201211-2 Graves Construction DocumentsFile: 20-22 Graves Ave Print Date: 12/11/20LIST OF DRAWINGS
D1.1
D1.2
D1.3
A1.1
A1.2
A1.3
A7.1
A7.2
FIRST FLOOR DEMOLITION PLAN
SECOND FLOOR DEMOLITION PLAN
THIRD FLOOR DEMOLITION PLAN
FIRST FLOOR PLAN
SECOND FLOOR PLAN
THIRD FLOOR PLAN
KITCHEN INTERIOR ELEVATIONS
KITCHEN PHOTOS
C&H Architects
2 Graves Ave
11 December 2020
Constrution Documents
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20D1.1DW REF
FULL WALL
REMOVE DOOR LEAF AND
REPLACE WITH LIVING ROOM LEAF-
REBUILD FRAME AS NECESSARY
REMOVE SHELF
REMOVE ALL CABINETS
REMOVE WALL BEHIND CABINETS
REMOVE SHELVES
RELOCATE TO
WEST KITCHEN
RELOCATE DOOR
LEAF TO LIVING ROOM
RELOCATE RADIATOR
REMOVE RADIATOR UPREMOVE TILE BACKSPLASH
THROUGHOUT
N
SCALE: 1/4" = 1'-0"1 KITCHEN DEMOLITION PLAN
3 4 6 7 8
1/4" = 1'-0"
1001259
REMOVE
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20D1.2UPDNN
SCALE: 1/4" = 1'-0"1 SECOND FLOOR DEMOLITION PLAN
NO W
O
R
K
T
HI
S FL
O
O
R
3 4 6 7 8
1/4" = 1'-0"
1001259
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20D1.3DNREMOVE DROPPED CEILING
AND ALL PLASTER AND
LATHE AT CEILING
REMOVE DROPPED CEILING
AND ALL PLASTER AND
LATHE AT CEILING
REMOVE DROPPED CEILING
AND ALL PLASTER AND
LATHE AT CEILING
REMOVE DROPPED CEILING
AND ALL PLASTER AND
LATHE AT CEILING
N
SCALE: 1/4" = 1'-0"1 THIRD FLOOR DEMOLITION PLAN
3 4 6 7 8
1/4" = 1'-0"
1001259
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20A1.1REF
DW
3'-9"1
3
2
4 A7.1
NEW RANGE WITH RE-CIRC HOOD
RELOCATE LIVING ROOM DOOR LEAF -
REBUILD FRAME TO FIT, LATCH SIDE
LOCATION TO REMAIN - PAINT DOOR
PROVIDE HEADER ABOVE
RELOCATE RECEPTACLES
SHELVING (UNDERCOUNTER LIGHTS)
PATCH FLOOR AT REMOVED WALL
(2) PENDANT LIGHT FIXTURES ABOVE
NEW CROWN MOLDING IN
DINING AND LIVING ROOMS
RELOCATE KITCHEN
EAST DOOR LEAF
RELOCATE KITCHEN
RADIATOR
PROVIDE STRUCTURAL
SUPPORT FOR HEADER
LIVING ROOM
DINING ROOM
ENTRYKITCHEN UPNEW FRIDGE
N
SCALE: 1/4" = 1'-0"2 FIRST FLOOR PLAN
3 4 6 7 8
1/4" = 1'-0"
1001259
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20A1.2UPBEDROOM 3
BEDROOM 4
STAIR 2BATH 2 DNN
SCALE: 1/4" = 1'-0"1 SECOND FLOOR PLAN
NO W
O
R
K
T
HI
S FL
O
O
R
3 4 6 7 8
1/4" = 1'-0"
1001259
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20A1.3DN(1) LAYER 3/8" SHEETROCK
ON ALL WALLS
(1) LAYER 3/8" SHEETROCK
ON ALL WALLS
(1) LAYER 1/2" SHEETROCK
ON CEILING +
STRAPPING IF REQUIRED
(1) LAYER 1/2" SHEETROCK
ON CEILING +
STRAPPING IF REQUIRED
(1) LAYER 1/2" SHEETROCK
ON CEILING +
STRAPPING IF REQUIRED
(1) LAYER 1/2" SHEETROCK
ON CEILING +
STRAPPING IF REQUIRED
7'-11"CEILING HEIGHT TYP.
BEDROOM 1
BEDROOM 2
BATH 1 STAIR 3
N
SCALE: 1/4" = 1'-0"1 THIRD FLOOR PLAN
3 4 6 7 8
1/4" = 1'-0"
1001259
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20A7.1SOAPSTONE
BACKSPLASH
SHELVING ON BRACKETS
END PANEL
COUNTER OVERHANG SUPPORTED
BY HIDDEN FLAT STEEL BARS
SCALE: 3/8" = 1'-0"1 KITCHEN NORTH
SCALE: 3/8" = 1'-0"2 KITCHEN SOUTH
SCALE: 3/8" = 1'-0"3 KITCHEN WEST
SCALE: 3/8" = 1'-0"4 KITCHEN EAST
C&H ArchitectsFile: 20-22 Graves Ave Print Date: 12/11/20Date:Project No.Drawing Ref.:Scale:20-222 Graves AveRenovation12/11/20A7.2SWAP FRIDGE AND RANGE LOCATIONS
REMOVE WALL
REMOVE WALL
SWAP DOOR PANEL WITH EAST KITCHEN DOOR,
MAINTAIN LATCH SIDE LOCATION TO ALLOW
AREA FOR UPPER CABINETS BEHIND THE DOOR
REMOVE BACKSPLASH TILES
REMOVE BACKSPLASH TILES, UPPER
CABINET AND MICROWAVE