RE: CT ENV 071311 0000 0000000145, Chapter 312, Actions of 2008 Earmark
Northampton Connecticut River Community Boathouse and Connecticut River Greenway
Dear Ms. Hanlon
Please consider this our formal request for an extension of the above referenced project. The project is
making phenomenal progress but will not quite be finished this year.
Status of Project Phases Status
Full design for Phase I of the Connecticut River Greenway riverfront park, which
includes all of the basic site improvements included in the site plan
Complete
Required city permits (Wetlands Order of Conditions, Planning Board Site Plan
Approval, Planning Board Approval Not Required, and DPW Stormwater Permit)
Complete
Required state and federal permits required before ANY work can begin
(MassHistoric Federal Section 106 Review, Mass Endangered Species)
Complete
Required state and federal permits before full site can be developed (Waterways
Chapter 91 license, Water Quality Certificate, Clean Water Act Section 401 fill
permit, HG&E Docks per Federal Energy license)
Applied for, expect
shortly
Determined project below all MEPA review thresholds Complete
Design of final aspects of the project and related permitting—bridge Fall 2013
Design of final aspects of the project, site plan details and reviews Summer‐fall 2013
We would like to request an extension through FY2014 to allow these final aspects of the project to be
completed.
Status of Funding Amount Status
FY2012 Design and permitting $50,000 Reimbursement from Commonwealth PAID
FY2013 Design and permitting $15,000 Expected reimbursement request
FY2014 Design and permitting $35,000 Request for contract extension to FY2014
Thank you for your consideration.
Sincerely,
Wayne Feiden, FAICP
Director of Planning and Sustainability