing.DR-09 The bridge must have a minimum of 3ft 6 in railing on either side It must also have a rub rail at least 3 ft from grade. Railing >= 3' 6" Rub rail >= 3" VTrans Pedestrian Pedestrian and Bicycle Facility Planning and Design Manual Conceptual Design 66 Appendix C: Stakeholder and Design Requirement Development This section explains our stakeholders and their needs in greater detail than the body of the report. Appendix C1: Stakeholder Development Appendix C1.1: Northampton Office of Planning and Sustainability The Northampton Office of Planning and Sustainability (NOPS) is one of the major stakeholders of this proposed public works project. NOPS needs the design of both the shared use path and the bridge abutment foundation to not encroach on the existing agricultural land. This constraint is part of their long term goal of filing the legislation for easements for the project and also allows them to reach a consensus with the Massachusetts Department of Agricultural Resources and the Smith Vocational Agricultural High School. In the same vein, this limitation overlaps with NOPS’s need of minimizing the bridge abutment and foundation footprint in the local ecosystem. Both of these needs determine the project's capacity to receive funding, as MassDOT will not fund projects that infringe on wetlands and disruptive activities in sensitive areas. NOPS not only requires that the path meet all other design requirements outlined by the Massachusetts Department of Transportation (MassDOT), but also the Americans with Disabilities Act (ADA) and the City of Northampton. The two major requirements that must be met have to do with the path width and grading; the width must be 10 feet at a minimum and the grading can be no steeper than 4.5%. Although the ADA guidelines specify a 5% maximum grading, MassDOT and the City of Northampton mandate a 4.5% maximum grading to account for minor errors from contractors. MassDOT will not fund projects with grading higher than 4.5% (and even then a 8% maximum) unless it is proven that there is either no other alternatives present to circumvent that, or the area in question is part of a cliff, wetland, or archaeological site. It is important that the cost of the project is reasonable and justifiable. The estimated budget for this project is about $4 million dollars, however, according to NOPS, this is not necessarily a cap as compromises on design solely to fall within budget should be avoided. This will require a cost estimate to confirm that all aspects of the project are appropriately accounted for given the project’s scope and estimated budget constraints. Another need outlined by the stakeholder includes vehicular access for emergencies. As a result of this explicit need, other necessary structural standards and guidelines will inform the design and performance of the structure abutment foundation. 67 Appendix C1.2 Mill River Greenway Initiative Alongside NOPS, the Mill River Greenway Initiative is another central stakeholder that uplifts a complimentary set of community needs. Encapsulating the river’s history is part of MRGI’s broader mission to reshape community identity around the river, which was central to the success of the city during earlier stages of its development. Promoting the benefits of the bridge with a coherent narrative will gauge and galvanize community support which will be essential in facilitating local and state-wide funding for the project. Understanding the context in which the project is taking place also informs the process of construction, as important historical sites must be preserved to ensure that the mission of MRGI is upheld. Preservation of historical sites along with the wonderful scenery can also encourage recognition from the Conservation Commision that can move forward with legitimizing it as part of their Greenway Network. Appendix C1.3 Northampton Community Community engagement with the river is one of the major objectives of this proposed public works project, and therefore another primary stakeholder is the greater Northampton community. Both the proposed bridge and path should be easily accessible, providing all patrons with the capacity to engage with the space. This in turn will also confirm that any monetary investments are valuable. The proposed project promotes alternative transportation modes that provide access to Northampton High School for commuters in the community as well as handicap accessibility. Safety is of paramount importance for this project given that the bridge and path are expected to function through all seasons and for a range of user ages and abilities. The appropriate materials should be selected to ensure that the bridge does not sustain any cracking as a result of any freeze-thaw that is expected to occur with other materials. This need overlaps with structural needs of NOPS as maintenance costs of the bridge influence budget planning. It is also important to recall that a certain percentage of the local community will cycle on this path, and therefore the cusp that connects the bridge and the path should be gradual and smooth. This contributes to safety aspects as the cyclist population is not exposed to potential injury and limits the capacity for serious pedestrian and cyclist accidents. As described, there are sub communities that exist within the broader Northampton community, as seen with the cyclists and dog walkers, and therefore consideration of those as stakeholders will include people that engage the area regularly. Appendix C1.4: Local Environment Another stakeholder central to the design consideration that will be explored within this project is the local ecology, defined as the river, soil, flora and fauna in the region. Delineating the local ecological needs will inform an optimal design and implementation of the project. One of the 68 major needs is making sure that scour during time of construction is minimized to prevent water quality degradation. Although scour control is more closely monitored during the project implementation stage, the conceptual design process and suggested abutment design should consider and minimize sources of potential scour. Moreover, the local environment requires appropriate drainage mechanisms to exist as part of both the bridge and the path. Proper drainage plans for the site location that consider the Mill River floodplain may address erosion, potentially reduce erosion rates and/or prevent topsoil damage. Appendix C2 Design Requirement Development This appendix explains in more detail where some of our design requirements came from. A significant portion of quarter one was spent working to understand the engineering processes, laws, and other guidelines that would impact the bridge and trail designs. The relevant portions of these regulations and their impact on the design requirements are listed below. Appendix C2.1 Trail Accessibility Guidelines Beginning at the federal level, most of the guidelines are specifically tailored to National Parks. Although this area of trail is not part of a National Park, and hence, not legally bound to the guidelines outlined in the United States Forest Service Trail Accessibility Guidelines, it is still important to consider the rules and regulations at the federal level as this project is receiving funding from the federal government, not to mention the FSTAG provide reasonable technical provisions. The main two guidelines to consider for trail accessibility are its surface and slope, especially when it comes to paved surfaces. When it comes to the trail’s surface, the only provision the FSTAG notes is that it must be “both firm and stable.” Since this trail will be paved, this guideline is not terribly concerning because there is no question as to whether asphalt is considered firm and stable. Should the paved surface have any openings, however, those openings should be no larger than ½” or, in extenuating circumstances, ¾”. In addition, obstacles on the surface can be no larger than ½”. Shifting focus towards slope, for any distance of a trail, the slope cannot exceed 5%. If there is no way to achieve that slope percentage, there are exceptions that allow some parts of the trail to be no greater than 8.33%, or if absolutely necessary, 12%. With each slope comes regulations on resting intervals that increase in frequency as the slope steepens. This information is summarized nicely in Table C2 below from the 2015 FSTAG Pocket Version. It should also be noted that section 7.4.3.2 of FSTAG states if a trail is going to be paved or elevated above the natural ground, the cross slope (slope perpendicular to the direction) cannot exceed 2%. The FSTAG provides a quick reference flow chart that can help determine what technical provisions should be considered which is referenced in Tables C3.1 and C3.2. 69 Shifting focus to the state level, similar to how the federal level pertains to National Parks, state guidelines are heavily focused on State Parks. These guidelines are implemented and upheld at the state level by the Massachusetts Department of Conservation and Recreation (DCR). The DCR was created after a merger of two agencies was enacted, so there were different state-wide policies being followed from trail to trail. Now, with the DCR as the sole governing body behind state trails, they created the Trail Guidelines and Best Practices Manual. According to this manual, the DCR has adopted the same technical provisions outlined by the FSTAG. However, unlike the FSTAG, the DCR’s manual emphasizes the sustainability of an existing or proposed trail in the Commonwealth. Specifically, the manual says that sustainable trails should “...connect positive16, and avoid negative, control points, keep water off the trail, follow natural contours, keep users on the trail, and meet desired user experiences.” A brief description of each of these guidelines is provided in Figure C4. Moreover, the DCR provides more insight on how to design a sustainable contour trail with five technical specifications. These five specifications were taken directly from the DCR Trail Guidelines and Best Practices Manual’s section titled “Building Sustainable Trails” and placed in the Design Requirements section of this report. In addition to the technical side of trail building, the best practices manual touches on the softer side of trail design such as managing trail viewsheds, shapes, and landscape features as well. The DCR notes that viewsheds should spotlight the most scenic parts of the trail and down play the less attractive parts as to enhance the user’s experiences while using it. Shapes of the trail should vary from different sized loops to spurs to long flat areas and even more sloped areas.These trails should also have clear starting and ending points as well as clear destination points to leave the user feeling oriented and ultimately accomplished after their trail experience. Trail features like gateways, anchors, and edges can help tie the connection between the trail itself and the natural environment around it. Gateways can be man made, like with a physical art piece transitioning one part of the path to another, or occur naturally, like when dense tree coverage opens up to a meadow. Both make for a more intimate setting between the trail, the environment, and the user. Anchors may include a large boulder or a distinguished tree, but it can be any vertical object along the trail. At the state and local levels, most of the guidelines work in parallel because rules and regulations the local government have to follow come from the state. In this case, Northampton and the surrounding cities must abide by the laws of the Commonwealth of Massachusetts. When it comes to the proposed trail and bridge implementation, the most notable guidelines found at the local level are more permitting based than accessibility based because the local government’s accessibility guidelines do not deviate from the state’s accessibility guidelines. 16 https://www.mass.gov/doc/dcr-trails-guidelines-and-best-practices-manual/download Last Accessed 10/21/20 70 Table C1: Matrix of resources to reference when considering trail accessibility guidelines at the federal and state levels. Level Link Description Federal https://www.fs.usda.gov/managing- land/trails/trail-management- tools/trailplans Provides a step-by-step process on how to get a trail built on a NATIONAL Forest. Has bridge drawing and abutment examples. Federal Forest Service Trail Accessibility Guidelines (FSTAG) Pocket Version Pocket Version of the FSTAG Federal Trail Construction and Maintenance Notebook: 2007 Edition Book of How-Tos. Bridge Section. No abutment details. State Trails Program Gives technical specifications for trails and steps to take if in a sensitive area. State https://www.mass.gov/files/docume nts/2016/08/qq/management- guidelines.pdf?_ga=2.175076961.2 37079820.1600399520- 1562146276.1600399520 Classifies the type of trail. Explains why it’s classified as that and how to treat it as such and what things go along with that distinction. Provides maps to help prove that we are not State Park Property. State Wetland and Wetland Change Areas Map Wetland Map Viewer. State Regulatory Maps: Priority & Estimated Habitats Protected Habitat Area Map Viewer 71 Table C2: A summary of technical provisions for trails from the United States FSTAG Pocket Version. Figure C3.1: The FSTAG Quick Reference flow diagram that helps determine whether the FSTAG applies to a project and next steps. 72 Figure C3.2: A continuation of Figure C3.1, specifically looking at Steps 3 and 4 in the decision making process. 73 Figure C4: Softer technical provisions from the DCR best practices manual that should be considered when designing a sustainable trail system. 74 Appendix D: Site Visit Photos Appendix D1: February 28th 2021 Top: Ice Pond looking up the slope. Bottom: left side slope at proposed bridge site. 75 Top: River crossing at proposed bridge site. Bottom: Side view of river crossing at proposed bridge site. 76 Wireworks side of proposed bridge site slope, looking up. 77 Appendix D2: March 6th, 2021 Top: Slope issue after the drainage concern. Bottom: Possible stairs option near Village Hill. 78 Level front view of the river crossing at the proposed bridge site. 79 Appendix D3 March 10th, 2021 Left: Slope concern before the drainage concern. Right: Existing infrastructure near the Ice Pond area. 80 Appendix D4: March 22nd, 2021 Top: Side view of slope concern near Village Hill. Bottom: Side view of slope concern before drainage issue. 81 Top: Slope concern near the ice pond. Bottom: Ice Pond. 82 Appendix D5: March 29th, 2021 Left: Erosion concern near the Ice Pond. Right: Bridge approach. 83 Top: River cross section with person for scale. Bottom: River cross section looking downstream toward proposed bridge site. 84 Appendix E: Preliminary Path Slope and Grading Analysis Figure E1: The path file used to generate slope data, marked with approximate distance from beginning of path. Our path is about 2000 meters long. The analysis took the beginning of the path to be the bridge and the end to be its contact with the path network near Hospital Hill. The group split the path into four sections - A, B, C, and D - of 500m each. The split makes it easier to understand where slope problems are located. It was confirmed that 500m, 1000m, and 1500m are all flat, and therefore we are not splitting a problem spot down the middle of two sections. Discussions with our liaisons revealed that Section D is going to change. We will present our findings for the layout of Section D that we were initially given. Appendix E1: Problem Statement The path must comply with the Americans with Disabilities Act, which requires a maximum grade of 5%. The purpose of the analysis was to identify regions of the path that are too steep, and therefore, do not comply with ADA regulations. Along the path, grade is allowed to increase 85 the 4.5% minimum to 8% over short stretches of path if a 5% grade is impossible. To ensure that the project maximizes accessibility over the entire span of the path, a maximum grade of 4.5% is the goal to ensure absolute compliance. Appendix E2: Methods Using ArcGIS along with an elevation model, data on the elevation of the profile was extracted which would allow us to perform a slope assessment. It is important to note that the data used for this assessment used data points that were perhaps located on contour lines that were placed at 1m intervals. Given that the elevation profile of the path was exported from ArcGIS into a comma separated file, the initial analysis required we order the arbitrary outlined paths into the path that would be followed by a pedestrian from the proposed bridge site to the hospital hill site. Moving forward slope and then grade was calculated using the functions available in the Microsoft Excel software to produce an initial visualization of the grade variation along the path. This initial graph detailed noisy data that did not facilitate in identifying any true regions of concern along the path. To refine the number of potential problem regions the team calculated an average grade of every 40 meters along the path. This graph was used as a tool to visually pinpoint regions of concern which would then need to be addressed to ensure ADA compliance. The team further annotated the provided graphs and decided that tackling sections of the path would be best. Therefore, moving forward the team sectioned off the path into four equal sections to address regions with higher grade percentages. Moving forward in the process to address any regions of concern, the team was advised to understand how averaging across certain sections of the path with respect to cohesive slope might make regions of concern more obvious. The process required averaging the grades along the sections that were suggested by Professor Aaron Rubin. These estimates were graphed along the average distance of that path section and these data are seen clearly in Figure E2. 86 Figure E2: Annotation of what sections along the path provide visual cohesion to be used for averaging of slope. These annotations were provided as rough visual suggestions by Professor Aaron Rubin. 87 Appendix E3: Results and Discussion Figure E3: Team annotated graph for the 8-point average of slope for the path as one moves from the proposed bridge site towards hospital hill. This graph also details the four major regions of concern that informed which way the path was to be sectioned off. In Figure E3, elevation and average slope are graphed against distance along the path. Problem spots are highlighted in cyan and labeled A, B, C and D. (Different from section labels A, B, C, D) The data are noisy, and the path we got this slope data from is not the current version of the path - Section D on Hospital Hill is different now. Since we have larger-level changes to make, the group will only explain and attempt to address the most obvious problem spots by proposing cut and fill, switchback, or rerouting as a solution to achieve grading compliance. 88 Figure E4: Graph of the entire path elevation profile along with the grade percentages as the path distance changes. This figure depicts the four sections that were chosen to further the problem region analysis. The first section ends at the 500 meter mark, the second at 1000 meters, the third at 1500 meter, and the fourth at the end of the path. These sections were labeled A, B, C, and D respectively. 89 Appendix E3.1: Section A Figure E5: Section A Section A has a clear problem area at the very beginning of the path which begins on Federal Street instead of its actual beginning on the Mill River. There is a strong belief that the data that was extracted from ArcGIS may have some inconsistencies that may provide inaccurate information at the site. 90 Appendix E3.2: Section B Figure E6: Section B of the path. Section B has one potential problem region that might be located near the agricultural fields. 91 Appendix E3.3 Section C Figure E7: Section C of the path As of now the section labeled Section C includes Hospital Hill. This section seems to be the most problematic but given that much of this section path does not exist the team will refrain from further analysis. 92 Appendix E3.4 Section D Figure E8: Section D Section D is currently the end of the path section that is no longer part of the proposed shared use path that will be paved. This section will change when the appropriate LiDAR data is extracted. Moving forward,Section D at the end of the path will be updated to demonstrate the region which will be added to be part of the shared use path. Other Suggested Methods As briefly explained, the team also decided to conduct visual averaging of the slopes to understand what this would look like as the previous data were too noisy. This analysis yielded the following results which may not depict the path accurately but does confirm that the bridge site location poses a site of concern (Figure E9). 93 Figure E9: Graph depicting the elevation profile of the proposed shared use path in meters. This graph also demonstrates the average of the sections as we move along the path. Appendix E4: Discussion of Preliminary Analysis This analysis made use of an embedded digital elevation model (DEM) of the greater Northampton region and a data layer with the proposed path was used to view elevation changes. The path was sectioned into four different pieces and an elevation profile for each of the sections was produced by ArcGIS. Figure E10 depicts one such path that ArcGIS used to calculate and produce a corresponding elevation profile. Given that the path was partitioned arbitrarily by the software, to better understand the changes in the elevation, path data was adjusted accordingly and an entire path elevation profile was produced (Figure E11). Adjustments to the data also allowed for calculations on grade variation along the path. Specifically, the grade was averaged for eight different points along the path to reduce the noise produced by a more refined analysis (process further explained in Appendix F). As seen in Figure E11, grade varied substantially in a few areas along the path. 94 Figure E10: Map depicting the elevation of the region surrounding the Mill River near the State Hospital Site. The section of the path highlighted was partitioned by the ArcGIS software and analyzed to produce a unique elevation profile. 95 Figure E11: Path elevation profile produced for the highlighted path in Figure 3 which demonstrates change in meters of elevation as patrons move horizontally away from the starting point on the highlighted path towards the State Hospital Site. This figure also details the change in grade percentage as the distance along the path increases. The two lines mark the 4.5% or the - 4.5% grade percentage lines to ease in identification of problem spots. As seen in the elevation profile output for the entire path, there seems to be a steep incline occurring from the 1200 meter mark to the 1500 meter mark along the path. In this region there are grade percentages higher than the permitted 4.5% grade constraint (Figure E11). This region poses an issue due to this steep elevation that may require considering switchbacks from the path that may demonstrate a lesser elevation as horizontal distance across the path increases toward the bridge site. Ideally, the path can be altered to better comply with regulations regarding the required ADA grading of 4.5-5% grading. To better identify the regions that do not meet ADA requirements, the region was manually split into four regions. Previously ArcGIS had arbitrarily chosen the path sections, but manually adapting the data allowed the team to move from vague problem regions previously identified to a closer look at particular path locations. This analysis was done by sectioning the path off at several different meter distances along the path.Each of the individual sections were also graphed 96 to take an even closer look at problem regions within the smaller distances in each section. As seen in Figure E11, there are very few regions where the elevation of the path exceeds the required 4.5% and all of these regions are towards the beginning of the trail. Identifying these regions early in the process can help enumerate the number of regions and perhaps inform us which way might be most cost effective to implement. The other section elevation profiles will also be further analyzed to closely identify the regions where ADA requirements are violated (section elevation profiles along with the grading percentages can be found in Appendix F). Figure E12: Section A is the first 500 meters of the total path depicted Figure 3 and begins at the bridge site. The figure demonstrates the path elevation profile as well as the variation in grade percentage as one moves along the path. The black line across the graph is meant to serve as a limit so if points surpass it they are potential sites of concern as the grading percentage is higher than the 4.5% allowed. It was suggested to the team to visually inspect the slope change and manually average regions with a cohesive slope. This would inform of any more significant regions that might need to be addressed with priority. Professor Aaron Rubin provided annotations of Figure E11 that served as the visual basis for this averaging. These annotated cutoff points were then used to produce a 97 visual representation of how the path grade varies as one moves from the proposed bridge site to hospital hill (Figure E12). Figure E13: Graph depicting the elevation profile of the proposed shared use path in meters. This graph also demonstrates the average of the sections suggested as we move along the path. Figure E13 provides a cleaner visual of what the path profile looks like alongside the values for average grading of several sections. As suggested in the figure, there is only one major spot that may need to be addressed but there is doubt that this is the only region that might need to be revisited and designed. Given that the team does not have adequate evidence to conclude that the path has no other major regions of concern, we will move forward with another method for sectional analysis. Appendix E5: Conclusion Overall, as seen by this analysis of the existing path and available data there are two major problem spots, these being near the agricultural field as well as the section of path near Hospital Hill. As of now, other regions along the path have a grade that is lower than the maximum permitted 5% and while this is not immediately concerning, the team will work on these once the 98 most concerning regions have been addressed. Next steps of the path analysis will make use of available LiDAR data that may confirm any regions of concern and provide an accurate path. 99 Appendix F: Refined Path Slope and Grading Analysis The preliminary analysis of the previous path served as a method to exercise tools that would aid in refining the approach taken to address any concerns along the proposed shared use path. The path that was analyzed in Appendix E was an inaccurate analysis of an incorrect path. The actual path that is intended to be paved as part of this project is seen throughout this report and is depicted in Figure 1 in the Introduction but is depicted below for reference (Figure F1). Figure F1: Open street map view of existing trail from the Smith College athletic fields to where it ends near the abandoned Wireworks factory. Appendix F1: Problem Statement The problem statement is the same as stated in Appendix E1 and essentially requires that the path comply with the Americans with Disabilities Act and maintain a maximum grade of 5%. For a detailed description refer to the aforementioned appendix section. Appendix F2: Entire Existing Path Elevation Appendix F2.1: Methods The trail profile made use of the GPS Logger Application which collected the data as Karena Garcia walked the existing trail from the athletic fields towards the bridge site. The GPS data only extracted data points at arbitrary points along the path and connected them to produce a continuous line the length of 1750 meters. These data points were then imported into ArcGIS Pro 100 as points and lines. Given that the application collected these data under a different geographic coordinate system, they were projected onto the ArcGIS map into the coordinate system used in this region of the Americas using the Project Tool in the Geospacing Toolbox of the Analysis Section in ArcGIS Pro. Once the path was properly projected into the respective GIS map, the path elevation was extracted with the use of the Stack Profile Tool. This stack profile tool used the LiDAR data that was superimposed onto the given GIS map to collect the elevation at each data point in meters. This data was then presented as a table that was extracted into Microsoft Excel. In Excel, the data were graphed to demonstrate the variation of the path elevation in an exaggerated scale and in true scale. This elevation data offered a great visual representation of the variation in elevation along the path but did not detail the actual grade in many of the regions. Therefore to better understand the variation in grade percentage, the grade of 50 meter path sections was calculated as an estimate of the average grade percentage. To calculate the grade, the slope between two points 50 meters apart was calculated and then using trigonometry the angle in radians between the slope of the 50 meter section and leveled ground was calculated. This was then converted to degrees which equates to the grade percentage of that given path segment. A visual representation that was used alongside the trigonometric relations for this analysis is outlined below (Figure F2). Figure F2: Demonstrates the change in elevation as Δz from two points with distance along path, x, and elevation, z both in meters. θ is the angle in radians made by leveled ground and the slope of the 50 meter segment. For clarification purposes, a short walkthrough of the calculation of angle θ is shown below: 𝑠𝑠𝑠𝑠𝑠𝑠(𝜃𝜃)=𝛥𝛥𝑧𝑧𝛥𝛥𝛥𝛥 (x2,z2) (x1,z1) θ Δz 101 𝜃𝜃=𝑎𝑎𝑠𝑠𝑠𝑠𝑠𝑠(𝛥𝛥𝑧𝑧𝛥𝛥𝛥𝛥) Appendix F2.2: Results and Discussion From the analysis done at every 50 meters the team was able to understand the variation of the grade along the path. The true scale visual that resulted from this analysis is not as informative and appeared to sustain no grading issues as the path progresses from the athletic fields towards the bridge site (Figure F3). The true scale path was relatively leveled and therefore to better visualize the grade variation between these 50 meter segments we have displayed an exaggerated scale graph (F4). Figure F3: True scale graph with the left axis displaying the elevation (m) along the distance of the path in meters from the Smith College athletic fields towards the proposed bridge site. The right axis depicts the grade percentage as averages across 50 meter segments along the path. 102 Figure F4: Exaggerated scale graph with the left axis displaying the elevation (m) along the distance of the path in meters from the Smith College athletic fields towards the proposed bridge site. The right axis depicts the grade percentage as averages across 50 meter segments along the path. As seen from the two figures above the variation of the path is significant and allowed us to pinpoint sections of major concern along the path that are summarized in Appendix F3. Appendix F3: Slope Areas of Concern Analysis and Solutions Given the analysis that was produced for the entire existing path the tea pinpointed four major regions of slope concern and single drainage. This section summarizes the analysis of the four major slope concerns mentioned in section 5.4.6 Shared Use Path Concerns and Solutions and not the drainage concern. For Area of Concern A, a switchback solution was suggested that is analyzed herein. Regarding Areas of Concerns B, C, and D, they were suggested as candidates for cut and fill therefore suggested profiles are also provided. 103 Appendix F3.1: Methods The method of analysis for these path sections made use of data that was collected by Karena Garcia with the GPS Logger Application. The individual path sections were collected separately and were analyzed individually. The analyses of the four sections and the switchback suggestion for Area of Concern A followed the same process outlined in Appendix E2.1 with a few differences in the sectioning of them. In the process outlined in Appendix E2.1 the entire existing path was sectioned by every 50 meters whereas these areas of concern and the switchback suggestion were sectioned off differently to ensure that the average grade estimation was as accurate as possible. A brief overview of the sections are provide below: ● Area of Concern A: This path segment was 120 meters and was pretty uniform in slope and was therefore not sectioned off at all. The grade was estimated from a trendline estimation when the data were graphed. ○ Switchback Suggestion: This segment was 154 meters in length and was broken into two main sections, 0-80 meters, and 80-154 meters ● Area of Concern B: This path segment was 60 meters in length and was broken into four main sections, 0-20 meters, 20-40 meters, 40-50 meters, and 50-60 meters ● Area of Concern C:This path segment was 100 meters in length and was broken into five main sections, 0-20 meters, 20-40 meters, 40-50 meters, 50-65 meters, and 65-100 meters ● Area of Concern D: This path segment was 60 meters in length and was broken into three main sections, 0-10 meters, 10-40 meters, and 40-60 meters As for the suggested cut and fill profiles for Area of Concerns B, C, and D the profiles use two arbitrary data points that were chosen to visually improve the elevation profile of the respective sites. These two data points were then graphed as a line and the grade for these were also calculated using the method in Appendix E2.1. Appendix F3.2: Results and Brief Discussion Area of Concern A Using the data collected for this region, the analysis produced an approximate elevation profile for Area of Concern A that can be seen in true scale in Figure F5. 104 Figure F5: True scale plot of the 120 meter long Area of Concern A. Distance along the segment is seen in meters as is the elevation along the path segment. 105 Figure F6:. Exaggerated scale plot of the 120 meter long Area of Concern A. Distance along the segment is seen in meters as is the elevation along the path segment. To better gauge the variation in elevation, an exaggerated scale plot of Area of Concern A was produced as seen in Figure F6. As a result of the analysis Area of Concern A was estimated to have a grade average of 7.64% which was not compliant with the 4.5% ADA grading threshold. Therefore, this location is a great candidate for a switchback given the severity of the steepness but should be reassessed when officializing the shared use path. The switchback suggested for Area of Concern A can is assessed in the next section of this appendix. Switchback Suggestion The elevation profile of the suggested switchback for Area of Concern A can be seen in Figure F7 in true scale, but once again to better visualize the changes in elevation Figure F8 is provided. 106 Figure F7: True scale plot of the 154 meter long Switchback Suggestion for Area of Concern A. Distance along the segment is seen in meters as is the elevation along the path segment. 107 Figure F8: Exaggerated scale plot of the 154 meter long Switchback Suggestion for Area of Concern A. Distance along the segment is seen in meters as is the elevation along the path segment. The switchback that was collected as an option to address the steep slope Area of Concern A was identified to have an estimated grade average of 5.51% which was not compliant with the 4.5% grading required by ADA. Although the switchback was not below the 4.5% threshold, it still demonstrated that a switchback solution for this region might address the grading concern. It is suggested that other switchback options be explored for this site prior to future implementation. Area of Concern B Data collected for Area of Concern B was used to produce Figure F9, which is a true scale plot of the elevation at the site. While this elevation profile is useful, the exaggerated scale plot in Figure F10 can better display the severity of the slope at this site. 108 Figure F9: True scale plot of the 60 meter long Area of Concern B. Distance along the segment is seen in meters as is the elevation along the path segment. 109 Figure F10: Exaggerated scale plot of the 60 meter long Area of Concern B. Distance along the segment is seen in meters as is the elevation along the path segment. Given the collected data for this region, Area of Concern B was identified to have a grade average of 6.34% which was not compliant with the 4.5% ADA grading. Given that this region’s average grading was not compliant, it is suggested that cut and fill be used as a means to resolve this concern. The suggested profile for the cut and fill solution is seen in Figure F11 and would decrease the estimated grade to 4.06%. 110 Figure F11: Exaggerated scale plot of the 60 meter long Area of Concern B profile alongside the suggested cut and fill profile. Distance along the segment is seen in meters as is the elevation along the path segment. Area of Concern C Data from the region that encompasses Area of Concern C was used to produce Figure F12 and Figure F13, true scale and exaggerated scale plots, respectively. 111 Figure F12: True scale plot of the 100 meter long Area of Concern C. Distance along the segment is seen in meters as is the elevation along the path segment. 112 Figure F13: Exaggerated scale plot of the 100 meter long Area of Concern C. Distance along the segment is seen in meters as is the elevation along the path segment. Using the data, Area of Concern C was identified to have a grade average of 3.65% which was not compliant with the 4.5% ADA grading. This value might seem compliant but may be skewed to be portrayed as such. The 10m section that occurs between 40-50 meters in Figure F13 has a very steep slope of 6.1%. This section combined with the average slope of 4.9% within the 65m and 100m region seen in Figure F13, are still regions that require further inspection. Overall, Area of Concern C is a good candidate for cut and fill and the suggested profile for the cut and fill solution is seen in Figure F14 and would decrease the grade to 3.59%. 113 Figure F14: Exaggerated scale plot of the 100 meter long Area of Concern C profile alongside the suggested cut and fill profile. Distance along the segment is seen in meters as is the elevation along the path segment. Area of Concern D The last segment of the existing path,Area of Concern D, that was analyzed produced a telling elevation profile seen in true scale in Figure F15 and exaggerated scale in Figure F16. 114 Figure F15: True scale plot of the 60 meter long Area of Concern D. Distance along the segment is seen in meters as is the elevation along the path segment. 115 Figure F16: Exaggerated scale plot of the 60 meter long Area of Concern D. Distance along the segment is seen in meters as is the elevation along the path segment. As a result of the analysis, Area of Concern D was identified to have a grade average of 4.77% which was not compliant with the 4.5% ADA grading. Much Like Areas of Concern B and C, Area of Concern D is also a good candidate for cut and fill. The suggested cut and fill profile is seen in Figure F17, this profile visually addresses any abrupt variations in the elevation and improves the grade to 4.42%. 116 Figure F17: Exaggerated scale plot of the 60 meter long Area of Concern D profile alongside the suggested cut and fill profile. Distance along the segment is seen in meters as is the elevation along the path segment. Appendix F4: Overall Suggestions for Existing Path It is recommended that the areas of concern discussed be addressed with a combination of cut and fill and switchbacks. Specifically, for Area of Concern A, a switchback would be recommended to reduce the existing non compliant grading but cut and fill would also address this issue. As for the other three areas of concern, B,C, and D, all are great candidates for cut and fill which could be used to address grading concerns to ensure ADA compliance. 117 Appendix G: Geotechnical Literature Review This appendix is a compilation of the information from a literature review of geotechnical resources. The fundamental and theoretical work gathered here will be used to analyze the work done in the field. Appendix G1: Bearing Capacity The Following is from Soils and Foundations (Seventh Edition) by Cheng Liu and Jack B. Evett. Section 9.4, pages 282-287 Bearing capacity refers to the ability of a soil to support or hold up a foundation and structure. The ultimate bearing capacity (qult) of a soil refers to the loading per unit area that will just cause shear failure in the soil. The allowable bearing capacity (qa) refers to the loading per unit area that the soil is able to support without unsafe movement. It is also known as the design bearing capacity. 𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎𝐴𝐴𝐴𝐴𝐴𝐴 𝐴𝐴𝐴𝐴𝑎𝑎𝑙𝑙 = (𝑞𝑞𝑎𝑎)(𝐴𝐴𝐴𝐴𝐴𝐴𝑎𝑎 𝐴𝐴𝑜𝑜 𝑐𝑐𝐴𝐴𝑠𝑠𝑐𝑐𝑎𝑎𝑐𝑐𝑐𝑐 𝐴𝐴𝐴𝐴𝑐𝑐𝐴𝐴𝐴𝐴𝐴𝐴𝑠𝑠 𝑜𝑜𝐴𝐴𝑓𝑓𝑠𝑠𝑙𝑙𝑎𝑎𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 𝑎𝑎𝑠𝑠𝑙𝑙 𝑠𝑠𝐴𝐴𝑠𝑠𝐴𝐴) (𝑞𝑞𝑎𝑎) = (𝑞𝑞𝑢𝑢𝑢𝑢𝑢𝑢)𝑓𝑓𝑎𝑎𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 𝑓𝑓𝑓𝑓 𝑠𝑠𝑎𝑎𝑓𝑓𝑠𝑠𝑓𝑓𝑠𝑠 (2.5 𝑓𝑓𝑓𝑓 3) Footings are safely designed by considering possible foundation failures (collapse) or when excessive settlement might occur. As load (Q) is applied, the footing undergoes a certain amount of settlement as it is pushed downward, and a wedge of soil directly below the footing’s base moves downward with the footing. The soil’s downward movement is resisted by shear resistance of the foundation soil along slip surfaces cde and cfg and by the weight of the soil in sliding wedges acfg and bcde. For each set of assumed slip surfaces, the corresponding load Q that would cause failure can be determined. The set of slip surfaces giving the least applied load Q (that would cause failure ) is the most critical; hence, the soil’s ultimate bearing capacity (qult) is equal to the least load divided by the footing’s area. Equation 1: 𝐶𝐶𝐴𝐴𝑠𝑠𝑐𝑐𝑠𝑠𝑠𝑠𝑓𝑓𝐴𝐴𝑓𝑓𝑠𝑠 𝑜𝑜𝐴𝐴𝐴𝐴𝑐𝑐𝑠𝑠𝑠𝑠𝑓𝑓𝑠𝑠 (𝐴𝐴𝑠𝑠𝑙𝑙𝑐𝑐ℎ 𝐵𝐵) = 𝑞𝑞𝑓𝑓𝐴𝐴𝑐𝑐 = 𝑐𝑐𝑁𝑁𝑓𝑓+𝛾𝛾1𝐷𝐷𝑓𝑓𝑁𝑁𝑞𝑞+.5𝛾𝛾2 𝐵𝐵𝑁𝑁𝛾𝛾 Equation 2: 𝐶𝐶𝑠𝑠𝐴𝐴𝑐𝑐𝑓𝑓𝐴𝐴𝑎𝑎𝐴𝐴 𝑜𝑜𝐴𝐴𝐴𝐴𝑐𝑐𝑠𝑠𝑠𝑠𝑓𝑓𝑠𝑠 (𝐴𝐴𝑎𝑎𝑙𝑙𝑠𝑠𝑓𝑓𝑠𝑠 𝑅𝑅) = 𝑞𝑞𝑓𝑓𝐴𝐴𝑐𝑐 = 1.2𝑐𝑐𝑁𝑁𝑓𝑓+𝛾𝛾1 𝐷𝐷𝑓𝑓𝑁𝑁𝑞𝑞+.6𝛾𝛾2𝑅𝑅𝑁𝑁𝛾𝛾 Equation 3: 𝑆𝑆𝑞𝑞𝑓𝑓𝑎𝑎𝐴𝐴𝐴𝐴 𝑜𝑜𝐴𝐴𝐴𝐴𝑐𝑐𝑠𝑠𝑠𝑠𝑓𝑓𝑠𝑠 (𝐴𝐴𝑠𝑠𝑙𝑙𝑐𝑐ℎ 𝐵𝐵) = 𝑞𝑞𝑓𝑓𝐴𝐴𝑐𝑐 = 1.2𝑐𝑐𝑁𝑁𝑓𝑓+𝛾𝛾1𝐷𝐷𝑓𝑓𝑁𝑁𝑞𝑞+.4𝛾𝛾2 𝐵𝐵𝑁𝑁𝛾𝛾 Where: qult = ultimate bearing capacity 118 c = cohesion of soil 𝑁𝑁𝑓𝑓, 𝑁𝑁𝑞𝑞, 𝑁𝑁𝛾𝛾 = Terzaghi’s bearing capacity factors 𝛾𝛾1= effective unit weight of soil above base of foundation 𝛾𝛾2= effective unit weight of soil below foundation 𝐷𝐷𝑓𝑓= depth of footing, or distance from ground surface to base of footing B = width of continuous or square footing R = radius of circular footing 𝑁𝑁𝑓𝑓, 𝑁𝑁𝑞𝑞, and 𝑁𝑁𝛾𝛾are functions of the soil’s angle of internal friction (𝜙𝜙). 𝑁𝑁𝑓𝑓cites the influence of the soil’s cohesion on its bearing capacity while the term 𝑁𝑁𝑞𝑞reflects the influences of surcharge and 𝑁𝑁𝛾𝛾shows the influence of soil weight and foundation width or radius. 𝑁𝑁𝑞𝑞= 𝐴𝐴𝜋𝜋𝑓𝑓𝑎𝑎𝜋𝜋𝜋𝜋𝑐𝑐𝑎𝑎𝑠𝑠2 (45∘+ 𝜋𝜋2 ) 𝑁𝑁𝑓𝑓= 𝑐𝑐𝐴𝐴𝑐𝑐𝜙𝜙(𝑁𝑁𝑞𝑞 −1) 𝑁𝑁𝛾𝛾= (𝑁𝑁𝑞𝑞 −1)𝑐𝑐𝑎𝑎𝑠𝑠(1.4𝜙𝜙) Equations 1, 2, and 3 are applicable for both cohesive and cohesionless soils. Dense sand and stiff clay produce general shear while loose sand and soft clay produce local shear. In the latter soil conditions, c is replaced with 𝑐𝑐′= 23 𝑐𝑐 and 𝑁𝑁𝑓𝑓, 𝑁𝑁𝑞𝑞, and 𝑁𝑁𝛾𝛾are replaced with 𝑁𝑁′𝑓𝑓, 𝑁𝑁′𝑞𝑞, and 𝑁𝑁′𝛾𝛾and are modified by 𝜙𝜙′ = 𝑎𝑎𝐴𝐴𝑐𝑐𝑐𝑐𝑎𝑎𝑠𝑠(23 𝑐𝑐𝑎𝑎𝑠𝑠𝜙𝜙). With cohesive soils, shear strength is most critical just after construction or as the load is first applied, at which time shear strength is assumed to consist of only cohesion. In this case, 𝜙𝜙is zero. To evaluate cohesion, one can use the unconfined compression test for ordinary sensitive or insensitive normally consolidated clay (c is equal to half of the unconfined compressive strength 12 𝑞𝑞𝑢𝑢). For a sensitive clay, a field vane test may be used to evaluate cohesion. For cohesionless soils, the c term in Equations 1, 2, and 3 is zero where the value of 𝜙𝜙may be found through a STP test. 119 Figure G1: Scan of textbook Figure 9-7 showing the relationship between bearing capacity factors and degrees (Soils and Foundations, 284) 120 Figure G2: Scan of textbook Figure 9-9 showing the relationship between bearing capacity factors (𝑁𝑁𝑞𝑞and 𝑁𝑁𝛾𝛾) and the angle of internal friction as well as the rough empirical relationship between capacity factors or the angle and values of standard penetration resistance, N. (Soils and Foundations, 286) 121 Appendix G2: Settlement Settlement is how much the soil changes as a result of vertical stresses placed on it. Settlement is one of the most important geotechnical concepts to consider because it governs foundation design for structures. Estimating settlement mainly depends on soil properties, especially whether the soil is cohesive, like clay, or non-cohesive, like sand. In this project, there was no indication of a cohesive clay layer, so more focus is spent on estimating the settlement on granular soils. Moreover, since no clay is assumed to be present, it is recommended that the project use shallow foundations. There are many methods that exist for estimating settlement of shallow foundations on granular soils, but one method in particular suited this project. The Schmertmann (1971) method outlined in Soils and Foundations by Liu et. al was used in this case to estimate the settlement. When clay soil is involved, the time rate of consolidation is important to consider because settlement generally increases with time for this type of soil. When it comes to more granular soil like the kind that exists at the project site, time rate of consolidation is not a major concern because by the end of construction, most of the settlement from the loads will have occurred. There are three main methods discussed in Soils and Foundations for estimating settlements of shallow foundations on granular soil: Bazaraa, Burkand and Burbridge, and Schmertmann. Each of these methods estimate settlement empirically, meaning that they rely on data collected at a given site. Standard penetration testing (SPT) is the main method for empirical results used in Bazaraa and Burkand and Burbridge. SPT could also be used in the Schmertmann method, but cone penetration testing is used as the main data collection method, which is also the method used for this project’s site testing. The Schmertmann method uses the following equations: 𝑆𝑆𝑓𝑓=𝐶𝐶1𝐶𝐶2 𝛥𝛥𝛥𝛥∑2𝐵𝐵0 (𝐼𝐼𝑧𝑧/𝐸𝐸𝑠𝑠)𝛥𝛥𝑧𝑧 (for L/B = 0) 𝑆𝑆𝑓𝑓=𝐶𝐶1𝐶𝐶2 𝛥𝛥𝛥𝛥∑4𝐵𝐵0 (𝐼𝐼𝑧𝑧/𝐸𝐸𝑠𝑠)𝛥𝛥𝑧𝑧 (for L/B > 10) where 𝑆𝑆𝑓𝑓=𝑠𝑠𝐴𝐴𝑐𝑐𝑐𝑐𝐴𝐴𝐴𝐴𝑠𝑠𝐴𝐴𝑠𝑠𝑐𝑐 𝐴𝐴𝑜𝑜 𝑜𝑜𝐴𝐴𝑓𝑓𝑠𝑠𝑙𝑙𝑎𝑎𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 𝑐𝑐 𝑦𝑦𝐴𝐴𝑎𝑎𝐴𝐴𝑠𝑠 𝑎𝑎𝑜𝑜𝑐𝑐𝐴𝐴𝐴𝐴 𝑐𝑐𝐴𝐴𝑠𝑠𝑠𝑠𝑐𝑐𝐴𝐴𝑓𝑓𝑐𝑐𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 𝐶𝐶1 = 𝑐𝑐𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝑐𝑐𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 𝑜𝑜𝑎𝑎𝑐𝑐𝑐𝑐𝐴𝐴𝐴𝐴 𝑜𝑜𝐴𝐴𝐴𝐴 𝐴𝐴𝑜𝑜𝑜𝑜𝐴𝐴𝑐𝑐𝑐𝑐 𝐴𝐴𝑜𝑜 𝑙𝑙𝐴𝐴𝛥𝛥𝑐𝑐ℎ 𝐴𝐴𝑜𝑜 𝑜𝑜𝐴𝐴𝑓𝑓𝑠𝑠𝑙𝑙𝑎𝑎𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 𝐴𝐴𝑠𝑠𝐴𝐴𝐴𝐴𝑙𝑙𝑠𝑠𝐴𝐴𝑠𝑠𝑐𝑐 𝐶𝐶1 =1 −0.5(𝛥𝛥0/𝛥𝛥𝛥𝛥) where 𝛥𝛥0 =𝑠𝑠𝐴𝐴𝑠𝑠𝐴𝐴 𝐴𝐴𝑜𝑜𝐴𝐴𝐴𝐴𝐴𝐴𝑓𝑓𝐴𝐴𝑙𝑙𝐴𝐴𝑠𝑠 𝛥𝛥𝐴𝐴𝐴𝐴𝑠𝑠𝑠𝑠𝑓𝑓𝐴𝐴𝐴𝐴 𝑎𝑎𝑐𝑐 𝐴𝐴𝑎𝑎𝑠𝑠𝐴𝐴 𝐴𝐴𝑜𝑜 𝑜𝑜𝐴𝐴𝑓𝑓𝑠𝑠𝑙𝑙𝑎𝑎𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 (𝑘𝑘𝑁𝑁/𝑠𝑠2) 𝛥𝛥𝛥𝛥=𝑠𝑠𝐴𝐴𝑐𝑐 𝑜𝑜𝐴𝐴𝑓𝑓𝑠𝑠𝑙𝑙𝑎𝑎𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 𝛥𝛥𝐴𝐴𝐴𝐴𝑠𝑠𝑠𝑠𝑓𝑓𝐴𝐴𝐴𝐴 𝑠𝑠𝑠𝑠𝛥𝛥𝐴𝐴𝑠𝑠𝐴𝐴𝑙𝑙 𝐴𝐴𝑠𝑠𝑐𝑐𝐴𝐴 𝑠𝑠𝐴𝐴𝑠𝑠𝐴𝐴 𝑎𝑎𝑐𝑐 𝐴𝐴𝑎𝑎𝑠𝑠𝐴𝐴 𝐴𝐴𝑜𝑜 𝑜𝑜𝐴𝐴𝑓𝑓𝑠𝑠𝑙𝑙𝑎𝑎𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 (𝑘𝑘𝑁𝑁/𝑠𝑠2 ) 𝐶𝐶2=𝑐𝑐𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝑐𝑐𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 𝑜𝑜𝑎𝑎𝑐𝑐𝑐𝑐𝐴𝐴𝐴𝐴 𝑜𝑜𝐴𝐴𝐴𝐴 𝐴𝐴𝑜𝑜𝑜𝑜𝐴𝐴𝑐𝑐𝑐𝑐 𝐴𝐴𝑜𝑜 𝑐𝑐𝐴𝐴𝐴𝐴𝐴𝐴𝛥𝛥 𝑐𝑐𝑦𝑦𝛥𝛥𝐴𝐴 𝛥𝛥ℎ𝐴𝐴𝑠𝑠𝐴𝐴𝑠𝑠𝐴𝐴𝑠𝑠𝐴𝐴𝑠𝑠 𝑎𝑎𝑠𝑠𝑙𝑙 𝐴𝐴𝑐𝑐ℎ𝐴𝐴𝐴𝐴 𝑜𝑜𝑎𝑎𝑐𝑐𝑐𝑐𝐴𝐴𝐴𝐴𝑠𝑠 𝐴𝐴𝑜𝑜𝐴𝐴𝐴𝐴 𝑐𝑐𝑠𝑠𝑠𝑠𝐴𝐴 𝐶𝐶2 =1 +0.2(𝐴𝐴𝐴𝐴𝑓𝑓 10𝑐𝑐) where 122 𝑐𝑐=𝑐𝑐𝑠𝑠𝑠𝑠𝐴𝐴 𝑠𝑠𝑠𝑠 𝑦𝑦𝐴𝐴𝑎𝑎𝐴𝐴𝑠𝑠 𝐼𝐼𝑧𝑧=𝑠𝑠𝑐𝑐𝐴𝐴𝑎𝑎𝑠𝑠𝑠𝑠 𝑠𝑠𝑠𝑠𝑜𝑜𝐴𝐴𝑓𝑓𝐴𝐴𝑠𝑠𝑐𝑐𝐴𝐴 𝑜𝑜𝑎𝑎𝑐𝑐𝑐𝑐𝐴𝐴𝐴𝐴 𝑜𝑜𝐴𝐴𝐴𝐴 𝑠𝑠𝐴𝐴𝑠𝑠𝐴𝐴 𝑧𝑧𝐴𝐴𝑠𝑠𝐴𝐴 𝑧𝑧 𝑙𝑙𝐴𝐴𝛥𝛥𝑐𝑐ℎ 𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 𝑜𝑜𝐴𝐴𝑓𝑓𝑠𝑠𝑙𝑙𝑎𝑎𝑐𝑐𝑠𝑠𝐴𝐴𝑠𝑠 (𝑙𝑙𝑠𝑠𝑠𝑠𝐴𝐴𝑠𝑠𝑠𝑠𝑠𝑠𝐴𝐴𝑠𝑠𝐴𝐴𝐴𝐴𝑠𝑠𝑠𝑠) 𝐸𝐸𝑠𝑠=𝑠𝑠𝐴𝐴𝑙𝑙𝑓𝑓𝐴𝐴𝑓𝑓𝑠𝑠 𝐴𝐴𝑜𝑜 𝐴𝐴𝐴𝐴𝑎𝑎𝑠𝑠𝑐𝑐𝑠𝑠𝑐𝑐𝑠𝑠𝑐𝑐𝑦𝑦 𝐴𝐴𝑜𝑜 𝑠𝑠𝑎𝑎𝑠𝑠𝑙𝑙 (𝑘𝑘𝑁𝑁/𝑠𝑠2) 𝑧𝑧=𝑠𝑠𝑎𝑎𝑠𝑠𝑙𝑙′𝑠𝑠 𝐴𝐴𝑎𝑎𝑦𝑦𝐴𝐴𝐴𝐴 𝑐𝑐ℎ𝑠𝑠𝑐𝑐𝑘𝑘𝑠𝑠𝐴𝐴𝑠𝑠𝑠𝑠 (𝑠𝑠) The modulus of elasticity will depend on the cone penetration resistance, 𝑞𝑞𝑓𝑓. It’s relationship to the elastic modulus depends on the soil type. The cone penetration resistance can also be related to SPT as summarized by the table below. Table G3: The relationship between elastic modulus, cone penetration resistance, and standard penetrations blows. Soil Type Approximate Values of 𝑬𝑬𝒔𝒔 In Terms of 𝑵𝑵 In Terms of 𝒒𝒒𝒄𝒄 Sand-silt mixture 4N 1.5𝑞𝑞𝑓𝑓 Fine-to-medium sands, fine- medium-coarse sands 7-10N 2-3𝑞𝑞𝑓𝑓 Sand-gravel mixtures 12N 4𝑞𝑞𝑓𝑓 Figures G1 and G2 may be useful in determining what soil type is present, and thus, which relationship to use when approximating the elastic modulus. Figure G4: Criteria for describing the structure of coarse-grained soils in their natural or in- place condition. 123 \ Figure G5: Typical values of void ratio and porosity of granular soils. Appendix G3: Scour Scour is a destructive phenomenon in which a flood erodes and weathers the soil around the foundations of a bridge. Bridges are often designed for hydraulic resistance to a flood of a certain size, often the 100-year flood. Bridges must resist failing due to scour during floods that are larger than the design flood, because bridges are damaged in floods and destroyed by scour. Flood damage can be repaired quickly, bridge destruction cannot. Therefore, it makes economic sense to build a bridge that can withstand a larger flood than the design flood to ward off the chance that the bridge must be totally replaced before the end of its service life. What follows is a condensed version of the explanation of how to conduct a scour analysis from Hydraulic Engineering Circular no. 18, “Evaluating Scour at Bridges.” Evaluating Scour at Bridges. Hydraulic Engineering Circular No. 18. 2012. Adapted from HEC 2.2-2.4 2.2 GENERAL DESIGN PROCEDURE The general design procedure for scour outlined in the following steps is recommended for determining bridge type, size, and location (TS&L) of substructure units: 124 Step 1. Select the flood event(s) that are expected to produce appropriately severe scour conditions. Balancing risk of failure against safety, reliability, and economic requirements suggests that scour should be evaluated for an event larger than the hydraulic design flood. For example, if a bridge is designed for a hydraulic capacity of Q25, then the Scour Design Flood Frequency would be for a Q50 flood and the Scour Design Check Flood Frequency would be the Q100 flood. In all cases, if there is an overtopping event that causes greater hydraulic stresses to the bridge than the hydraulic design event then that flood should be used for computing scour and designing the foundations. Overtopping refers to flow over the approach embankment(s), the bridge itself, or both. See Appendix B for a discussion of extreme event combinations and design flood exceedance probabilities. [Barb Comment: We are designing for 100 year flood = design flood, so according to [1] (p 2.1) · Hydraulic design flood frequency, Qd = 100 yrs · Scour design flood frequency, Qs = 200 yrs · Scour design check flood frequency, Qc = 500 yrs · Unsure if the magnitude of overtopping flood would > Qd or Qs, but worth checking. Step 2. Develop hydraulic parameters necessary to estimate scour for the flood flows in Step 1. This is typically done by the application of a one- or two-dimensional hydraulic model. Care must be taken to evaluate the full range of hydraulic conditions that could impact the flow conditions at and near the bridge being designed. These conditions could include the effects of downstream tail water, confluences with other streams, etc.. For one-dimensional hydraulic analysis the U.S. Army Corps of Engineers (USACE) Hydrologic Engineering Center's River Analysis System (HEC-RAS) is recommended for this task (USACE 2010a). For bridges with complex flow characteristics such as flow on embankments skewed to the flood flows, multiple floodplain openings, wide flood plains, highly contracted flows, etc., it is recommended that the FHWA's FST2DH (FHWA 2003b) two-dimensional hydraulic analysis model be used. Step 3. Using the six-step Specific Design Approach for Scour in Section 2.4, estimate total scour for the hydraulic conditions identified from Steps 1 and 2 above. The resulting scour computed from the selected flood event should be considered in the design of a foundation. For this condition, minimum geotechnical safety factors commonly accepted by FHWA, AASHTO, and DOTs should be applied. For example, for a pile designed to have its bearing capacity through friction, a commonly applied factor of safety ranges from two to three. Step 4. Plot the total scour depths obtained in Step 3 on a cross section of the stream channel and floodplain at the bridge site. 125 Step 5. Evaluate the results obtained in Steps 3 and 4 for reasonableness. Based on the judgment of a multi-disciplinary team of hydraulic, geotechnical, and structural engineers, the reasonableness of the results must be evaluated. There are many factors that could affect the magnitude of the overall scour estimate. They could include storm duration, erodibility of channel materials, flow conditions, ice and debris, and many others. In order to assure the most reliable estimates of scour, one must also have an understanding of the theory and development of the procedures used to determine scour. Based on the factors mentioned above, the scour depth(s) adopted for use in design may differ from the computed value(s). Step 6. Evaluate the proposed bridge size, configuration, and foundation elements on the basis of the scour analysis performed in Steps 3 through 5. Modify the design as necessary based on the following discussion: 1. Develop an understanding of the overall flood flow pattern at the bridge site for the design conditions. Also, develop an understanding of the dynamic channel and floodplain characteristics for the reach of the stream that contains the bridge. Use the understanding of these factors to identify those bridge elements most vulnerable to flood flows, channel change, and resulting scour. 2. To the extent possible, modify components of the bridge length, location, configuration, and sub-structure elements to minimize scour. The following factors can lead to reduced scour depths. a. Increase the bridge length. Increasing the bridge length generally reduces depths of flow and velocities through the bridge opening which reduces the magnitude of scour. b. Locate new or replacement bridges such as they experience as little scour as possible. This means the bridge would cross the floodplain as perpendicular as possible to the flood flows and would be located in the floodplain where the conveyance is highest. c. Provide substructure elements that are not as susceptible to scour as others. For example, piers that are aligned with the flow do not experience as much scour as piers that are not aligned with the flow. Also, certain pier configurations are not as susceptible to scour as others. Round nosed piers are not as susceptible to scour as square nosed piers and circular piers are not as susceptible to scour caused from non-aligned flow as are solid-wall piers. d. Design and install guide banks to reduce scour at the abutments. Guide banks help align flow with the abutments and minimize the adverse flow conditions at the abutments that contribute to scour. Guide banks also provide an additional benefit in that they make the bridge opening more hydraulically efficient. 126 Step 7. Perform the bridge foundation analysis on the basis that all streambed material in the scour prism above the total scour line (Step 4) has been removed and is not available for bearing or lateral support. All foundations should be designed in accordance with the AASHTO Standard Specifications for Highway Bridges (AASHTO 1992a). In the case of a pile foundation, the piling should be designed for additional lateral restraint and column action because of the increase in unsupported pile length during and after scour. In areas where the local scour is confined to the proximity of the footing, the lateral ground stresses on the pile length which remains embedded may be significantly reduced from the pre-local scour conditions." Hydraulic Engineering Circular pp 2.2-2.4 127 Appendix H: Geotechnical Analysis of Proposed Bridge Site Before designing the necessary foundations or general structures needed for the bridge, it was important to learn more about the soil present and its effects on scour, bearing capacity, and settlement. The goal of these analyses, including scour, is to determine any critical conditions that drive the engineering decisions on the foundations of the bridge. The following sections provide a brief overview of what soil conditions were found after two different occasions of soil testing. Appendix H1: Various Geotechnical Tests The table below is a compilation of various geotechnical tests possible. This table was helpful in determining which tests were needed and possible given the equipment available. For the first soil analysis, a sieve test was run on a sample of collected soil. In the second test, a Dynamic Cone Penetration (DCP) test was run in addition to a sieve test. Table H1: A list of possible geotechnical tests that may prove useful to the project from Sabatini et al, Geotechnical Circular No 5 (2002). Appendix H1.1: First Field Test, 10/4/2020 Geotechnical analyses are necessary to understand the current soil conditions of the proposed bridge site. A soil sample was taken at the location shown in Figure H2 approximately two feet below the surface of the ground as shown in Figure H3. After conducting a sieve test, the test data was analyzed to produce a grain size distribution (GSD), the coefficient of uniformity and curvature was found, and the unified soil classification (USC) guide was used to determine the soil characteristics. Tables H4 and H6 organize the grain size data by the percentage of soil 128 retained and passing to which were used the plot points on the GSD curves in Figures H5 and H8. Using the results shown in Tables H4 and H7 and the USC guide in Figure H10, the analysis concluded the soil is most likely well graded, and it is on the cusp of being classified as SP, gravelly sands with little or no fines, or SM-SW, sand with silt. Figure H2: Screenshot taken at time of soil collection providing satellite imagery with approximate coordinates of sample location. Figure H3: Photograph of hole dug to collect soil sample with a drawn on scale to depict hole depth. The image shows approximately a foot of darker, organic material near the surface and a lighter, sandier soil where the sample was collected from. 129 Table H4: Sieve analysis calculations of soil percentage retained and passing for sample A. Sieve No. Mass Retained (g) % Retained % Passing 4 .5 .032 99.968 10 .5 .032 99.936 20 17.5 1.12 98.816 40 287.0 18.5 80.316 60 509.5 32.9 47.416 100 348 22.5 24.916 200 217.5 14.0 10.916 Tin 169.5 10.93 0 Total 1550 ___ ___ 130 Figure H5: Grain size distribution curve using values calculated from Table H4. Additionally, the curve is annotated with the needed D10, D30, and D60 values. 131 Table H6: Summary of results from GSD curve and USC guide for soil sample A. Soil Sample A D10 = .075 mm D30 = .16 mm D60 = .3 mm Cu = 4 Cc = 1.14 Well graded: D60 >> D10, Cu > 6 (sand) and 1 < Cc < 4 Uniformly graded: 1 < Cu < 4 or 6 From Unified Soil Classification: Well graded, SP or SM-SW (sand with silt) Table H7: Sieve analysis calculations of soil percentage retained and passing for sample B. Sieve No. Mass Retained (g) % Retained % Passing 4 0 0 100 10 .5 .031 99.969 20 19 1.19 98.779 40 280 17.6 81.179 60 520 32.6 48.579 100 344.5 21.6 26.979 200 248 15.6 11.379 Tin 181 11.36 0 Total 1593 ___ ___ 132 Figure H8: Grain size distribution curve using values calculated from Table I7. Additionally, the curve is annotated with the needed D10, D30, and D60 values. 133 Table H9: Summary of results from GSD curve and USC guide for soil sample B. Soil Sample B D10 = .075 mm D30 = .15 mm D60 = .3 mm Cu = 4 Cc = 1 Well graded: D60 >> D10, Cu > 6 (sand) and 1 < Cc < 4 Uniformly graded: 1 < Cu < 4 or 6 From Unified Soil Classification: Well graded, SP or SM-SW (sand with silt) 134 Figure H10: Unified Soil Classification guide used to make conclusions for soil analyses as seen in Tables H4 and H7. Appendix H1.2: Second Field Test, 11/14/2020 November 14, 2020 Site Visit Conditions ❖ Around 12:30, a bit overcast ❖ Soil appeared to be damp from recent rainfall ❖ Hole from previous soil sample identified ❖ By 3:30, sunny Timeline ❖ 11 AM - Ruth, Auden, Professor Rubin meet next to Sage Hall and discuss plan for getting supplies ready to take to site 135 ❖ 11:30 AM - Meet at outdoor tennis court parking lot by the athletic fields, unpack necessary equipment, organize what tools and gear we would need to take and leave behind ❖ 11:45 AM - Begin hike to proposed bridge site ❖ 12:05 PM - Met Professor Howe along the trail near the Village Hill path connection ❖ 12:30 PM - Arrived at proposed site location ❖ 12:35 PM - Identified hole dug from initial soil sample, decided to use this location for auger and DCP tests, conducted a brief safety training for using the testing devices ❖ 12:45 PM - Started Zoom session for DC team, began to dig first auger hole ❖ 1:00 PM - Begin DCP Test ❖ 1:15 PM - Since hard rock hit around 50 in, second hole started about 1 foot next to first hole ❖ 1:45 PM - Tough roots hit, around 48 in, third hole started about two feet away from first hole ❖ 1:45 - 2:55 PM - Work on the third hole, conduct an auger test until about 5 ft. and DCP test to about 8.75 ft. ❖ 3 PM - Began clean up and started to pack ❖ 3:15 PM - Started hike back to tennis court parking lot ❖ 4 PM - Arrived to parking lot ❖ 4:15 PM - Met Professor Rubin at Ford Hall parking lot to unpack and fully label soil samples ❖ 4:30 PM - Walk back to Ziskind House 136 Figure H11: The data sheet created for the geotechnical test conducted on 11/14/20. Design Clinic 2020-2021 NOPS/MRGI Collected Site Data Date: 11/14/2020 Sample: “AH1” Equipment Used: DGSI Standard Hand Auger, Dynamic Cone Penetrometer with 9.4 lb hammer Sample Location: (42.3224232, -72.6567691) Sample Taken By: Ruth Penberthy, Aaron Rubin, Auden Balouch Depth to Bedrock: Unsure Depth to Water Table/Groundwater: Possibly 54-60 in below surface Depth (in.) Subsurface Condition Notes # blows / 3in Sample No. Additional Notes 0-24 First collected sample, darker brown, higher moisture, more organic material, ~24 in sandier material - 24-27 Still sandier material, more yellow in color 1 27-30 2 30-33 2 33-36 2 36-39 2 A 39-42 3 42-45 3 45-48 7 48-51 7 B Ended second hole here, hit dense roots 137 51-54 *21* Ended first experimental hole here, hit rock like material hence the higher blow count 54-57 Started to become much drier, possibly suggesting water table is above this depth, brighter yellow color 3 Started to become so dry that samples couldn’t be extracted, poured water on hole in attempt to 57-60 9 C 60-63 9 63-66 8 D 66-69 Started to hit gravel, making it difficult to extract soil 11 Sample E might indicate possible signs of glacial deposit 69-72 8 E Depth (in.) Subsurface Condition Notes # blows / 3in Sample No. Additional Notes 72-75 9 75-78 7 78-81 23 81-84 35 84-87 14 87-90 30 90-93 24 93-96 38 138 96-99 43 99-102 100 Figure H12: The GSD graph for sample C. Table H13: The USC card for sample C. 139 Soil Sample C D10 = .15 mm D30 = .3 mm D60 = 2.9 mm Cu = 19.3 Cc = .207 Poorly graded: D60 >> D10 From Unified Soil Classification: SP, poorly graded sands or gravelly sands, little or no fines 140 Figure H14: The GSD for sample E. Table H15: The USC card for sample E. 141 Soil Sample E D10 = .15 mm D30 = .37 mm D60 = 3 mm Cu = 20 Cc = .304 Poorly graded: D60 >> D10, From Unified Soil Classification: SP, poorly graded sands or gravelly sands, little or no fines 142 Appendix I. Footing Calculations This section outlines the process used to create a bearing capacity, contact pressure, and retaining wall calculator in Google Sheets. Much of the information in these calculators is based on results from the dynamic cone penetration (DCP) test that was done on the side of the Mill River that is closest to the agricultural fields. Below is a screenshot of the DCP datasheet. The most important columns in this data are the DCP (Blows/foot), Angle of Internal friction (degrees), and Unit Weight of Soil (lbs/ft^3). Throughout these sections, this datasheet can be referenced so it is clear where these values come from as well as how they are related. Figure I1: The DCP datasheet with information used to create the bearing capacity, contact pressure, and factor of safety calculators. 143 Appendix I1: Bearing Capacity The footing designed for this project was created by following the procedures outlined in Chapter 9: Shallow Foundations and Chapter 13: Retaining Structures in the 7th Edition of Soils and Foundations by Liu and Evett. One of the first steps of this procedure was to calculate bearing capacity. A Google Sheet was created to help streamline the design process as dimensions like Df, distance from ground surface, and B, width of continuous footing, could be changed easily and a new bearing capacity would result. An image of what this calculator looks like can be seen below. Figure I2: A screenshot of the bearing capacity calculator. Explaining how the Google Sheet was created begins first with the type of footing needed in this design. Based on the text, it was decided that a continuous footing would be the most appropriate option. An example of what this looks like is shown below. Figure I3: Simple diagram of a continuous footing from figure 9-2 in Soils and Foundations. 144 The ultimate bearing capacity equation changes based on the type of footing, so the equation that corresponds to the continuous footing was used. In that equation, there are the terms Nc, Nq, and Ny, known as the Terzaghi bearing capacity factors. These can be seen below. Ultimate bearing capacity equation for a continuous footing. These factors rely on characteristics of the soil, specifically its cohesion and internal angle of friction. Both of these factors were determined previously using the results from the dynamic cone penetration (DCP) testing. The table that relates blows per foot to internal friction angle is shown below. Table I3: Relation between bearing capacity factors and internal friction angle. 145 Using the blows of the DCP test, the internal friction angle was deduced, and thus, the bearing capacity factors. Since, however, the soil test results showed no evidence of cohesive soil, the soil was assumed to be cohesionless which meant that the Nc term could be ignored. The next parameters needed were the unit weights of the soil above the base of the footing, y1, and the unit weight of the soil below the footing, y2. Based on the blows per foot, the unit weights were able to be estimated. The table used for this relationship is shown below. Table I4: Empirical values for unit weight of granular soils based on the dynamic cone penetration blows per foot (from Bowels, Foundation Analysis). Appendix I2: Contact Pressure After the bearing capacity was calculated, the next step in the process was to calculate contact pressure. A screenshot of the contact pressure calculator is shown below. Figure I5: Contact pressure calculation sheet. 146 Contact pressure relies mainly on the geometry of the footing itself. Some preliminary values for the general dimensions of the footing were used initially, but after various iterations of the design process, the final geometries are reflected in the screenshot above. More specifically, the contact pressure relied on the total axial vertical load. In order to calculate that value, the column load, the weight of the footing’s base pad, the weight of the footing’s pedestal, and the weight of the backfill soil were needed. Starting with the column load, that was a very conservative estimate of the load each footing would have to be designed for. This value was informed by the dead load, snow load, and wind load the bridge would experience divided by two since there would be two footings on either side supporting it. Next, the weight of the footing’s base pad was calculated using the unit weight of concrete, the area of the footing pad, and the thickness of said pad. The weight of the footing’s pedestal was calculated similarly; only the area of the stem, its thickness, and its length were used along with the unit weight of concrete. The weight of the backfill soil was calculated using the area of the footing base minus the area of the footing web multiplied by the length of the stem and the unit weight of soil. Finally, all of these values could be added together to get the total axial load on the footing. This could then be divided by the area of the footing’s base pad which resulted in the final contact pressure. Appendix I3: Retaining Wall In addition to the bearing capacity and contact pressure calculations, a retaining wall analysis was needed to ensure the footing could withstand overturning and sliding. One of the first values for calculating the factor of safety for overturning and sliding is active earth pressure. The calculator necessary for this calculation can be seen below. 147 Figure I6: Part of the retaining wall calculation sheet showing active earth pressure. Active earth pressure depends on the earth pressure coefficient and the depth of the footing base as seen in the equation below. The earth pressure coefficient is determined by the soil type. In this case, the soil at the site was assumed to be type 1 which is “coarse-grained soil without admixture of fine soil particles, very free draining (clean sand, gravel, broken stone).” According to Figure 13-3 in Chapter 13, the earth pressure coefficient with this soil and slope is 30. 148 Figure I7: Active earth pressure coefficient for soil type 1. Earth pressure is then used to determine the overturning moment, and thus its factor of safety, as well as the sliding factor of safety. All of these factors also depend on the geometry of the footing, of course. In fact, part of the calculator is specifically used for finding the moments about the toe of the footing as well as the weight of each part of the footing. With the geometries of the footing, earth pressure, and moments set, the factors of safety can be easily determined using the equations below. Figure I8: The factor of safety equations for overturning and sliding. The results of the factor of safety calculations can then be compared with the allowable factor of safety for these two parameters to see if the geometries selected for the footing are appropriate and safe. The allowable factors for each factor of safety are provided below. 149 Figure I9: Factor of safety ranges for overturning and sliding. The results of the factor of safety analysis can be seen in the calculator. The “OK” signifies that the footing geometries selected are theoretically appropriate for the given bridge design. Figure I10: Factor of safety evaluation for footing geometries. Appendix J. Truss Research The following appendix section includes the research done on the carious truss shapes along with a corresponding brief description. 150 Appendix J1: The K Truss The K Truss is a variation on the Parker Truss which is a variation of the Pratt Truss. There are two configurations of the K truss; the first is shown in Figure 13a which forms a diamond of sorts at the center of the bridge and the other in Figure 13b forms more of an “X” at the center. Figure J1: The first form of the K Truss where the center of the structure forms a diamond. The advantage of using the K Truss is that it reduces the likelihood of buckling under pressure due to the shorter diagonal members used. However, this design is more complex because of all the members involved 17. This increases the cost and time needed to construct it. Although unique in design, the complexity involved with the K Truss is unnecessary for this project, especially when there are other more simple designs available. Figure J2: The second form of the K Truss that forms an “X” shape at the center of the structure. Appendix J2: The Warren Truss The Warren Truss is one of the most widely known and used truss bridges. It’s name comes from its patented design by James Warren and is made up of equilateral triangles connected along the top and bottom chords which span the length of the bridge. It is possible to add both vertical members in between the equilateral triangles and overhead bracing if desired. Warren Trusses work best when the load is distributed as each member takes on a portion of the load. That being 17 https://www.machines4u.com.au/mag/4-types-of-truss-bridges-which-is-worth-the-weight/ 151 said, the Warren Truss’s performance under concentrated loads is not as optimized as it is for distributed loads 18. Figure J3.1: The most basic Warren Truss configuration made up of equilateral triangles. Figure J3.2: An additional vertical member added to the most basic Warren Truss configuration. Unlike the K Truss, the Warren Truss is very simple in design, so the cost and construction time are minimized. Although the Warren Truss is said to work best for distributed loads, it could be a viable option because of its simple and cost effective design. Some real life examples are shown in Figures J4 and J5 19. These are possible designs that could work for this project with some variation in materials as a possibility. 18 https://skyciv.com/docs/tutorials/truss-tutorials/types-of-truss-structures/#k 19 http://www.wheeler-con.com/recreation-bridges/steel-recreation-bridges/warren-truss-prefabricated- steel-bridges/ 152 Figure J4: Warren Truss with wood decking and handrails and steel superstructure. 153 Figure J5: Warren Truss with steel vertical members, wood decking and handrails, and an overhead bracing. Two other variations of the Warren Truss include the Double Intersection Warren and the Lattice. The Double Intersection Warren is equivalent to two warren bridges superimposed and offset over each other as shown in Figure J6. Figure J6: Two Warren Trusses superimposed and offset over each other. The Lattice is a bit more complex because it has more than two warren trusses virtually superimposed and stacked atop each other as seen in Figure J7. Figure J7: More than two Warren Trusses superimposed and stacked. 154 Since these are all fundamentally Warren Trusses, they have relatively the same advantages of load carrying capacity, but increase in complexity, and thus cost, with the addition of more members. The Warren Truss itself is a viable option for this project, and although unique, the Lattice’s complexity is not necessary for this project. Appendix J3: The Pratt Truss: The Pratt Truss 20 was made of right triangles oriented so that the diagonal members point toward the center of the bridge, aside from the two right triangles at either end of the bridge (Figure 20). The Pratt Truss can support heavy loads, can span short and long distances, and each member is used efficiently. Although each member is used efficiently, the bridge can end up being relatively heavy because of all of the components. Moreover, materials can be wasted if the truss is not designed properly. Appendix J4: The Baltimore Truss: The Baltimore Truss is a variation on the Pratt Truss where additional diagonals are added specifically to the lower parts of the truss. This design is typically used for railroad designs, but it is a simple design with high strength. Figure J8: The Baltimore Truss Appendix J5: The Howe Truss: The Howe Truss can be thought of as the opposite of the Pratt Truss; it is made up of right triangles with diagonal members that point away from the center of the bridge. It has similar advantages and disadvantages as the Pratt Truss. 20 https://navajocodetalkers.org/the-pros-and-cons-of-truss-bridges/ 155 Figure J9: The Pratt Truss above compared to the Howe Truss below 21. Appendix J6: The Bowstring Truss: The Bowstring Truss has an arched top chord that can either meet the bottom chord at the deck or the end post that connects the bottom and top chords. The Bowstring truss has diagonal members oriented in a Pratt-like way in that they point toward the center of the bridge. This type of truss is unlike its more square counterparts, making its design stick out amongst the rest. 21 https://www.quora.com/What-is-pratt-truss 156 Figure J10: Bowstring Truss in Durango, CO where the top chord meets the bottom chord at the deck.22 22 http://www.wheeler-con.com/recreation-bridges/steel-recreation-bridges/bowstring-truss/ 157 Figure J11: Bowstring Truss in Savannah, IL where the top chord meets the bottom chord at the deck and the diagonal trusses meet each other in the middle of each section10. 158 Appendix K: Decking Material Research The following is research done on the various types of decking material. Appendix K1 Wood: Wood decking for bridges is typically made up of sawn lumber planks, nail-laminated lumber (nail-lam), or glue-laminated lumber (glulam). Sawn lumber planks for decking is one of the oldest and most simple methods used in bridge decking. It can be oriented in the transverse or longitudinal direction of the bridge, but it is not water resistant and is subject to weathering. Since the introduction of glulam, nail-lam has become less common. Nail-laminated decks are most commonly used in a transverse orientation on sawn lumber or steel beams spaced 2 to 6 feet apart. As spaces between beams increases, the service life decreases for this type of decking because of deflection and variation in water content. According to the United States Department of Agriculture 23 (USDA), glulam is the “...most common type of timber deck and is used in two basic configurations, non-interconnected and doweled. Non-interconnected panels are placed edge to edge, with no connection between adjacent panels. Doweled panels are interconnected with steel dowels to improve load distribution and reduce differential displacements at the panel joints. Doweled panels are more costly to fabricate and construct but can result in thinner decks and better performance for asphalt wearing surfaces. Glulam decks are stronger and stiffer than conventional plank or nail- laminated decks because of the homogeneous bond between laminations and the dispersion of strength-reducing characteristics of glulam. Glulam panels can be constructed to form a watertight surface and afford protection for supporting beams and other components. Because of their increased stiffness, glulam decks also provide a firm base for asphalt pavement, which is frequently used as the wearing surface. Panels are completely fabricated and drilled for deck attachment prior to preservative treatment, producing estimated service lives of 50 years or more.” Appendix K2: Steel For steel decking, it is typically broken up into open grid decks, half filled grid decks, filled grid decks, and Exodermic decks. Open grid decks are steel grids that are not filled with concrete. While walking over this deck, one would see through the floor below. Half filled grid decks are partially filled with concrete making them lighter in weight while keeping its stability. Filled grid 23 https://www.fpl.fs.fed.us/documnts/misc/em7700_8--entire-publication.pdf 159 decks are completely filled with concrete, but can only span 10 ft. Exodermic decks is an unfilled steel grid with a slab of reinforced concrete over it. These offer greater span capacities and have a slight weight advantage over the half filled grid decks 24. Figure K1: Diagrams of half filled grid decking (top left), fully filled grid decking (top right), Exodermic decking (bottom left), and open grid decking (bottom right). Appendix K3: Concrete Concrete decking is the most common for steel bridges. They can be reinforced with steel and can either come precast or be poured on site. Although most common and simple, concrete has high environmental impacts compared to other materials like wood, steel, and FRP. The aesthetics of concrete are not particularly attractive or adjustable besides adding paint that would have to be reapplied after a certain amount of time or dye during the manufacturing process. 24 http://www.bgfma.org/grids.htm 160 Appendix K4: Fiber Reinforced Plastic (FRP) According to the American Concrete Institute25, FRP “...materials are composite materials that typically consist of strong fibers embedded in a resin matrix. The fibers provide strength and stiffness to the composite and generally carry most of the applied loads. The matrix acts to bond and protect the fibers and to provide for transfer of stress from fiber to fiber through shear stresses. The most common fibers are glass, carbon, and synthetic fibers.” Over the years, using FRP materials for bridge structures and bridge decking has become more popular. The material is strong, lightweight, has a straightforward installation process, and does not require much maintenance when installed. In addition, FRP does not rot, warp, corrode, or conduct electricity. All of the previously listed are advantages of FRP, but it is not a perfect material, however. Some of the disadvantages of FRP are that it uses different drill bits and saw blades typically used for steel and timber, lack of experience with them in industry, lack of standards and codes, and high cost relative to timber and unpainted low-carbon steel 26. Two tables 27 comparing characteristics of FRP, wood, steel, and aluminium are provided below. 25 https://www.concrete.org/topicsinconcrete/topicdetail/Fiber%20Reinforced%20Polymer?search=Fiber%20 Reinforced%20Polymer 26 https://www.fs.fed.us/t- d/pubs/htmlpubs/htm06232824/page03.htm#:~:text=One%20disadvantage%20of%20FRP%20materials,u sed%20with%20wood%20or%20steel. 27 https://bedfordreinforced.com/resources/#product-literature 161 Table K2: A table comparing the attributes of FRP, aluminum, steel, and wood decking materials. 162 163 Appendix K5: Decking Selection - Matrix Scoring Table K3: Scoring descriptions for 1s and 5s in the decking matrix. Category Rating 1 Rating 5 Environmental Impact very hazardous to the environment not hazardous at all Maintenance heavily maintained little to no maintenance Impact Resistance easily deform on impact hard to permanently deform Weight very heavy lightweight Cost expensive upfront and in the future inexpensive upfront and in the future Aesthetics material does not align with overall aesthetics of bridge or natural environment material matches overall aesthetics of bridge and fits natural environment 164 Appendix L. Superstructure Concept Selection This appendix provides more details on the bridge concept selection process and the matrix that corresponds to it. The names of the conceptual designs in this appendix do not match the report, but the three concepts that are mentioned in the report go by the names of “kinda #artsy” (Bowstring), “Another Day, Another Dollar” (Pratt Option 1), and “She’ll Do” (Pratt Option 2). Appendix L1: Bridge Concepts The bridge concepts are described in the table below from the most extravagant on the left to the least extravagant on the right. Table L1: All five concepts considered for the bridge component of the project Maximum Arte Kinda Artsy Another Day Another Dollar Lumberjacks Dream She’ll do Superstructure Bowstring Bowstring Pratt Pratt Pratt Structural Material Wood Steel Steel Wood Steel Lookout Type Bubble in the Middle Bubble in the Middle Non- structural middle On abutment On abutment Art Location on Bridge Sides over water Railing under abutments Sides over water Railings near abutment Railings near abutments Appendix L2: Initial Evaluation Appendix L2.1: Reference Concept “Another Day Another Dollar” ● SUPERSTRUCTURE: pratt ● STRUCTURAL MATERIAL: steel ● LOOKOUT TYPE: non-structural middle ● ART LOCATION: sides over water This concept was selected as our reference because it’s what we would like to do if approval from locals and money permit its construction. 165 Table L2: Filled Selection Matrix (Pugh) Selection Criteria Maximum Arte kinda #artsy Another Day Another Dollar (ref) lumberjack’s dream. She’ll Do Abutment Impact + + 0 + + Carbon Footprint + 0 0 + 0 Construction Cost - - 0 - 0 Maintenance Cost - 0 0 - 0 Visual Weight - + 0 - + Interactive Potential + + 0 + + Sum Total 0 2 0 0 3 Rank 3 2 3 3 1 Based on our Pugh chart, we would screen out the Maximum Arte and She’ll Do options because they were worse than our reference bridge. Note that it was assumed that the wooden bridges would be more visually intrusive than the steel bridges because a wooden bridge of the same strength and span as a steel bridge would require larger members and a larger truss, which would contribute to visual bulk and might create backlash. 166 Appendix L2.2: Rating Scales We chose to use a five-level rating scale because we don’t have much information on how these options differ. A three-point scale is informative enough for our purposes, but without more data a finer scale isn’t worth much. The meaning of each number is given in the rubric below. A 5 represents the best possible rank in that category and a 1 the worst. All ratings were given relative to a theoretical steel Pratt truss bridge because we felt much more comfortable relating our options to a given bridge than trying to figure out where our options fell on more absolute scales. (Easier to say “this is lighter than a steel Pratt truss bridge - give it a 1” than “this is relatively light considering the vast array of non-truss options for a pedestrian bridge of this span...give it a 2 probably?”) Table L3: Five Point Weighing Scale Rubric 5 ★★★★★ 4 ★★★★ 3 ★★★ 2 ★★ 1 ★ Abutment Impact Significantly less impact than steel bridge with low wind loading. Somewhat less impact than steel bridges with low wind loading. Average impact to steel bridge with low wind loading. Somewhat greater impact than steel bridge with low wind loading. Significantly greater impact than steel bridge with low wind loading. Carbon Footprint Significantly smaller carbon footprint than steel Pratt truss bridge Somewhat smaller carbon footprint than steel Pratt truss bridge. Average carbon footprint for steel Pratt truss bridge Somewhat larger carbon footprint than steel Pratt truss bridge. Significantly larger carbon footprint than steel Pratt truss bridge Construction Cost Significantly cheaper than cost of steel Pratt truss bridge. Somewhat cheaper than steel Pratt truss bridge. Average cost of steel Pratt truss bridge. Somewhat more expensive than the steel Pratt truss bridge but still reasonable. Significantly more expensive than steel Pratt truss bridge. Maintenance Cost Very little maintenance over the life of the bridge Sporadic required yearly upkeep that add to the costs of the bridge Regular maintenance required thus adding cost Requires consistent yearly upkeep Excessive maintenance required thus greatly increasing costs Visual Weight Minimally intrusive bridge, very classic New England look. Low profile. Minor intrusion in the space as design is slimmer and blends with region architecture Intrudes moderately on the space but does have more New England Style accents Intrudes on the space but is slim and more minimalist in appeal Intrudes significantly on the space (bulky or out- of-place looking bridge). Interactive Potential Ample space on the bridge that allows for art installation or appropriate scenic lookouts Moderate space available for installation of community pieces And moderate lookout potential Some space available for installation of community art pieces and lookout specification Minimal space available for art pieces and no particular scenic lookout Little-to-no space available for community art works and no particular scenic lookout 167 Appendix L2.3: Weighted Criteria Table 13: Selection Criterion Weights Selection Criteria Weight Abutment Impact 0.25 Carbon Footprint 0.075 Construction Cost 0.20 Maintenance Cost 0.20 Visual Weight 0.20 Interactive Potential 0.075 Sum Weight 1 The matrix above details the weight of each criterion deemed most appropriate by the team. As seen, abutment impact was rated most important considering it is the measure of safety that ensures the entire structure does not fail. Costs (both construction and maintenance) were weighted with equal importance because the budget imposes a constraint on the design of the bridge. Visual weight was weighted the same as the costs because our key stakeholders considered the visual appeal and simplicity of the bridge in the context of the river as very significant. While the carbon footprint of the project is important, unfortunately it was not weighted significantly higher than any other design criterion due to the fact that carbon footprint is simply a minor consideration. In the same vein, interactive potential was also a minor consideration because the entire bridge serves the purpose of allowing for community interaction with the surrounding environment. 168 Appendix M: Superstructure Design Analysis - Dimensional Calculations Appendix M1: Loads and Hand Calculations for Beam Sizing Smith Design Clinic/KL&A CTM NOPS/MRGI Mill River Bridge Truss Geometry SK - 1 Apr 27, 2021 at 11:13 AM 210303 Bridge v1.r3d Y XZ Section Sets Top Chord Bottom Chord Vert Diag Appendix M2: Finite Element Analysis - Created by Technical Liaison Catherine Mulhern Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeDead LoadSK - 2Apr 27, 2021 at 10:53 AM210303 Bridge v1.r3d-.1k/ftYXZLoads: BLC 1, DL Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeUniform Live LoadSK - 3Apr 27, 2021 at 10:54 AM210303 Bridge v1.r3d-.45k/ftYXZLoads: BLC 2, uniform LL Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeSnow LoadSK - 4Apr 27, 2021 at 10:54 AM210303 Bridge v1.r3d-.15k/ftYXZLoads: BLC 3, SL Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeLive Load - Truck at Mid-pointSK - 5Apr 27, 2021 at 10:55 AM210303 Bridge v1.r3d-2k-8kYXZLoads: BLC 5, Truck - mid Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeLive Load - Truck at EndSK - 6Apr 27, 2021 at 10:56 AM210303 Bridge v1.r3d-2k-8kYXZLoads: BLC 6, Truck - end Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeLRFD Utilization (Uniform Live Load)SK - 7Apr 27, 2021 at 10:59 AM210303 Bridge v1.r3dYXZCode Check( Env )No Calc > 1.0.90-1.0.75-.90.50-.75 0.-.50 Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeDeflected Shape for Uniform Live LoadSK - 8Apr 27, 2021 at 11:00 AM210303 Bridge v1.r3dYXZResults for LC 9, LL Smith Design Clinic/KL&ACTMNOPS/MRGI Mill River BridgeUnfactored Reaction (DL+0.75LL+0.75SL)SK - 9Apr 27, 2021 at 11:03 AM210303 Bridge v1.r3d44.444.4YXZResults for LC 8, IBC 16-11 (b) Y-direction Reaction Units are k and k-ft 190 Appendix N: Visuals - GIS Maps Appendix N1: Current/Final Maps Figure N1: Existing path and important existing landmarks. Figure N2: Existing path with landmarks and areas of concern mapped out. 191 Figure N3: Slope Concern - A. Figure N4: Slope Concern - A Solution. 192 Figure N5: Slope Concern - B. Figure N6: Drainage Concern. 193 Figure N7: Slope Concern - C Solution. Figure N8: Slope Concern - D. 194 Figure N9: Shared use path to pedestrian bridge connection. Figure N10: New proposed path. 195 Figure N11: Shared use path with 10ft. buffer near the agricultural fields. 196 Appendix O: Visuals - Footing CAD Designs O1: Sheet 5 - Annotated footing and bridge complete super structure. 197 O2: Sheet - 6 Complete bridge superstructure. 198 O3: Sheet 7 - Annotated footing details. 199 Appendix P: Visuals - Superstructure CAD Designs & Drawings P1: Sheet - 1 Truss and truss height dimensions. 200 P2: Sheet 2 - Safety railing dimensions. 201 P3: Sheet 3 - Front view of the bridge. 202 P4: Path plan view. 203 P5: Preliminary bridge superimposed over natural site location. P6: Final bridge cross section view. 204 P7: Final front view visual. 205 Appendix Q: Brief Ecological Impacts Appendix Q1: Permitting When attempting to build a new trail, conduct new activity on an existing one, or add structures like bridges to said trail in the Commonwealth of Massachusetts, there are three stipulations that must be considered before any proposed project may proceed. First, it should be checked whether the activity in the area is either 100 feet from a wetland or within 200 feet of a stream or river. Then, the area should be checked to see whether it is considered a Priority Habitat or not. In addition, an archaeological assessment may be required for any activity that disturbs the soil near the river (e.g., the bridge abutments). Finally, if the project has been funded by the state or federal government, it is essential to know if the activity will be disturbing any soil. Should any of these three stipulations hold true for the activity within the proposed area, various corresponding forms will need to be filed in order to proceed. Figure Q1 displays these stipulations and their next steps in a simple checklist from the Department of Conservation and Recreation in Massachusetts. Figure Q1: Checklist of the permitting authorities that may have jurisdiction over a project in Massachusetts. In this project, all of the check boxes seen in Figure Q1 would be marked “Yes.” Sections 4.3.3a and 4.2.2b will go into more detail about how this project is affected by the Wetlands Protection Act as well as its distinction as a Priority Habitat Area. The third checkbox is not discussed in its own section because there are not many details to add besides filing a Project Notification form 206 with the Massachusetts Historical Commission. However, it should be noted that because this area is of high historical importance, there will most likely need to be an archaeological survey done before complete soil disturbance and construction begins. Appendix Q2: Wetlands Protection Act In 1972,28 Massachusetts created the Wetlands Protection Act (WPA) which designated many natural areas all over the Commonwealth as wetlands. These wetlands typically contain sensitive ecology, native species, and natural resources that need protection. Any time there is a proposed activity in or nearby one of these areas, the Conservation Commission must review the project to see if the area is under the WPA jurisdiction, and if so, determine whether the activity will be harmful to the sensitive area. In this case, the area this project is hoping to take place in, specifically the proposed bridge site, is approaching part of land that is considered wetland. The map depicted by Figure Q2 shows a GIS map from the MassDEP Wetland and Wetland Change Areas Map that clearly marks elements like shorelines, vernal pool, and most importantly, apparent wetland limits. As demonstrated, the proposed bridge site is near a designated wetland outlined in green. This area, of course, is definitely going to be within 200 feet of a river as it is a bridge to cross it, but it is made even more clear by its proximity to the Mill River outlined in blue. It is important to note that proximity to the wetland is significant but one cannot overlook the importance of the proximity to the river. Ensuring that the river is significantly protected from any extensive ecological alterations is the project priority, therefore protecting the river in turn protects any designated wetlands. 28 https://www.maccweb.org/ Accessed 10/21/20 207 Figure Q2: GIS map of the regions around the river recognized as wetlands in lime green should be considered during the permitting process of construction in later stages of design implementation. Appendix Q3: Priority Habitat Similar to the WPA, there are areas in the Commonwealth called Priority Habitat Areas that are protected by certain laws and regulations (Figure Q3). According to the MassGIS Mapping Tool, most of the area the project revolves around is within the limits of a protected habitat area. This distinction requires a Massachusetts Endangered Species Act (MESA) Review Checklist filed through the Massachusetts Natural Heritage and Endangered Species Program (NHESP). 208 Figure Q3: Outlined regions surrounding the Mill River that are recognized as protected areas that should be protected and considered for the permitting process and later design implementation. Appendix Q4: Agricultural Land Regulation on development occurring in close proximity to agricultural lands is in place to ensure that construction does not infringe on the right to farm for any residents of the Commonwealth of Massachusetts as described in the Right to Farm By-law in Article 97 of the Massachusetts Constitution 29. Oversight of this project can happen with the aid of local authority groups like the Agricultural Commission of Northampton, a member of the Massachusetts Association of Agricultural Commissions and the Massachusetts Farm Bureau. Their primary tasks as a commission include “1)facilitating the pursuit of agriculture, 2)promoting agriculture based economic opportunities, 3)mediating, advocating, educating, and/or negotiating on farming issues, 4)advocating for preservation of prime agricultural lands, 5)researching initiatives to create a sustainable agricultural community, and 6)coordinating the license of city agricultural land”30. Massachusetts is adamant at ensuring that local land holders maintain their autonomy and in consistent production through the provision of subsidies and other funding opportunities like the Agricultural Preservation Restriction Program 31. While there are local commissions that maintain agricultural lands from being developed, it is important to note that 29 http://www.massagcom.org/agcoms/WestportRTF.pdf 30 https://www.northamptonma.gov/196/Agricultural- Commission#:~:text=About%20the%20Agricultural%20Commission&text=Facilitates%20the%20pursuit%20of%2 0agriculture,preservation%20of%20prime%20agricultural%20lands 31 https://www.mass.gov/service-details/agricultural-preservation-restriction-apr-program-details 209 the area in which the project will take place should be considered a farm as defined by the Commonwealth of Massachusetts in order to fall under conservation regulations. As of now, much of the foreseen development does not surpass the boundaries of the agricultural fields near the Mill River. Overall other planning and conservation efforts should refer to sources like the Conservation and Land Use Planning under Massachusetts’ Chapter 61 Laws for further guidance on how to protect agricultural lands in proximity to recent developments 32. 32 https://masswoods.org/sites/masswoods.net/files/pdf-doc-ppt/Mount_Grace_Ch61_Info.pdf 210 Appendix R: Cost Analysis This appendix aims to provide more description on how the given prices were estimated in the cost estimate. First, for the shared use path, many of the values came from a Northampton Department of Public Works 33 project that contained an itemized list of materials costs. The hot mix asphalt and hot mix asphalt base course estimated prices were adjusted for inflation and used for this project’s needs. The cut and fill price was found using general information found on HomeAdvisor.34 The drainage solution came from a vegetated swale estimate from a public works website.35 Finally, the vegetation removal estimate was obtained from the 2017 Site Work & Landscape Costs 36 textbook, adjusted for inflation. As for the bridge, every estimate except for the Douglas Fir, geotechnical tests, and crane estimates came from the Washington State Department of Transportation 37 resource for quantities, costs, and estimates when building a pedestrian bridge. These estimates were also adjusted for inflation. The Douglas Fir 38 and crane 39 estimates came from private sellers while the geotechnical tests estimate came from Site Work & Landscape Costs. 33 http://archive.northamptonma.gov/WebLink/DocView.aspx?id=598116&dbid=0&repo=CityOfNorthampton Last Accessed 4/29/21. 34 https://www.homeadvisor.com/cost/landscape/excavate- land/#:~:text=Cut%20and%20fill%20runs%20anywhere,leveling%20terrain%20for%20a%20road Last Accessed 4/29/21. 35 http://www.malvern.org/wp-content/uploads/2013/03/vegswale.pdf Last Accessed 4/29/21. 36 Hale, Derrick. Site Work & Landscape Costs. 2017. Last Accessed 4/29/21. 37 https://www.wsdot.com/publications/manuals/fulltext/M23-50/chapter12.pdf Last Accessed 4/29/21. 38 https://www.woodboardsandbeams.com/timbers Last Accessed 4/29/21 39 https://www.bigrentz.com/blog/crane-rental-cost Last Accessed 4/29/21. 211 Appendix S: Drainage Matrix NOPS/MRGI Created by:RP, KG 5/1/2021 Status:Complete Preliminary Cost Analysis Tool Preliminary Cost Estimate Shared-Use Path Path References Units Amount/Quantity Researched Price per unit Cost https://driveways.promatcher.com/cost/massachusetts.aspx http://enginemechanics.tpub.com/14081/css/Plant-Mix-Construction-469.htm Cost Per Unit:Hot Mix Asphalt tons 2045 $131.39 $268,683.05 Hot Mix Asphalt Base Course tons 2,045 $118.25 $241,812.70 Cut and Fill - Concern B, C, D yd^3 10,126 $15.00 $151,890.00 Drainage Issue Solution ft 130 $8.50 $1,105.00 path length = 6254 ft Vegetation Removal Acres 1 $13,642.59 $13,642.59 path width = 10 ft Drainage Issue Labor cost $/hr 120 $20.00 $2,400.00 depth of mat = 5 in Total Cost =$679,533.34 tons = 1902.258333 Total Cost with a 25% Contingency Added = $849,416.68 waste factor = 142.669375 Pedestrian Bridge Total Tons required =2045 Units Amount/Quantity Researched Price per unit Cost Costs Per Unit: Steel Truss (Pre fab)ft^2 1300 $450.00 $585,000.00 Douglas Fir (decking)board feet 6552 $3.50 $22,932.00 Concrete Footing yd^3 51 $700.00 $35,700.00 Steel Railing linear ft 260 $100.00 $26,000.00 Shoring Excavation ft^2 180 $22.00 $3,960.00 Excavation (Eath + Rock)yd^3 740 $220.00 $162,800.00 Geotechnical Surveys linear ft 1080 $101.00 $109,080.00 Bridge References Crane Service $/day 30 $1,000.00 $30,000.00 Steel Girder ft^2 260 $330.00 $85,800.00 Truss https://concrete.promatcher.com/cost/massachusetts.aspx Total Cost = $1,061,272.00 Top Chord 140', HSS, 12'x6', .5" wall Total Cost with a 25% Contingency Added = $1,326,590.00 Bottom Chord 130', HSS, 10'x6', .5" wall http://www.excelbridge.com/for-engineers/cost Vertical Nodes HSS, 3'x3', .25" wall Total Preliminary Project Cost Diagonal Beams HSS, 3'x3', .25" wall https://www.dot.state.mn.us/stateaid/bridge/docs/cy2011bridgecostreport.pdf Total Project Costs = $2,176,007 1 board of douglas fir = 42 board feet 6552 Footing Volume (one side)680 ft^3 Bridge Dimensions for calcs: 150kips/ft^3 = 102,000 lbs 130' x 10' = 1300 ft^2 CITES (KARENA) https://porch.com/project-cost/cost-to-backfill-a-trench http://archive.northamptonma.gov/WebLink/DocView.aspx?id=598116&dbid=0&repo=CityOfNorthampton https://porch.com/project-cost/cost-to-set-concrete-formwork#:~:text=The%20national%20average%20materials%20cost,range%20of%20%24764.78%20to%20%24926.14. Adjust the prices based on what the links from Wayne say. Add and adjust the price for all of the things that Professor Rubin suggested https://www.bigrentz.com/blog/crane-rental-cost https://www.usinflationcalculator.com/ Table S1.Matrix outlining solutions to the drainage concern along the path near the agricultural fields Solution Advantages Disadvantages Reference Image Culvert ●Directly addresses and drains excess fluid that may puddle during heavy rain events ●Exposure of infrastructure can negatively impact aesthetic of the region as a result of continual erosion ●High opportunity for ecological disruption at installment ●Inadequate sizing can result in flooding and potential path failure1 Figure 1. Culvert in Greenfield, MA currently undergoing construction1 Permeable Pavement ●Supports fluid drainage in the region that can help reduce the splashing zones in regions of concern after higher rainfall events ●Cost is about 20-25% times as expensive as regular asphalt2 ●Consistent maintenance like vacuuming required to ensure porosity is maintained2 2 http://www.pvpc.org/sites/default/files/files/PVPC-Porous%20Asphalt.pdf 1 https://www.recorder.com/Hawley-Leyden-garner-culvert-replacement-grants-36280921 ●Actively treats drainage of the water and has the potential of removing solids, pathogens, hydrocarbons, and other contaminants2, 3 ●30 year life span compared to traditional 15 year life span of regular asphalt2 Figure 2. Typical permeable pavement schematic3 3 https://www.sciencedirect.com/science/article/pii/S0360132306004227?casa_token=rqxk8Icb_cAAAAAA:DRZ8UZ32Vp04Tbe0dF0goTxMW_dEL QNhKxqC7MLkLsFkwM5mcmaxbcRDhgvIf0HJ3pzq4Y_Zbg Cross Slope ●2% permitted cross-slope grading in Massachusetts4 can facilitate runoff flow off the path to prevent on-path puddling ●Maintenance is required to ensure that the permitted cross slope grade is consistent ●Potential for uncomfortable bike riding Figure 3.Geometric design of varying cross slopes for highway design5 5 https://www.slideshare.net/junaidahmed3192479/geometric-design-of-highway-79804785 4 https://www.mass.gov/files/documents/2018/03/07/e-12-005.pdf Vegetated Swale/Rain Garden ●Reduces the erosion from the runoff by reducing the velocity of the discharge6 ●Removes various particulate pollutants in the discharge as well ●Pretty low cost and low maintenance so as long the vegetation is successfully propagated ●The largest disadvantage of incorporating this method is that individual trees in the region of implementation cannot be salvaged and older trees6 Figure 4.Typical cross-section of an implemented vegetated swale7 7 https://www.stormwaterpa.org/assets/media/BMP_manual/chapter_6/Chapter_6-4-8.pdf 6 https://www.mass.gov/doc/complete-erosion-and-sedimentation-control-guidelines-a-guide-for-planners-designers-and/download 215 Appendix T: Legislative Presentation Feasibility Study of the Northampton State Hospital Shared-Use Path Karena Garcia ✦ Barb Garrison ✦ Ruth Penberthy ✦ Christian Madrigal Smith College Design Clinic 2020-2021 4/30/2021 Current Northampton Bike Path Network The red box surrounds the region where the proposed shared use path and pedestrian bridge would be developed. Note, how the area boxed currently lacks extensives routes and shared use paths. Proposed Path Route Proposed Path Route This site is located near a drainage concern and the Village Hill residential complex. This section of the path would need to be re-graded as the current estimated grade is 6.34%, non compliant with ADA. As a solution, cut and fill is proposed as the re-grading technique for this site. The adjusted path grade and paving would provide better access for all local community members. Proposed Path Route This site is also located near the Village Hill residential complex and the main concern in this region includes non compliant 4.5% ADA grading. A 10 meter segment along this path section has a 6.1% grade. To address this inaccessibility, this region would also be a great candidate for cut and fill. Along with re-grading this region, railing with signs can be placed for aesthetic and safety purposes to engage passersby with rich site history. Proposed Path Route This site is located in close proximity to the historic Ice Pond and is also suggested this site be reassessed. Non compliance with the 4.5% grading threshold is once again the main concern in this region. It is estimated that the current grade is slope is about 4.77%. This non compliant grade can also be adjusted with cut and fill. Similarly to the previous location, this site could further immerse pedestrians with signage to contextualize the space. Additionally, railing could be used as a safety measure for users apparent erosion sites. Proposed Path Route This path segment is several meters from the proposed bridge site. This section would be paved to provide both pedestrian and cyclist access to the path network. Most importantly, signs would be added to further distinguish the proposed shared use path from other local trails. Bridge Superstructure Concept Overview of Process Towards Implementation ➔Attain approval from local authorities and commissions, along with state authorities such as Senator Jo Comerford ➔Submit an application to Public Works at the Northampton Office of Planning and Sustainability ➔Submit permitting applications and fees for the proposed project ➔Pay fees to cover costs associated with protective gear for construction provided by the City of Northampton Photographs by Bailey Ryer Southgate Current Wireworks/Bridge Site Smith College - Landscape Studies Department In a broad-scale design and planning studio co-taught by professors Reid Bertone-Johnson and Gaby Immerman, students were asked to design an intervention at the old “Wireworks” building on Federal Street in Northampton that would increase access to the Mill River and greenway. The following slides include a sample of the various projects completed in the course and serve as examples for the vast opportunity and potential that Wireworks building has. Reimagining the Wireworks building with these proposals alongside the conceptual design for the expanded shared use path and pedestrian bridge give a complete look into how this section of the Mill River could be completely transformed and revitalized. With these designs, we hope to engage with our community and welcome them into the landscape. _______________________ Reimagining Wireworks Credit Author “Skatepark at the Wireworks” Tillie Schneiderman, Smith College ‘22 “Skatepark at the Wireworks” Tillie Schneiderman, Smith College ‘22 “Skatepark at the Wireworks” Tillie Schneiderman, Smith College ‘22 “Wireworks Recreation Center” Madison Biasin, Smith College ‘21 Example of an arcade space layout for along the first floor walls to allow for more than just sports to be played within the Recreation Center. Example of mesh curtain dividers between courts to allow walkways, keep the area open and airy, and to allow for spectators to watch across multiple courts at once. Examples from Forekicks Sports Complex in Marlborough, MA. “Wireworks Recreation Center” Madison Biasin, Smith College ‘21 The upstairs cafe will provide a hangout space for students to gather and get some food while being able to do homework after school together. This will also provide a space for parents to gather if it was used as a tournament space for sports teams. Couches and tables provide plenty of indoor seating for hanging out, homework sessions, and eating. Counter placed just as you walk in to make ordering convenient for those coming in to stay and those ordering to go. Outdoor seating out this way. “Wireworks Recreation Center” Madison Biasin, Smith College ‘21 Outdoor cafe seating for the warmer seasons and the fencing keeps those on the rooftop safe and in the respected area. Picnic tables give a fun outdoor feel, while the couches and roundtables give an additional piece of comfort and togetherness. Big windows and glass doors allow for connection to those indoors, and additional lighting can be added for night use. “Wireworks Recreation Center” Madison Biasin, Smith College ‘21 Rooftop garden gives an educational experience for students to learn how to grow any flower, fruit, or vegetable all while overlooking the Mill River. The access d o o r s open up fro m t h e upstairs edu c a t i o n a l room provi d i n g e a s y access when studying. Proximity and access to the Mill River provides perfect segway into education about the history of the area and the river. “Wireworks Recreation Center” Madison Biasin, Smith College ‘21 “Indoor Farmers Market & Garden” Andrea Gomez, Smith College ‘23 “Indoor Farmers Market & Garden” Andrea Gomez, Smith College ‘23 “Indoor Farmers Market & Garden” Andrea Gomez, Smith College ‘23 “Indoor Farmers Market & Garden” Andrea Gomez, Smith College ‘23 Proposed Project Impacts Increased access to proposed bridge site through the proposed shared use path demonstrates potential to increase local property values Walk, Transit, and Bike Score data are measured on a scale of 0-100 and measure access to walking routes towards destinations, measure transit accessibility, and measure bikeability of a region, respectively [1]. Currently, these values for the Wireworks Site are 24, 19, and 47, respectively, and this project is expected to increase these values by increasing overall access to this region of Northampton [2]. Data like these are used by local economists, realtors, and other property managers to determine property values as they have been linked to increase overall land value [3]. Legitimizing this shared use path as part of the existing path network holds promise for efficient access to Federal Street from other sites like the Smith College Athletic Fields Currently it takes an estimated 19 minutes to reach the Wireworks Site by foot and 5 minutes to bike according to Google Maps. Paving the proposed shared use path and incorporating the bridge is expected to cut down both of these times significantly. Overall destinati on As you can see, the statistics are evidence that all of these things can be realized altogether by… A pedestrian bridge!!! Also what better way to get people on that pedestrian bridge than by paving a super easy and beautiful path that leads you there! References [1] https://www.walkscore.com/professional/research.php [2] https://www.walkscore.com/score/122-federal-st-northampton-ma-01062 [3] https://nacto.org/docs/usdg/walking_the_walk_cortright.pdf Z% NHS Students Ride their bike to School