Loading...
gencond GENERAL CONDITIONS - 1 GENERAL CONDITIONS ARTICLE 1 - CONTRACT DOCUMENTS 1.1 Definitions 1.1.1 The Contract Documents 1.1.1.1 The Contract documents consist of the Owner-Contractor Agreement, Advertisement, Bidding Documents, Contract Forms, Conditions of the Contract, Specifications, Drawings, and all addenda issued prior to and all Modifications issued after execution of the Contract. A Modification is (1) a written amendment to the contract signed by both parties, (2) a Change Order, (3) a written interpretation issued by the Director pursuant to Subparagraph 2.2.8, or (4) a written order for a minor change in the work issued by the Director pursuant to Paragraph 12.4. Change Order Directives issued by the Architect on an AIA 201 are acceptable. 1.1.2 The Contract 1.1.1.1 The Contract Documents form the Contract for Construction. This Contract represents the entire and integrated agreement between the parties hereto and supersedes all prior negotiations, representations, or agreements, either written or oral. The Contract may be amended or modified only by a Modification as defined in Subparagraph 1.1.1. The Contract Documents shall not be construed to create any contractual relationship of any kind between the Director and the Contractor, but the Director shall be entitled to performance of obligations intended for his benefit, and to enforcement thereof. Nothing contained in the Contract Documents shall create any contractual relationship between the Owner or the Director and any Subcontractor or Sub-subcontractor. 1.1.3 The Work 1.1.1.1 The Work comprises the completed construction required by the Contract Documents and includes all labor necessary to produce such construction, and all materials and equipment incorporated or to be incorporated in such construction. 1.1.4 The Project 1.1.1.1 The project is the total construction of which the Work performed under the Contract Documents may be the whole or a part. 1.2 Execution Correlation and Intent 1.1.1 The Contract Documents shall be signed in not less than triplicate by the Owner and Contractor. If either the Owner or the Contractor or both do not sign the Conditions of the Contract, Drawings, Specifications, or any of the other Contract Documents, the Director shall identify such Documents. GENERAL CONDITIONS - 2 1.1.2 By executing the Contract, the Contractor represents that he has visited the site, familiarized himself with the local conditions under which the work is to be performed, and correlated his observations with the requirements of the Contract Documents. 1.1.3 The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work. The Contract Documents are complementary, and what is required by any one shall be as binding as if required by all. Work not covered in the Contract Documents will not be required unless it is consistent therewith and is reasonably inferable therefrom as being necessary to produce the intended results. Words and abbreviations which have well-known technical or trade meanings are used in the Contract Documents in accordance with such recognized meanings. In case of inconsistent requirements in the Contract Documents the requirements for the greater quantity or higher quality shall take precedence and shall be the Contract requirement. 1.1.4 The organization of the specifications into divisions, sections and articles, and the arrangement of Drawings shall not control the Contractor in dividing the work among Subcontractors or in establishing the extent of Work to be performed by any trade. 1.1.5 Where used in conjunction with the Director`s or Engineer`s response to submittals, requests, applications, inquiries, reports and claims by the Contractor, the meaning of the term "approved" will be held to the limitations of the Director`s responsibilities and duties as specified in the General and Supplementary Conditions. In no case will "approval" by the Director be interpreted as an assurance to the Contractor that the requirements of the Contract Documents have been fulfilled. 1.1.6 Where reference is made to standards or trade association publications, it shall mean to refer to the latest edition and revision thereof, if any, in effect on the date of the contract Documents. 1.1.7 Except as otherwise defined in context, the following words, terms, and phrases shall mean as follows: 1.1.1.1 "as shown," "as indicated," "as detailed," or "as noted" shall mean "as shown (indicated, etc.) on drawings or any other diagrammatic or written reference on the Drawings." 1.1.1.2 "Provide" shall mean "furnish and install, complete and ready for intended use." 1.1.1.3 "Directed," "required," "permitted," "ordered," "designed," "prescribed," and similar words shall mean the "direction (requirement, permission, order, designation, or prescription) of the Director." 1.1.1.4 "Approved," "acceptable," "satisfactory," and similar words shall mean "approved by (acceptable or satisfactory to) the Director". 1.1.1.5 "Necessary," "responsible," "proper," "correct," and similar words shall mean "necessary (reasonable, proper, or correct) in the judgment of the Director." 1.1.1.6 Words in the singular shall also mean and include the plural, wherever the context so indicates, and words in the plural shall mean the singular, wherever the context so indicates. GENERAL CONDITIONS - 3 1.3 Ownership and Use of Documents 1.1.1 All Drawings, Specifications and copies thereof furnished by the Director are and shall remain his property. They are to be used only with respect to his project and are not to be used any other project. With the exception of one contract set for each party to the Contract, such documents are to be returned or suitably accounted for to the Director on request at the completion of the Work. Submission or distribution to meet official regulatory requirements or for other purposes in connection with the Project is not to be construed as publication in derogation of the Director's common law copyright or other reserved rights. ARTICLE 2 - DIRECTOR 2.1 Definition 1.1.1 The duly authorized representative of the Owner that is responsible for the satisfactory completion of the project. The Department Head for the Department awarding the contract is the Director unless otherwise noted. 2.2 Administration of the Contract 1.1.1 The Director will provide administration of the Contract as hereinafter described. 1.1.2 The Director will be the Owner's representative during construction and until final payment is due. The Director will advise and consult with the Owner. The Owner's instructions to the Contractor shall be forwarded through the Director. The Director will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written instrument in accordance with Subparagraph 2.2.18. 1.1.3 The Director will visit the site at intervals appropriate to the stage of construction to familiarize himself generally with the progress and quality of the Work and to determine in general if the Work is proceeding in accordance with the Contract Documents. However, the Director will not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work. On the basis of his on-site observations as a Director, he will keep the Owner informed of the progress of the work, and will endeavor to guard the Owner against defects and deficiencies in the Work of the Contractor. The Director will not be responsible for and will not have control or charge of construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, and he will not be responsible for the Contractor's failure to carry out the Work in accordance with the Contract Documents. The Director will not be responsible for or have control or charge over the acts or omissions of the Contractor, Subcontractors, or any of their agents or employees, or any other persons performing any of the Work. 1.1.4 The Director shall at all times have access to the Work wherever it is in preparation and progress. The Contractor shall provide facilities for such access so the Director may perform his functions under the Contract Documents. GENERAL CONDITIONS - 4 1.1.5 Based on the Directors observations and an evaluation of the Contractor's Applications for Payment, the Director will determine the amounts owing to the Contractor and will issue Certificates for Payment in such amounts, as provided in Paragraph 9.4. 1.1.6 The Director will be the interpreter of the requirements of the Contract Documents and the judge of the performance thereunder by both the Owner and Contractor. 1.1.7 The Director will render interpretations necessary for the proper execution or progress of the Work, with reasonable promptness and within thirty (30) days of request for interpretation, in accordance with Subparagraph 3.2.8. Either party to the Contract may make written request to the Director for such interpretations. 1.1.8 Claims, disputes and other matters in question between the Contractor and the Owner relating to the execution or progress of the Work or the interpretation of the Contract Documents shall be referred initially to the Director for decision which will render in writing within thirty (30) days. 1.1.9 All interpretations and decisions of the Director shall be consistent with the intent of and reasonably inferable from the Contract Documents and will be in writing or in the form of drawings. In his capacity as interpreter and judge, he will endeavor to secure faithful performance by both the Owner and the Contractor, will not show partiality to either, and will not be liable for the result of any interpretation or decision rendered in good faith in such capacity. 1.1.10 The Director's decisions in matters relating to artistic effect will be final if consistent with the intent of the Contract Documents. 1.1.11 The Director's decision shall be subject to the Contractor's right of appeal to the Administrator, as set forth in Subparagraph 7.9. 1.1.12 The Director will have authority to reject Work which does not conform to the Contract Documents. Whenever, in his opinion, he considers it necessary or advisable for the implementation of the intent of the Contract Documents, he will have authority to require special inspection or testing of the Work in accordance with Subparagraph 7.7.2 whether or not such Work be then fabricated, installed or completed. However, neither the Director's authority to act under this Subparagraph 2.2.13, nor any decision made by him in good faith either to exercise or not to exercise such authority, shall give rise to any duty or responsibility of the Director to the Contractor, any Subcontractor, any of their agents or employees, or any other person performing any of the Work. 1.1.13 The Director will review and approve or take other appropriate action upon Contractor's submittals such as Shop Drawings, Product Data and Samples, but only for conformance with the design concept of the Work and with the information given in the Contract Documents. Such action shall be taken with reasonable promptness so as to cause no delay. The Director's approval of a specific item shall not indicate approval of an assembly of which the item is a component. 1.1.14 The Director will prepare Change Orders in accordance with Article 12, and will have authority to order minor changes in the Work as provided in Subparagraph 12.4.1. GENERAL CONDITIONS - 5 1.1.15 The Director will conduct inspections to determine the dates of Substantial Completion and final completion, will receive and forward to the Owner for the Owner's review written warranties and related documents required by the Contract and assembled by the Contractor, and will issue a final Certificate for Payment upon compliance with the requirements of Paragraph 9.9. 1.1.16 If the Owner and Director agree, the Director will provide one or more Project Representatives to assist the Director in carrying out his responsibilities at the site. The duties, responsibilities and limitations of authority of any such Project Representative shall be as explained by the Director at a pre-construction meeting. 1.1.17 The duties, responsibilities and limitations of authority of the Director as the Owner's representative during construction as set forth in the Contract Documents will not be modified or extended without written consent of the Owner, the Contractor and the Director. 1.1.18 In case of the termination of the employment of the Director, the Owner shall appoint an Director whose status under the Contract Documents shall be that of the former Director. ARTICLE 3 - OWNER 3.1 Definition 1.1.1 The term "Owner", sometimes also referred to as the "Awarding Authority" or "Authority" means the City of Northampton identified in the Owner-Contractor Agreement, a public body, politic and corporate, organized and existing under the laws of the Commonwealth of Massachusetts. No member of the City shall in any way, directly or indirectly be personally liable under any of the provisions of this Contract. 1.1.2 The term "Administrator" means the Director as defined in Article 2.0. 1.1.3 The City and its authorized representatives and agents shall at all times have access to, and be permitted to observe and review all Work, materials, payrolls, records of personnel, conditions of employment, invoices of materials, and other relevant data and records. 1.1.4 All communications, except for protests or disputes, of the Contractor to the Department and its representatives and agents must be forwarded through the Director. They shall be in writing, addressed to the Department and be considered given if delivered to the office of Director either by hand or if in a sealed, postage prepaid envelope, addressed to the Department c/o the Director: or if delivered prepaid to a telegraph office for transmission to the Director's office. 1.1.5 Items requiring the Administrator's countersignature as per sub-paragraph 3.1.8 shall be valid only with the signature of the Administrator or with the signature of those designated to act in his/her stead. 1.1.6 Items requiring the Administrator's countersignature to be valid shall include but not be limited to the following: GENERAL CONDITIONS - 6 1.1.1.1 Approval, substitutions, and final selection of Sub- Bidders pursuant to M.G.L. Section 44F of Chapter 149. 1.1.1.2 Change Orders, whether or not they affect a change in the Contract Sum or in the Contract Time. 1.1.1.3 Written orders, notices, and approvals given by the Owner pursuant to the Contract Documents or pursuant to any Laws applicable to this Contract. 1.1.1.4 Stop Work order. 1.1.1.5 Certificate of Substantial Completion. 1.1.1.6 Final payment. 1.1.1.7 Termination of Contract. 1.1.7 In any instance needing clarification as to whose signature is required, the Contractor shall seek clarification in writing from the Director. 1.1.8 Work undertaken by the Contractor or a Subcontractor at the Owner's or any other person's order without the Administrator's countersignature prior to the start of such work shall be considered unauthorized work shall not be considered cause for any extra payment on account of the Contract, and the Contractor or Subcontractor shall be responsible for performing, at their own expense any corrective measures required by the Administrator. 3.2 Information and Services Required of the Owner 1.1.1 The Owner shall, at the request of the Contractor, at the time of execution of the Owner- Contractor Agreement, furnish to the Contractor reasonable evidence that he has made financial arrangements to fulfill his obligations under the Contract. Unless such reasonable evidence is furnished, the Contractor is not required to execute the Owner- Contractor Agreement or to commence the Work. 1.1.2 The Owner shall furnish all surveys describing the physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the site. 1.1.3 Except as provided in Subparagraph 4.7.1, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for the construction, use or occupancy of permanent structures or for permanent changes in existing facilities. 1.1.4 Information or services under the Owner's control shall be furnished by the Owner with reasonable promptness to avoid delay in the orderly progress of the Work. 1.1.5 The Owner will furnish to the Contractor, free of charge, all copies of Contract Documents reasonably necessary for the execution of the Work, including one set for record purposes. In addition, the Owner, through the Director, will furnish to the Contractor a reproducible transparency and one black line print of details and clarification drawings issued after the Contract has been awarded. The Contractor, at his GENERAL CONDITIONS - 7 own expense, shall provide and distribute such number of prints of these transparencies as required for his own and his Subcontractors' use. 1.1.6 The Owner shall forward all instructions to the Contractor through the Director. Communications shall be in writing and be considered given if delivered at the office of the Contractor; or if in a sealed, postage-prepaid envelope addressed to the Contractor's office and deposited in the United States mail; or if delivered prepaid to a telegraph office for transmission to the Contractor's office. 1.1.7 The foregoing are in addition to other duties and responsibilities of the Owner enumerated herein and especially those in respect to Work by Owner or by Separate Contractors, Payments and Completion, and insurance in Articles 6,9 and 11 respectively. 1.1.8 Pursuant to Chapter 30 of the General Laws, the following Section 39 P is included herein in its entirety. 1.1.9 Every contract subject to Section 39 M of this Chapter or Section 44 A of Chapter 149 which requires the City, any official, its Director or engineer to make a decision on interpretation of the specifications, approval of equipment, material or any other approval, or progress of the work, shall require that the decision be made promptly and, in any event, no later than thirty days after the written submission for decision: but if such decision requires extended investigation and study, the awarding authority, the official, Director or engineer shall, within thirty days after the receipt of the submission, give the party making the submission written notice of the reasons why the decision cannot be made within the thirty-day period and the date by which the decision will be made. 3.3 Owner’s Right to Stop the Work 1.1.1 If the Contractor fails to correct defective Work as required by Paragraph 13.2 or persistently fails to carry out the Work in accordance with the Contract Documents, the Owner, by a written order signed personally or by an agent specifically so empowered by the Owner in writing, may order the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of the Owner to stop the Work shall not give rise to any duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Subparagraph 6.1.3. 1.1.2 Pursuant to Chapter 30 of the General Laws, the following provisions (a) and (b) of Section 39 O are included herein in their entirety: 1.1.1.1 The Awarding Authority may order the General Contractor in writing to suspend, delay, or interrupt all or any part of the Work for such period of time as it may determine to be appropriate for the convenience of the Awarding Authority; provided, however, that if there is a suspension, delay or interruption for fifteen days or more due to a failure of the Awarding Authority to act within the time specified in this contract, the Awarding Authority shall make an adjustment in the Contract price for any increase in the cost of performance of this Contract, but shall not include any profit to the General Contractor on such increase; and provided further, that the Awarding Authority shall not make any adjustment in the Contract Price under this provision for any suspension, delays, interruption or GENERAL CONDITIONS - 8 failure to act to the extent that such is due to any cause for which this Contract provides for an equitable adjustment of the Contract Price under any other provisions. 1.1.1.2 The general contractor must submit the amount of a claim under provision (a) to the awarding authority in writing as soon as practicable after the end of the suspension, delay, interruption or failure to act and, in any event, not later than the date of final payment under this contract and, except for costs due to a suspension order, the awarding authority shall not approve any costs in the claim incurred more than twenty days before the general contractor notified the awarding authority in writing of the act or failure to act involved in the claim. 3.4 Owner’s Right to Carry Out the Work 1.1.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within seven days after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, after seven days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy he may have, make good such deficiencies. In such case an appropriate Change Order shall be issued deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation for the Director's additional services made necessary by such default, neglect or failure. Such action by the Owner and the amount charged to the Contractor are both subject to the prior approval of the Director. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner. ARTICLE 4 - CONTRACTOR 4.1 Definition 1.1.1 The "Contractor" sometimes referred to as the "General Contractor", is the person or entity identified as such in the Owner-Contractor Agreement and is referred to throughout the Contract Documents as if singular in number and masculine in gender. The term Contractor means the Contractor or his authorized representative. 4.2 Review of Contract Documents 1.1.1 The Contractor shall carefully study and compare the Contract Documents and shall at once report to the Director any error, inconsistency or omission he may discover. The Contractor shall not be liable to the Owner or the Director for any damage resulting from any such errors, inconsistencies or omissions in the Contract Documents. The Contractor shall perform no portion of the Work at any time without Contract Documents or, where required, approved Shop Drawings, Product Data or Samples for such portion of the Work. 1.1.2 The Contractor shall compare all grades, lines, levels, and dimensions shown on the Drawings with actual site conditions, and before commencing work he shall promptly report to, and await for the reply from the Director, any inconsistencies he may discover. The Director shall reply within five working days. GENERAL CONDITIONS - 9 4.3 Supervision and Construction Procedures 1.1.1 The Contractor shall supervise and direct the Work, using his best skill and attention. To this end, he shall employ a superintendent who shall be on the site all times work is in progress. He shall be solely responsible for all construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract. 1.1.2 The Contractor shall be responsible to the Owner for the acts and omissions of his employees, Subcontractors and their agents and employees, and other persons performing any of the Work under a contract with the Contractor. 1.1.3 The Contractor shall not be relieved from his obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of the Director in his administration of the Contract, or by inspections, tests or approvals required or performed under Paragraph 7.7 by persons other than the Contractor. 1.1.4 The Contractor, at his own expense, shall do all engineering required for establishing grades, lines, levels, dimensions, layouts, and reference points for all trades; shall be responsible for maintaining bench marks and other survey marks; and shall replace as directed any bench marks or survey marks which have been disturbed or destroyed. 1.1.5 Unless otherwise required under the Contract Documents, or directed in writing by the Director, all Work shall be done during regular working hours. However, if the Contractor desires to carry on the Work outside of regular working hours or Saturdays, Sundays, or Massachusetts holidays he shall allow ample time to enable satisfactory arrangements to be made for inspecting work in progress and shall bear all cost with respect thereto. The Owner shall bill the Contractor directly for such costs. 1.1.6 Work done outside of regular working hours without the consent or knowledge of the Director shall be subject to additional inspection and testing directed by the Director. The cost of this testing shall be paid by the Contractor whether the Work is found to be acceptable or not. 4.4 Labor and Materials 1.1.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. 1.1.2 The Contractor shall at all times enforce strict discipline and good order among his employees and shall not employ on the Work any unfit person or anyone not skilled in the task assigned to him. 1.1.3 Except where otherwise specifically provided to the contrary, the words "or equal" are hereby inserted immediately following the naming or describing of each article, assembly, system, or any component part thereof, in any of the Contract Documents. GENERAL CONDITIONS - 10 1.1.4 In accordance with Section 39M of Chapter 30 of the General Laws "an item shall be considered equal to the item so named or described if (1) it is at least equal in quality, durability, appearance, strength, and design, (2) it will perform at least equally the function imposed by the general design for the public work being contracted for or the material being purchased, and (3) it conforms substantially, even with deviations, to the detailed requirements for the item in the said specifications". 1.1.5 However, the Contractor and the Subcontractors are required to submit to the Director for consideration as to its equality, a written notice containing the name and full particulars pertaining to any items other than the specific or specifics named or described in the Contract Documents. Such submittal shall in no event be made later than 120 calendar days prior to the incorporation of the item into the Work, except in any case in which (1) the period of time specified in the Contract Documents for Substantial completion of the Work is less than 120 calendar days form the time of execution of the Contract. The aforesaid written notice shall be submitted to the Director immediately following the execution of the Contract. 1.1.6 Upon receipt of such written notice, the Director shall investigate whether the item in question shall be considered equal to the item named or described in the Contract Documents. Upon conclusion of the investigation, the Director shall, in writing, promptly advise the Contractor that the item in question is, or is not, considered the equal of the item named or described as aforesaid, and that said item may, or may not, be furnished on the Work accordingly. Such notice must have the concurrence of the Department to be valid. 1.1.7 In no case may an item be furnished on the Work other than the item named or described, unless the Director shall consider the item equal to the item so named or described, as provided by law. 1.1.8 The equality of items offered as "equal" to the items named or described shall be proved to the satisfaction of the Director at the expense of the Contractor or Subcontractor submitting the substitution. 1.1.9 The Contractor or Subcontractor, as the case may be, shall assume full responsibility for the prior performance of any item submitted as "equal" to the specific or specifics named and assume the costs of any changes in his own Work or in the Work of other trades which may be due to such substitution. 4.5 Warranty 1.1.1 The Contractor warrants to the Owner and the Director that all materials and equipment furnished under this Contract will be new unless otherwise specified, and that all Work will be of good quality, free from faults and defects and in conformance with the Contract Documents. All Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective. If required by the Director, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. This warranty is not limited by the provisions of Paragraph 13.2. 4.6 Taxes GENERAL CONDITIONS - 11 1.1.1 The Contractor shall pay all sales, consumer, use and other similar taxes for the Work or portions thereof provided by the Contractor which are legally enacted at the time bids are received, whether or not yet effective. 1.1.2 The Owner is exempt from payment of the Commonwealth of Massachusetts Sales Tax. 4.7 Permits, Fees and Notices 1.1.1 Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for the building permit and for all other permits and governmental fees, licenses and inspections necessary for the proper execution and completion of the Work, which are customarily secured after execution of the Contract and which are legally required at the time the bids are received. 1.1.2 The Contractor shall give all notices and comply with all laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the performance of the Work. 1.1.3 It is not the responsibility of the Contractor to make certain that the Contract Documents are in accordance with applicable laws, statutes, building codes and regulations. If the Contractor observes that any of the Contract Documents are at variance therewith in any respect, he shall promptly notify the Director in writing, and any necessary changes shall be accomplished by appropriate Modification. 1.1.4 If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Director, he shall assume full responsibility therefor and shall bear all costs attributable thereto. 4.8 Allowances (intentionally deleted) 4.9 Superintendent 1.1.1 The Contractor shall employ a competent superintendent and necessary assistants who shall be in attendance at the Project site during the progress of the Work. The superintendent shall represent the Contractor and all communications given to the superintendent shall be as binding as if given to the Contractor. Important communications shall be confirmed in writing. Other communications shall be so confirmed on written request in each case. 4.10 Progress Schedule 1.1.1 The Contractor, immediately after being awarded the Contract, shall prepare and submit for the Owner's and Director's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work. 1.1.2 The progress schedule shall show by bar graph or critical path method, as acceptable to the Director, in sufficient detail, clearly the interrelationships between the various construction operations and the percentage of completion and the dollar value on the first day of each month for the Work in each Section of the Specifications and also for the GENERAL CONDITIONS - 12 entire work. The graph shall also show the date that the Work in each Section commenced. 1.1.3 A copy of the progress schedule shall be kept in the Contractor's field office and be brought up to date each month to show the actual progress of the Work. 4.11 Documents and Samples at the Site 1.1.1 The Contractor shall maintain at the site for the Owner one record copy of all Drawings, Specifications, Addenda, Change Orders and other Modifications, in good order and marked currently to record all changes made during construction, and approved Shop Drawings, Product Data and Samples. These shall be available to the Director and shall be delivered to him for the Owner upon completion of the Work. 4.12 Shop Drawings, Product Data and Samples 1.1.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared for the Work by the Contractor or any Subcontractor, manufacturer, supplier or Distributor to illustrate some portion of the Work. 1.1.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the contractor to illustrate a material, product or system for some portion of the Work. 1.1.3 Samples are physical examples which illustrate materials, equipment or workmanship and establish standards by which the Work will be judged. 1.1.4 The Contractor shall review, approve and submit, with reasonable promptness and in such sequence as to cause no delay in the Work or in the work of the Owner or any separate contractor, all Shop Drawings, Product Data and Samples required by the Contract Documents. 1.1.5 By approving and submitting Shop Drawings, Product Data and Samples, the Contractor represents that he has determined and verified all materials, field measurements and field construction criteria related thereto, or will do so, and that he has checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents. 1.1.6 The Contractor shall not be relieved of responsibility for any deviation from the requirements of the Contract Documents by the Director's approval of Shop Drawings, Product Data or Samples under Subparagraph 2.2.14 unless the Contractor has specifically informed the Director in writing of such deviation at the time of submission and the Director has given written approval to the specific deviation. The Contractor shall not be relieved from responsibility for errors or omissions in the Shop Drawings, Product Data or Samples by the Director's approval thereof. 1.1.7 The Contractor shall direct specific attention, in writing or on resubmitted Shop Drawings, Product Data or Samples, to revisions other than those requested by the Director on previous submittals. GENERAL CONDITIONS - 13 1.1.8 No portion of the Work requiring submission of a Shop Drawing, Product Data or Sample shall be commenced until the submittal has been approved by the Director as provided in Subparagraph 2.2.14. All such portions of the Work shall be in accordance with approved submittals. 4.13 Use of Site 1.1.1 The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits and the Contract Documents and shall not unreasonably encumber the site with any materials or equipment. 4.14 Cutting and Patching of Work 1.1.1 The Contractor shall be responsible for all cutting, fitting or patching that may be required to complete the Work or to make its several parts fit together properly. 1.1.2 The Contractor shall not damage or endanger any portion of the Work or the work of the Owner or any separate contractors by cutting, patching or otherwise altering any work, or by excavation. The Contractor shall not cut or otherwise alter the work of the Owner or any separate contractor except with the written consent of the Owner and of such separate contractor. The Contractor shall not unreasonably withhold from the Owner or any separate contractor his consent to cutting or otherwise altering the Work. 4.15 Cleaning Up 1.1.1 The Contractor at all times shall keep the premises free from accumulation of waste materials or rubbish caused by his operations. At the completion of the Work he shall remove all his waste materials and rubbish from and about the Project as well as all his tools, construction equipment, machinery and surplus materials. 1.1.2 If the Contractor fails to clean up at the completion of the Work, the Owner may do so as provided in Paragraph 3.4 and the cost thereof shall be charged to the Contractor. 4.16 Indemnification 1.1.1 To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner and the Director and their agents and employees from and against all claims, damages, losses and expenses, including but not limited to attorneys' fees, arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense (1) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting therefrom, and (2) is caused in whole or in part by any negligent act or omission of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or otherwise reduce any other right or obligation of indemnity which would otherwise exist as to any party or person described in this Paragraph 4.18. 1.1.2 In any and all claims against the Owner or the Director or any of their agents or employees by any employee of the Contractor, any Subcontractor, anyone directly or GENERAL CONDITIONS - 14 indirectly employed by any of them or anyone for whose acts any of them may be liable, the indemnification obligation under this Paragraph 4.18 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or or for the Contractor or any Subcontractor under worker's or workmen's compensation acts, disability benefit acts or other employee benefit acts. 1.1.3 The obligations of the Contractor under this Paragraph 4.18 shall not extend to the liability of the Director, his agents or employees arising out of (1) the preparation or approval of maps, drawings, opinions, reports, surveys, change orders, designs or specifications, or (2) the giving of or the failure to give directions or instructions by the Director, his agents or employees provided such giving or failure to give is the primary cause of the injury or damage. ARTICLE 5 - SUBCONTRACTORS 5.1 Definition 1.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform any of the Work at the site. The term Subcontractor is referred to throughout the Contract Documents as if singular in number and masculine in gender and means a Subcontractor or his authorized representative. The term Subcontractor does not include any separate contractor or his subcontractors. 1.1.2 A Sub-subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to perform any of the Work at the site. The term Sub-subcontractor is referred to throughout the Contract Documents as if singular in number and masculine in gender and means a Sub-subcontractor or an authorized representative thereof. 5.2 Award of Subcontracts and Other Contracts for Portions of the Work 1.1.1 Unless otherwise required by the Contract Documents or the Bidding Documents, the Contractor, as soon as practicable after the award of the Contract, shall furnish to the Owner and the Director in writing the names of the persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for each of the principal portions of the Work. The Director will promptly reply to the Contractor in writing stating whether or not the Owner or the Director, after due investigation, has reasonable objection to any such proposed person or entity. Failure of the Owner or Director to reply promptly shall constitute notice of no reasonable objection. 1.1.2 The Contractor shall not contract with any such proposed person or entity to whom the Owner or the Director has made reasonable objection under the provisions of Subparagraph 5.2.1. The Contractor shall not be required to contract with anyone to whom he has a reasonable objection. 1.1.3 If the Owner or the Director has reasonable objection to any such proposed person or entity, the Contractor shall submit a substitute to whom the Owner or the Director has no reasonable objection, and the Contract Sum shall be increased or decreased by the difference in cost occasioned by such substitution and an appropriate Change Order shall be issued; however, no increase in the Contract Sum shall be allowed for any such GENERAL CONDITIONS - 15 substitution unless the Contractor has acted promptly and responsively in submitting names as required by Subparagraph 5.2.1. 1.1.4 The Contractor shall make no substitution for any Subcontractor, person or entity previously selected if the Owner or Director makes reasonable objection to such substitution. 1.1.5 Paragraphs 5.2.1. through 5.2.4 apply to any sub-trade included in Item 1 of the Form for General Bid. 1.1.6 The award of subcontracts for any sub-trade included in Item 2 of the Form for General Bid shall be in accordance with Chapter 149, Sections 44A to 44H, M.G.L. 5.3 Subcontractural Relations 1.1.1 By an appropriate agreement, written where legally required for validity, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by the terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities which the Contractor, by these Documents, assumes toward the Owner and the Director. Said agreement shall preserve and protect the rights of the Owner and the Director under the Contract Documents with respect to the Work to be performed by the Subcontractor so that the subcontracting thereof will not prejudice such rights, and shall allow to the Subcontractor, unless specifically provided otherwise in the Contractor-Subcontractor agreement, the benefit of all rights, remedies and redress against the Contractor that the Contractor, by these Documents, has against the Owner. Where appropriate, the Contractor shall require each Subcontractor to enter into similar agreements with his Subsubcontractors. The Contractor shall make available to each proposed Subcontractor, prior to the execution of the Subcontract, copies of the Contract Documents to which the Subcontractor will be bound by this Paragraph 5.3, and identify to the Subcontractor any terms and conditions of the proposed Subcontract which may be at variance with the Contract Documents. Each Subcontractor shall similarly make copies of such documents available to his Sub-subcontractors. 1.1.2 Paragraph 5.3.1 applies to Subcontractors for sub-trades included in Item 1 of the Form for General Bid. 1.1.3 The Contractor and each Subcontractor for a sub-trade listed in Item 2 of the form for General Bid shall execute a Subcontract in accordance with M.G.L. Chapter 149, Section 44F. ARTICLE 6 - INTENTIONALLY DELETED ARTICLE 7 - MISCELLANEOUS PROVISIONS 7.1 Governing Law 1.1.1 The Contract shall be governed by the law of the place where the Project is located. 7.2 Successors and Assigns GENERAL CONDITIONS - 16 1.1.1 The Owner and the Contractor each binds himself, his partners, successors, assigns and legal representatives to the other party hereto and to the partners, successors, assigns and legal representatives of such other party in respect to all covenants, agreements and obligations contained in the Contract Documents. Neither party to the Contract shall assign the Contract or sublet it as a whole without the written consent of the other, nor shall the Contractor assign any moneys due or to become due to him hereunder, without the previous written consent of the Owner. 7.3 Written Notice 1.1.1 Written notice shall be deemed to have been duly served if delivered in person to the individual or member of the firm or entity or to an officer of the corporation for whom it was intended, or if delivered at or sent by registered or certified mail to the last business address known to him who gives the notice. 7.4 Claims for Damages 1.1.1 Should either party to the Contract suffer injury or damage to person or property because of any act or omission of the other party or of any of his employees, agents or others for whose acts he is legally liable, claim shall be made in writing to such other party within a reasonable time after the first observance of such injury or damage. 7.5 Performance Bond and Labor and Material Payment Bond 1.1.1 The Owner shall have the right to require the Contractor to furnish bonds covering the faithful performance of the Contract and the payment of all obligations arising thereunder if and as required in the Bidding Documents or in the Contract Documents. 7.6 Rights and Remedies 1.1.1 The duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law. 1.1.2 No action or failure to act by the Owner, Director or Contractor shall constitute a waiver of any right or duty afforded any of them under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach thereunder, except as may be specifically agreed in writing. 7.7 Tests 1.1.1 If the Contract Documents, laws, ordinances, rules, regulations or orders of any public authority having jurisdiction require any portion of the Work to be inspected, tested, or approved, the Contractor shall give the Director timely notice of its readiness so the Director may observe such inspection, testing or approval. The Contractor shall bear all costs of such inspections, tests or approvals conducted by public authorities. Unless otherwise provided, the Owner shall bear all costs of other inspections, tests or approvals. 1.1.2 If the Director determines that any Work requires special inspection, testing or approval which Subparagraph 7.7.1 does not include, he will, upon written authorization from the Owner, instruct the Contractor to order such special inspection, testing or approval, and GENERAL CONDITIONS - 17 the Contractor shall give notice as provided in Subparagraph 7.7.1. If such special inspection or testing reveals a failure of the Work to comply with the requirements of the Contract Documents, the Contractor shall bear all costs thereof, including compensation for the Director's additional services made necessary by such failure; otherwise the Owner shall bear such costs, and an appropriate Change Order shall be issued. 1.1.3 Required certificates of inspection, testing or approval shall be secured by the Contractor and promptly delivered by him to the Director. 1.1.4 If the Director is to observe the inspections, tests or approvals required by the Contract Documents, he will do so promptly and, where practicable, at the source of supply. 7.8 Interest 1.1.1 Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due at such rate as the parties may agree upon in writing or, in the absence thereof, at the legal rate prevailing at the place of the Project. 7.9 Disputes 1.1.1 Claims, disputes, and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof, except as provided in Subparagraph 2.2.11 with respect to the Director's decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payment as provided by Subparagraph 9.9.4 and 9.9.5. shall be decided by the Director subject to the right of appeal to the City Solicitor. If the Director fails to render a decision within thirty calendar days after receiving written notice of claim, either party may request a written decision from the City Solicitor. 1.1.2 Appeal of a Director's decision must be made directly to the City Solicitor by certified mail (copy to the Director and Owner) within twenty-one calendar days after the date on which the party making the appeal receives the Director's written decision. Failure to appeal within this period will result in the Director's decision becoming final and binding upon the Owner and the Contractor. 1.1.3 Appeal procedures shall be in conformance with M.G.L. Chapter 30, Section 39Q which provides as follows: 1.1.1.1 Dispute regarding changes in and interpretations of the terms or scope of the Contract and denials of or failures to act upon claims for payment for extra work or materials shall be resolved according to the following procedures, which shall constitute the exclusive method for resolving such disputes. Written notice of the matter in dispute shall be submitted promptly by the claimant to the chief executive official of the state agency which awarded the contract or his/her designee. No person or business entity having a contract with a state agency shall delay, suspend, or curtail performance under that contract as a result of any dispute subject to this section. Any disputed order, decision, or action by the agency or its authorized representative shall be fully performed or complied with pending resolution of the dispute. GENERAL CONDITIONS - 18 1.1.1.2 Within thirty days of submission of the dispute to the chief executive official of the state agency or his/her designee, s/he shall issue a written decision stating the reasons therefor, and shall notify the parties of their right of appeal under this section. If the official or his/her designee is unable to issue a decision within thirty days, s/he shall notify the parties to the dispute in writing of the reasons why a decision cannot be issued within thirty days and of the date by which the decision shall issue. Failure to issue a decision within the thirty-day period of within the additional time period specified in such written notice shall be deemed to constitute a denial of the claim and shall authorize resort to the appeal procedure described below. The decision of the chief executive official or his/her designee shall be final and conclusive unless an appeal is taken as provided below. 1.1.1.3 Within twenty-one calendar days of the receipt of a written decision or of the failure to issue a decision as stated in the preceding subparagraph, any aggrieved party may file a notice of claim for an adjudicatory hearing with the division of hearing officers or if the amount in controversy exceeds ten thousand dollars in lieu of appealing the decision of the chief executive official, the aggrieved party may file an action directly in a court of competent jurisdiction and shall serve copies thereof upon all other parties in the form and manner prescribed by the rules governing the conduct of adjudicatory proceedings of the division of hearing officers. The appeal shall be referred to a hearing officer experienced in construction law and shall be prosecuted in accordance with the formal rules of procedure for the conduct of adjudicatory hearings of the division of hearing officers, except as provided below. The hearing officer shall issue a final decision as expeditiously as possible, but in no event more than one hundred and twenty calendar days after conclusion of the adjudicatory hearings, unless the decision is delayed by a request for extension of time for filing post-hearing briefs or other submissions assented to by all parties. Whenever, because an extension of time has been granted, the hearing officer is unable to issue a decision within one hundred and twenty days, s/he shall notify all parties of the reasons for the delay and the date when the decision will issue. Failure to issue a decision with in the one hundred and twenty-day period or within the additional period specified in such written notice shall give the petitioner the right to pursue any legal remedies available to him/her without further delay. 1.1.1.4 When the amount in dispute is less then ten thousand dollars, a contractor who is party to the dispute may elect to submit the appeal to a hearing officer experienced in construction law for expedited hearing in accordance with the informal rules of practice and procedure of the division of hearing officers. An expedited hearing under this subparagraph shall be available at the sole option of the contractor. The hearing officer shall issue a decision no later than sixty days following the conclusion of any hearing conducted pursuant to this subparagraph. The hearing officer's decision shall be final and conclusive, and shall not be set aside except in cases of fraud. 1.1.4 The Contractor shall proceed with the disputed Work as directed by the Director. Notice must be given to the Project Representative by the Contractor's superintendent every day that disputed Work is to be performed. Accurate records of the nature and extent of the disputed Work and of the time spent and equipment used on the disputed Work shall be maintained by the superintendent and verified daily by the Project Representative. GENERAL CONDITIONS - 19 7.10 Record Keeping and Management Controls 1.1.1 The Contractor shall make and retain for at least six years after final payment records which reflect the transactions and dispositions of the firm in accordance with the requirements of M.G.L. Chapter 30, Section 39R (b). 1.1.2 These records and the subcontractor's records pertaining to this Contract shall be available for examination by the Owner, Department, Division of Capital Planning and Operations, and Inspector General for six years after final payment. 1.1.3 Prior to execution of the Contract the Contractor shall submit a statement of management on internal accounting controls to the Owner in conformance with M.G.L. Chapter 30, Section 39R (c). The system of controls must reasonably assure that: 1.1.1.1 transactions are executed in accordance with management's general and specific authorization: 1.1.1.2 the transactions are recorded as necessary to permit preparation of financial statements in conformity with generally accepted accounting principles and to maintain accountability for asset: 1.1.1.3 access to assets is permitted only in accordance with management's authorization: and 1.1.1.4 the recorded accountability for assets is compared with existing assets at reasonable intervals and appropriate action was taken with respect to any difference. 1.1.4 The statement of management on internal accounting controls must have been reviewed by an independent certified public accountant (CPA), and that CPA shall file a statement with the Owner in conformance with the requirements of M.G.L. Chapter 30, Section 39R (c). The CPA's statements must: 1.1.1.1 state that the internal accounting controls statement was examined: 1.1.1.2 express an opinion as to whether management's statement of internal accounting controls is consistent with management's evaluation of the system of internal accounting controls; and 1.1.1.3 express an opinion as to whether the statement is reasonable with respect to transactions and assets of material amounts in the context of the firm's overall financial picture. 1.1.5 The Contractor shall submit to the Owner annually during the term of the Contract a financial statement prepared by an independent CPA. This statement shall be based on an audit of the firm's records in accordance with the requirements of M.G.L. Chapter 30, Section 39R (a) (5). The financial statement shall be accompanied by an accountant's report in accordance with the requirements of M.G.L. Chapter 30, Section 39R (a) (6) stating: 1.1.1.1 the scope of the audit made by the CPA and GENERAL CONDITIONS - 20 1.1.1.2 the CPA's opinion of the financial statement as a whole and exceptions and qualifications to that opinion or 1.1.1.3 The CPA's statement, with reasons, that an overall opinion cannot be expressed. 1.1.1.4 The accountant's report shall include a signed statement by the responsible corporate officer attesting that all material facts were disclosed to the CPA and that the financial statement is a true and complete statement of financial condition. 1.1.1.5 Changes in the method of record keeping which materially affect any of the statements required by Subparagraph 7.10.3 through 7.10.5 shall be reported to the Owner. State the change, the reason for it, and the date of the change. Include a statement from the CPA approving or commenting on the change in conformance with M.G.L. Chapter 30, Section 39R (b) (3). 1.1.1.6 Subparagraph 7.10.3 through 7.10.6 shall apply only to filed subcontractors and general contractors whose contracts exceed $100,000. ARTICLE 8 - TIME 8.1 Definitions 1.1.1 Unless otherwise provided, the Contract Time is the period of time allotted in the Contract Documents for Substantial Completion of the Work as defined in Subparagraph 8.1.3., including authorized adjustments thereto. The Contract Time for this project is sixty (60) calendar days. 1.1.2 The date of commencement of the Work is the date established in a notice to proceed. If there is no notice to proceed, it shall be the date of the Owner-Contractor Agreement or such other date as may be established therein. 1.1.3 The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Director when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended. 1.1.4 The term day as used in the Contract Documents shall mean calendar day unless otherwise specifically designated. 8.2 Progress and Completion 1.1.1 All time limits stated in the Contract Documents are of the essence of the Contract. 1.1.2 The Contractor shall begin the Work on the date of commencement as defined in Subparagraph 8.1.2. He shall carry the Work forward expeditiously with adequate forces and shall achieve Substantial Completion within the Contract Time. 8.3 Delays and Extension of Time GENERAL CONDITIONS - 21 1.1.1 If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the Owner or the Director, or by any employee of either, or by any separate contractor employed by the Owner, or by changes ordered in the Work, or by labor disputes, fire unusual delay in transportation, adverse weather conditions not reasonably anticipatable, unavoidable casualties, or any causes beyond the Contractor's control, or by delay authorized by the Owner pending appeal to and decision by the Administrator", or by any other cause which the Director determines may justify the delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Director may determine. 1.1.2 Any claim for extension of time shall be made in writing to the Director not more than twenty days after the commencement of the delay; otherwise it shall be waived. In the case of a continuing delay only one claim is necessary. The Contractor shall provide an estimate of the probable effect of such delay on the progress of the Work. 1.1.3 If no agreement is made stating the dates upon which interpretations as provided in Subparagraph 2.2.8 shall be furnished, then no claim for delay shall be allowed on account of failure to furnish such interpretations until fifteen days after written request is made for them, and not then unless such claim is reasonable. 1.1.4 This Paragraph 8.3 does not exclude the recovery of damages for delay by either party under other provisions of the Contract Documents. 1.1.5 The Contractor and the Surety of the Contractor's performance bond shall be jointly and severally liable for, and shall pay to the Owner the expenses for inspection of Work performed after the time stipulated in the Owner-Contractor Agreement for Substantial Completion. Such inspection costs shall include fees paid to the Director as extra services at the rate stipulated in the Contract for Directorural Services between the Owner and the Director, the costs of the Project Representative at the current salary rate and any other direct expenses due to inspection. In no case, however, shall the total amount of inspection costs exceed an aggregate total computed at the rate of two hundred dollars per day. The Owner may retain from monies otherwise due the Contractor whatever sums accrue to the Owner pursuant to this provision. The Contractor shall not be liable for inspection costs for delay in performance as provided hereunder for any period for which an extension of the Contract Time has been granted pursuant to the provisions of Subparagraph 8.3.1. ARTICLE 9 - PAYMENTS AND COMPLETION 9.1 Contract Sum 1.1.1 The Contract Sum is stated in the Owner-Contract Agreement and, including authorized adjustments thereto, is the total amount payable by the Owner to the Contractor for the performance of the Work under the Contract Documents. 9.2 Schedule of Values 1.1.1 Before the first Application for Payment, the Contractor shall submit to the Director a schedule of values allocated to the various portions of the Work, prepared in such form and supported by such data to substantiate its accuracy as the Director may require. This GENERAL CONDITIONS - 22 schedule, unless objected to by the Director, shall be used only as a basis for the Contractor's Applications for Payment. 1.1.2 The Schedule of Values shall contain a separate item for each Section of these Specifications broken down in such form as the Director may require. Each item in the schedule of values shall include its proper share of overhead and profit. 9.3 Application for Payment 1.1.1 Once each month, on a date established at the beginning of the Work, the Contractor shall deliver to the Director by hand or by registered or certified mail with return receipt an itemized Application for Payment, supported by such data substantiating the Contractor's right to payment as the Director may require, and reflecting retainage as provided in Paragraph 9.5 as supplemented. Such Application for Payment shall be submitted on a form supplied by the Director. The form shall show separately: 1.1.1.1 The value of Labor and materials incorporated in the Work. 1.1.1.2 The value, kind, and quantity of each item of material or equipment not incorporated in the Work but delivered and suitably stored at some other location agreed upon in writing. 1.1.1.3 The value, kind, and quantity of each item of material or equipment not incorporated in the Work but suitably stored at some other location agreed upon in writing. 1.1.1.4 All Change Orders approved up to the date of the Application for Payment. 1.1.2 In no event may materials or equipment be deemed delivered and suitably stored at the site (or at some other location agreed upon in writing), unless the following requirements are met: 1.1.1.1 The materials or equipment are ready for an actually scheduled for prompt use, as so-called stockpiling is expressly forbidden, except as otherwise specified or permitted by the Director. 1.1.1.2 The materials or equipment meet the requirements of the Contract Documents and required submittals have been approved by the Director. 1.1.1.3 The Contractor can and will adequately protect the materials or equipment until they are incorporated in the Work. 1.1.1.4 The Contractor will pay storage charges and related expenses if materials or equipment are stored at some other location agreed upon in writing. 9.4 Certificates for Payment 1.1.1 The Director will, within seven days after the receipts of the Contractor's Application for Payment, either issue a Certificate for Payment to the Owner, with a copy to the Contractor, for such amount as the Director determines is properly due, or notify the GENERAL CONDITIONS - 23 Contractor in writing his reasons for withholding a Certificate as provided in Subparagraph 9.6.1. 1.1.2 The issuance of a Certificate for Payment will constitute a representation by the Director to the Owner, based on his observations at the site as provided in Sub-paragraph 2.2.3 and the data comprising the Application for Payment, that the Work has progressed to the point indicated; that, to the best of his knowledge, information and belief, the quality of the Work is in accordance with the Contract Documents (subject to an evaluation of the Work for conformance with the Contract Documents upon Substantial Completion, to the results of any subsequent tests required by or performed under the Contract Documents, to minor deviations from the Contract Documents, correctable prior to completion, and to any specific qualifications stated in his Certificate); and that the contractor is entitled to payment in the amount certified. However, by issuing a Certificate for Payment, the Director shall not thereby; be deemed to represent that he has made exhaustive or continuous on-site inspections to check the quality or quantity of the Work or that he has reviewed the construction means, methods, techniques, sequences or procedures, or that he has made any examination to ascertain how or for what purpose the Contractor has used the moneys previously paid on account of the Contract Sum. 9.5 Progress Payments 1.1.1 After the Director has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents. 1.1.2 The Contractor shall promptly pay each Subcontractor, upon receipt of payment from the Owner, out of the amount paid to the Contractor on account of such Subcontractor's Work, the amount to which said Subcontractor is entitled, reflecting the percentage actually retained, if any, from payments to the Contractor on account of such Subcontractor's Work. The Contractor shall, by an appropriate agreement with each Subcontractor, require each Subcontractor to make payments to his Sub-subcontractors in similar manner. 1.1.3 The Director may, on request and at his discretion, furnish to any Subcontractor, if practicable, information regarding the percentages of completion or the amounts applied for by the Contractor and the action taken thereon by the Director on account of Work done by such Subcontractor. 1.1.4 Neither the Owner nor the Director shall have any obligation to pay or to see to the payment of any moneys to any Subcontractor except as may otherwise be required by law. 1.1.5 No Certificate for a progress payment, nor any progress payment, nor any partial or entire use or occupancy of the Project by the Owner, shall constitute an acceptance of any Work not in accordance with the Contract Documents. 1.1.6 After the Director has issued a Certificate for Payment the Owner shall make payment to the Contractor in accordance with Section 39K of Chapter 30 of the General Laws which provides as follows: 1.1.7 Within 15 days after receipt from the Contractor, at the place designated by the awarding authority if such a place is so designated, of a periodic estimate requesting payment of the GENERAL CONDITIONS - 24 amount due for the preceding month, the City will make a periodic payment to the Contractor for the Work performed during the preceding month and for the materials not incorporated in the Work but delivered and suitably stored at the site (or at some location agreed upon in writing) to which the Contractor has title or to which a subcontractor has title and has authorized the Contractor to transfer title to the awarding Authority, less (1) a retention based on its estimate of the fair value of its claims against the Contractor and less (2) a retention for direct payments to Subcontractors based on demands for same in accordance with the provisions of Section 39 F. and less (3) a retention not exceeding ten percent (10%) of the approved amount of the periodic payment. After the receipt of a periodic estimate requesting final payment and within 65 days after (a) the Contractor fully completes the Work or substantially completes the work so that the value of the work remaining to be done is, in the estimate of the City, less than one percent (1%) of the original Contract price, or (b) the Contractor substantially completes the Work and the City takes possession for occupancy, whichever occurs first, the City shall pay the Contractor the entire balance due on the Contract less, (1) a retention based on its estimate of the fair value of its claims against the Contractor and of the cost of completing the incomplete and unsatisfactory items of Work less (2) a retention for direct payments to Subcontractors based on demands for same in accordance with the provisions of Section 39 F, or based on the record of payments by the Contractor to the Subcontractors under this Contract if such record of payment indicates that the Contractor has not paid Subcontractors as provided in Section 39 F. If the City fails to make payment as herein provided, there shall be added to each such payment daily interest at the rate of three percentage points above the rediscount rate than charged by the Federal Reserve Bank of Boston commencing on the first day after said payment is due and continuing until the payment is delivered or mailed to the Contractor; provided, that no interest shall be due, in any event, on the amount due on a periodic estimate for final payment until fifteen days after receipt of such a periodic estimate form the Contractor, at the place designated by the City if such a place is so designated. The Contractor agrees to pay to each Subcontractor a portion of any such interest paid in accordance with the amount due each Subcontractor. 1.1.8 The Contractor shall make payments to filed Subcontractors and to other Subcontractors as defined in following Subparagraph 9.5.8 in accordance with Section 39F of Chapter 30 of the General Laws which provides as follows: 1.1.1.1 Forthwith after the Contractor receives payment on account of a periodic estimate, the Contractor shall pay to each Subcontractor the amount paid for the labor performed and the materials furnished by the Subcontractor, less any amount specified in any court proceedings barring such payment and also less any amount claimed due from the Subcontractor by the Contractor. 1.1.1.2 Not later than the 65th day after each Subcontractor substantially completes his Work in accordance with the plans and specifications, the entire balance due under the subcontract less amounts retained by the City as the estimated costs of completing the incomplete and unsatisfactory items of Work, shall be due the Subcontractor; and the City shall pay that amount to the Contractor. The Contractor shall forthwith pay to the Subcontractor the full amount received from the City less any amount specified in any court proceedings barring such payment and also less any amount claimed due from the Subcontractor by the Contractor. GENERAL CONDITIONS - 25 1.1.1.3 Each payment made by the City to the Contractor pursuant to subparagraphs (a) and (b) of this paragraph for the labor performed and the materials furnished by a subcontractor shall be made to the Contractor for the account of that Subcontractor; and the City shall take reasonable steps to compel the Contractor to make each such payment to each such Subcontractor. If the City has received a demand for direct payment from a Subcontractor for any amount which has already been included in a payment to the Contractor or which is to be included in a payment to the Contractor for payment to the Subcontractor as provided in subparagraphs (a) and (b), the City shall act upon the demand as provided in this section. 1.1.1.4 If, within 70 days after the Subcontractor has substantially completed the Subcontract Work, the Subcontractor has not received from the Contractor the balance due under the Subcontract including any amount due for extra labor and materials furnished to the Contractor, less any amount retained by the City as the estimated costs of completing the incomplete and unsatisfactory items of Work, the Subcontractor may demand direct payment of that balance from the City. The demand shall be by a sworn statement delivered to or sent by certified mail to the City, and a copy be valid even if delivered or mailed prior to the seventieth day after the Subcontractor has substantially completed the Subcontract Work. Within ten days after the Subcontractor has delivered or so mailed a copy to the Contractor, the Contractor may reply to the demand. The reply shall be by a sworn statement delivered to or sent by certified mail to the City and a copy shall be delivered to or sent by certified mail to the Subcontractor at the same time. The reply shall contain a detailed breakdown of the balance due under the Subcontract including any amount due for extra labor and materials furnished to the Contractor and of the amount due for extra labor and materials furnished to the Contractor and of the amount due for each claim made by the Contractor against the Subcontractor. 1.1.1.5 Within 15 days after receipt of the demand by the City, but in no event prior to the 70th day after substantial completion of the Subcontract Work, the City shall make direct payment to the Subcontractor of the balance due under the Subcontract including any amount due for extra labor and materials furnished to the Contractor, less any amount (i) retained by the City as the estimated cost of completing the incomplete or unsatisfactory items of Work, (ii) specified in any court proceedings barring such payment, or (iii) disputed by the Contractor in the sworn reply; provided, that the City shall not deduct from a direct payment any amount as provided in part (iii) if the reply is not sworn to, or for which the sworn reply does not contain the detailed breakdown required by subparagraph (d). The City shall make further direct payments to the Subcontractor forthwith after the removal of the basis for deductions from direct payments made as provided in part (i) and (ii) of this subparagraph. 1.1.1.6 The City shall forthwith deposit the amount deducted from a direct payment as provided in part (iii) of subparagraph (e) in an interest-bearing joint account in the names of the Contractor and the Subcontractor in a bank in Massachusetts selected by the City or agreed upon by the contractor and the Subcontractor and shall notify the Contractor and the Subcontractor of the date of the deposit and GENERAL CONDITIONS - 26 the bank receiving the deposit. The bank shall pay the amount in the account, including accrued interest, as provided in an agreement between the Contractor and the Subcontractor or as determined by decree of a court of competent jurisdiction. 1.1.1.7 All direct payments and all deductions from demands for direct payments deposited in an interest-bearing account or accounts in a bank pursuant to subparagraph (f) shall be made out of amounts payable to the general Contractor at the time of receipt of a demand for direct payment from a Subcontractor and out of amounts which later become payable to the Contractor and in order of receipt of such demands from Subcontractors. All direct payments shall discharge the obligation of the City to the Contractor to the extent of such payment. 1.1.1.8 The City shall deduct from payments to the Contractor amounts which, together with the deposits in interest-bearing accounts pursuant to subparagraph (f), are sufficient to satisfy all unpaid balances of demands for direct payment received from Subcontractors. All such amounts shall be earmarked for such direct payments, and the Subcontractors shall have a right to such deductions prior to any claims against such amounts by creditors of the Contractor. 1.1.1.9 If the Subcontractor does not receive payment as provided in subparagraph (a) or if the Contractor does not submit a periodic estimate for the value of the labor and materials performed or furnished by the Subcontractor and the Subcontractor does not receive payment for same when due less the deductions provided for in subparagraph (a), the Subcontractor may demand direct payment by following the procedure in subparagraph (d) and the Contractor may file a sworn reply as provided in that same subparagraph. A demand made after the first day of the month following that for which the Subcontractor performed or furnished the labor and materials for which the Subcontractor seeks payment shall be valid even if delivered or mailed prior to the time payment was due on a periodic estimate from the Contractor. Thereafter the City shall proceed as provided in subparagraph (e), (f), (g), and (h). 1.1.9 Pursuant to section 39F of Chapter 30 of the Laws, the term "Subcontractor" as used in preceding Subparagraph 9.5.7 shall mean a person who files a sub-bid and receives a Subcontract as a result of that filed sub-bid or who is approved by the City in writing as a person performing labor or both performing labor and furnishing materials pursuant to a contract with the Contractor. 9.6 Payments Withheld 1.1.1 The Director may decline to certify payment and may withhold his Certificate in whole or in part, to the extent necessary reasonably to protect the Owner, if in his opinion he is unable to make representations to the Owner as provided in Subparagraph 9.4.2. If the Director is unable to make representations to the Owner as provided in Subparagraph 9.4.2 and to certify payment in the amount of the Application, he will notify the Contractor as provided in Subparagraph 9.4.1. If the Contractor and the Director cannot agree on a revised amount, the Director will promptly issue a Certificate for Payment for the amount for which he is able to make such representations to the Owner. Subject to the provisions of Subparagraph 9.6.3 herein below, the Director may also decline to GENERAL CONDITIONS - 27 certify payment or, because of subsequently discovered evidence or subsequent observations, he may nullify the whole or any part of any Certificate for Payment previously issued to such extent as may be necessary in his opinion to protect the Owner from loss because of: 1.1.1.1 defective Work not remedied 1.1.1.2 third party claims filed or reasonable evidence indicating probable filing of such claims, 1.1.1.3 failure of the contractor to make payments properly to Subcontractors or for labor, materials or equipment, reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum, damage to the Owner or another contractor, reasonable evidence that the Work will not be completed within the Contract Time, or persistent failure to carry out the Work in accordance with the Contract Documents. 1.1.2 When the above grounds in Subparagraph 9.6.1 are removed, payment shall be made for amounts withheld because of them. 1.1.3 The City may make changes in any periodic estimate submitted by the Contractor in accordance with Section 39K of Chapter 30 of the General Laws, and the payment due on said periodic estimate shall be computed in accordance with the changes so made. The provisions of said Section 39K shall govern payments pursuant to periodic estimates on which the City has made changes. The Director shall mark the date of receipt on the estimate. 9.7 Failure of Payment 1.1.1 If the Owner fails to make payments as set forth in Section 39K of Chapter 30, the Contractor shall be compensated as set forth in said Section. 9.8 Substantial Completion 1.1.1 When the Contractor considers that the Work, or a designated portion thereof which is acceptable to the Owner, is substantially complete as defined in Subparagraph 8.1.3, the Contractor shall prepare for submission to the Director a list of items to be completed or corrected. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. When the Director on the basis of an inspection determines that the Work or designated portion therefor is substantially complete, he will then prepare a Certificate of Substantial Completion which shall establish the Date of Substantial Completion, shall state the responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, and insurance, and shall fix the time within which the Contractor shall complete the items listed therein. Warranties required by the Contract Documents shall commence on the Date of Substantial Completion of the Work or designated portion thereof unless otherwise provided in the Certificate of Substantial Completion. The Certificate of Substantial Completion shall be submitted to the Owner and the Contractor for their written acceptance of the responsibilities assigned to them in such Certificate. GENERAL CONDITIONS - 28 1.1.2 Upon substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Director, the Owner shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents. 9.9 Final Completion and Final Payment 1.1.1 Upon receipt of written notice that the work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Director will promptly make such inspection and, when he finds the Work acceptable under the Contract Documents and the Contract fully performed, he will promptly issue a final Certificate for Payment stating that to the best of his knowledge, information and belief, and on the basis of his observations and inspections, the Work has been completed in accordance with the terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor, and noted in said final Certificate, is due and payable. The Director's final Certificate for Payment will constitute a further representation that the conditions precedent to the Contractor's being entitled to final payment as set forth in Subparagraph 9.9.2 have been fulfilled. Final payment shall be made in accordance with section 39K of Chapter 30, quoted in Subparagraph 9.5.6 hereinabove, which Section takes precedence over any contradictory provisions of Paragraph 9.9. 1.1.2 Neither the final payment nor the remaining retained percentage shall become due until the Contractor submits to the Director (1) an affidavit that all payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the Owner or his property might in any way be responsible, have been paid or otherwise satisfied, (2) consent of surety, if any, to final payment and (3), if required by the Owner, other data establishing payment or satisfaction of all such obligations, such as receipts, releases and waivers of liens arising out of the Contract, to the extent and in such form as may be designated by the Owner. If any Subcontractor refuses to furnish a release or waiver required by the Owner, the Contractor may furnish a bond satisfactory to the Owner to indemnify him against any such lien. If any such lien remains unsatisfied after all payments are made, the Contractor shall refund to the Owner all moneys that the latter may be compelled to pay in discharging such lien, including all costs and reasonable attorneys' fees. The affidavit and consent of surety shall be submitted on AIA forms G706 "Contractor's Affidavit of Payment of Debts and Claims" and G707 "Consent of Surety Company to Final Payment". 1.1.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by the issuance of Change Orders affecting final completion, and the Director so confirms, the Owner shall, upon application by the Contractor and certification by the Director, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipulated in the Contract Documents, and if bonds have been furnished as provided in Paragraph 7.5, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Director prior to certification of such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims. GENERAL CONDITIONS - 29 1.1.4 The making of final payment shall constitute a waiver of all claims by the Owner except those arising from: 1.1.1.1 unsettled liens, 1.1.1.2 faulty or defective Work appearing after Substantial Completion, 1.1.1.3 failure of the Work to comply with the requirements of the Contract Documents, or terms of any special warranties required by the Contract Documents. 1.1.5 The acceptance of final payment shall constitute a waiver of all claims by the Contractor except those previously made in writing and identified by the Contractor as unsettled at the time of the final Application for Payment. ARTICLE 10 - PROTECTION OF PERSONS AND PROPERTY 10.1 Safety Precautions and Programs 1.1.1 The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. 10.2 Safety of Persons and Property 1.1.1 The Contractor shall take all reasonable precautions for the safety of, and shall provide all reasonable protection to prevent damage, injury or loss to: 1.1.1.1 all employees on the Work and all other persons who may be affected thereby; 1.1.1.2 all the Work and all materials and equipment to be incorporated therein, whether in storage on or off the site, under the care, custody or control of the Contractor or any of his Subcontractors or Sub-subcontractors; and other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction. 1.1.2 The Contractor shall give all notices and comply with all applicable laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the safety of persons or property or their protection from damage, injury or loss. 1.1.3 The Contractor shall erect and maintain, as required by existing conditions and progress of the Work, all reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent utilities. 1.1.4 When the use or storage of explosives or other hazardous materials or equipment is necessary for the execution of the Work, the Contractor shall exercise the utmost care and shall carry on such activities under the supervision of properly qualified personnel. 1.1.5 The Contractor shall promptly remedy all damage or loss (other than damage or loss insured under Paragraph 11.3) to any property referred to in Clauses 10.2.1.2 and 10.2.1.3 caused in whole or in part by the Contractor, any Subcontractor, any Sub- GENERAL CONDITIONS - 30 subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable and for which the Contractor is responsible under Clauses 10.2.1.2 and 10.2.1.3 except damage or loss attributable to the acts or omissions of the Owner or Director or anyone directly or indirectly employed by either of them, or by anyone for whose acts either of them may be liable, and not attributable to the fault or negligence of the Contractor. The foregoing obligations of the Contractor are in addition to his obligations under Paragraph 4.18. 1.1.6 The Contractor shall designate a responsible member of his organization at the site whose duty shall be the prevention of accidents. This person shall be the Contractor's superintendent unless otherwise designated by the Contractor in writing to the Owner and the Director. 1.1.7 The Contractor shall not load or permit any part of the Work to be loaded so as to endanger its safety. 10.3 Emergencies 1.1.1 In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work. ARTICLE 11 - INSURANCE 11.1 Contractor’s Liability Insurance 1.1.1 The Contractor shall purchase and maintain such insurance as will protect him from claims set forth below which may arise out of or result from the Contractor's operations under the Contract, whether such operations be by himself or by any Subcontractor or by anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable: 1.1.1.1 claims under workers' or workmen's compensation, disability benefit and other similar employee benefit acts; 1.1.1.2 claims for damages because of bodily injury, occupational sickness or disease, or death of his employees; 1.1.1.3 claims for damages because of bodily injury, sickness or disease, or death of any person other than his employees; 1.1.1.4 claims for damages insured by usual personal injury liability coverage which are sustained (1) by any person as a result of an offense directly or indirectly related to the employment of such person by the Contractor, or (2) by any other person; 1.1.1.5 claims for damages, other than to the Work itself, because of injury to or destruction of tangible property, including loss of use resulting therefrom; and claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance or use of any motor vehicle. GENERAL CONDITIONS - 31 1.1.2 The insurance required by Subparagraph 11.1.1 shall be taken out in a company or companies authorized to do such business in the Commonwealth of Massachusetts and satisfactory to the Owner and Department and shall be written for not less than any limits of liability specified herein below, or required by law, whichever is greater. 1.1.1.1 Workmen’s Compensation and other benefits as required under Chapter 152 of the Laws, as amended, and Section 34A of Chapter 149 of the General Laws. 1.1.1.2 Employer's liability with a limit of at least $300,000 each accident. 1.1.1.3 Comprehensive Public Liability including Contractor's Liability as applicable to the Contractor's obligations under Paragraph 4.18; Elevators (if any on the Work): Completed Operations and Products Liability: all on the occurrence basis with Personal Injury coverage and Broad Form Property Damage. Remove the XCU exclusions relating to Explosion, Collapse, and Underground Property Damage. Completed Operations Liability shall be kept in force for at least two years after the date of final completion. 1.1.1.4 Personal Injury and Accidental Death - General Liability a. Each person/aggregate $100,000/$1,000,000 1.1.1.5 Property Damage - General Liability a. Each Occurrence/aggregate $100,000/$500,000 1.1.1.6 Personal Injury - Automobile Liability a. Each person/aggregate $100,000/$500,000 1.1.1.7 Property Damage - Automobile Liability a. Each Occurrence/aggregate $50,000/$100,000 1.1.3 The insurance required by Subparagraph 11.1.1 shall include contractual liability insurance applicable to the Contractor's obligations under Paragraph 4.18. 1.1.4 Certificates of Insurance acceptable to the Owner shall be submitted to the Owner simultaneously with the execution of the Contract. Certificates shall indicate that Contractual Liability coverage is in force, as well as deletions of the XCU exclusions. These Certificates shall contain a provision that the insurance company will notify the Owner by registered mail at least 30 days in advance of any cancellation, change, or expiration of the policies. 11.2 Owner’s Liability Insurance 1.1.1 The Owner shall be named as an additional insured on the Contractor's Liability Insurance Policies. 11.3 Property Insurance GENERAL CONDITIONS - 32 1.1.1 The Contractor shall purchase and maintain Builders Risk insurance upon the entire Work at the site to the full insurable value thereof. This insurance shall be taken out in a company or companies against which the Owner has no reasonable objection and shall include the interests of the Owner, the Contractor, Subcontractors and Sub Subcontractors and shall insure against the perils of fire and extended coverage and shall include "all risks" insurance for physical loss or damage including, without duplication, theft, vandalism and malicious mischief. The insurance shall also cover portions of the Work stored off the site or in transit which are included in an Application for Payment under Subparagraph 9.3.2. If this insurance is written with stipulated amounts deductible, the Owner shall not be responsible for any difference between the payments made by the insurance carrier and the claim. 1.1.2 Delete Boiler AND Machinery coverage. 1.1.3 Any loss insured under Subparagraph 11.3.1 is to be adjusted with the Owner and made payable to the Owner as trustee for the insureds, as their interests may appear, subject to the requirements of any applicable mortgagee clause and of Subparagraph 11.3.8. The Contractor shall pay each Subcontractor a just share of any insurance moneys received by the Contractor, and by appropriate agreement, written where legally required for validity, shall required each Subcontractor to make payments to his Sub-subcontractors in similar manner. 1.1.4 The Contractor shall file the original and one certified copy of all policies with the Owner before exposure to loss may occur. If the Owner is damaged by the failure of the Contractor to maintain such insurance and to so notify the Owner, then the Contractor shall bear all reasonable costs properly attributable thereto. 1.1.5 (intentionally deleted) 1.1.6 The Owner and Contractor waive all rights against (1) each other and the Subcontractors, Sub-subcontractors, agents and employees each of the other, and (2) the Director and separate contractors, if any, and their subcontractors, sub-subcontractors, agents and employees, for damages caused by fire or other perils to the extent covered by insurance obtained pursuant to this Paragraph 11.3 or any other property insurance applicable to the Work, except such rights as they may have to the proceeds of such insurance held by the Owner as trustee. The foregoing waiver afforded the Director, his agents and employees shall not extend to the liability imposed by Subparagraph 4.18.3. The Owner or the Contractor, as appropriate, shall require of the Director, separate contractors, Subcontractors and Sub-subcontractors by appropriate agreements, written where legally required for validity, similar waivers each in favor of all other parties enumerated in this Subparagraph 11.3.6. 1.1.7 If required in writing by any party in interest, the Owner as trustee shall, upon the occurrence of an insured loss, give bond for the proper performance of his duties. He shall deposit in a separate account any money so received, and he shall distribute it in accordance with such agreement as the parties in interest may reach, or in accordance with an award by arbitration in which case the procedure shall be as provided in Paragraph 7.9. If after such loss no other special agreement is made, replacement of damaged work shall be covered by an appropriate Change Order. GENERAL CONDITIONS - 33 1.1.8 The Owner as trustee shall have power to adjust and settle any loss with the insurers unless one the of parties in interest shall object in writing within five days after the occurrence of loss to the Owner's exercise of this power, and if such objection be made, arbitrators shall be chosen as provided in Paragraph 7.9. The Owner as trustee shall, in that case, make settlement with the insurers in accordance with the directions of such arbitrators. If distribution of the insurance proceeds by arbitration is required, the arbitrators will direct such distribution. 1.1.9 If the Owner finds it necessary to occupy or use a portion or portions of the Work prior to Substantial Completion thereof, such occupancy or use shall not commence prior to a time mutually agreed to by the Owner and Contractor and to which the insurance company or companies providing the property insurance have consented by endorsement to the policy or policies. This insurance shall not be cancelled or lapsed on account of such partial occupancy or use. Consent of the Contractor and of the insurance company or companies to such occupancy or use shall not be unreasonably withheld. 11.4 Loss of Use Insurance 1.1.1 The Owner, at his option, may purchase and maintain such insurance as will insure him against loss of use of his property due to fire or other hazards, however caused. The Owner waives all rights of action against the Contractor for loss of use of his property, including consequential losses due to fire or other hazards however caused, to the extent covered by insurance under this Paragraph 11.4. ARTICLE 12 - CHANGES IN THE WORK 12.1 Change Orders 1.1.1 A Change Order is a written order to the Contractor signed by the Owner and the Director, issued after execution of the Contract, authorizing a change in the Work or an adjustment in the Contract Sum or the Contract Time. The Contract Sum and the Contract Time may be changed only by Change Order. A Change Order signed by the Contractor indicates his agreement therewith, including the adjustment in the Contract Sum or the Contract Time. All Change Orders must be countersigned by the Administrator in accordance with Paragraph 3.1 as supplemented. 1.1.2 The Owner, without invalidating the Contract, may order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and the Contract Time being adjusted accordingly. All such changes in the Work shall be authorized by Change Order, and shall be performed under the applicable conditions of the Contract Documents. 1.1.3 The cost or credit to the Owner resulting from a change in the Work shall be determined in one or more of the following ways: 1.1.1.1 by mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation; 1.1.1.2 by unit prices stated in the Contract Documents or subsequently agreed upon; GENERAL CONDITIONS - 34 1.1.1.3 by cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee, or 1.1.1.4 by the method provided in Subparagraph 12.1.4. 1.1.4 If none of the methods set forth in Clauses 12.1.3.1, 12.1.3.2 or 12.1.3.3 is agreed upon, the Contractor, provided he receives a written order signed by the Owner, shall promptly proceed with the Work involved. The cost of such Work shall then be determined by the Director on the basis of the reasonable expenditures and savings of those performing the Work attributable to the change, including, in the case of an increase in the Contract Sum, a reasonable allowance for overhead and profit. In such case, and also under Clauses 12.1.3.3 and 12.1.3.4 above, the Contractor shall keep and present, in such form as the Director may prescribe, an itemized accounting together with appropriate supporting data for inclusion in a Change Order. 1.1.1.1 Cost of materials entering permanently in the Work, including cost of delivery: 1.1.1.2 Cost of labor at the rates found elsewhere in this document including foremen: 1.1.1.3 Rental value at fair market rental rates of equipment and machinery employed directly on the Work (hand tools and minor equipment excluded): 1.1.1.4 A percentage amount of 25% of item 2 above to cover Workman's Compensation, F.I.C.A., and unemployment contributions. 1.1.5 For Work performed by the Contractor with his own forces there shall be added a percentage fee for the Contractor equal to 15% of the total of Items 1,2,3 hereinabove. 1.1.6 For Work performed by a filed or non-filed Subcontractor there shall be added a percentage fee for the Subcontractor equal to 15% of the total of Items 1,2,3 hereinabove. To this total amount of the Subcontractor's price there may be added an additional percentage fee of 10% for the Contractor. 1.1.7 The percentage fee shall be compensation to cover the cost of supervision, layout, overhead, bonds, profit, and all other expenses which are not included in the cost of the Work as defined above. 1.1.8 Pending final determination of cost to the Owner, payments on account shall be made on the Director's Certificate for Payment. The amount of credit to be allowed by the Contractor to the Owner for any deletion or change which results in a net decrease in the Contract Sum will be the amount of the actual net cost as confirmed by the Director. When both additions and credits covering related Work or substitutions are involved in any one change, the allowance for overhead and profit shall be figured on the basis of the net increase, if any, with respect to that change. 1.1.9 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if the quantities originally contemplated are so changed in a proposed Change Order that application of the agreed unit prices to the quantities of Work proposed will cause substantial inequity to the Owner or the Contractor, the applicable unit prices shall be equitably adjusted. GENERAL CONDITIONS - 35 12.2 Concealed Conditions 1.1.1 Pursuant to Section 39N of Chapter 30 of the Laws, the following shall apply to differing concealed conditions: 1.1.2 If, during the progress of the Work, the Contractor or the City discovers that the actual subsurface or latent physical conditions encountered at the site differ substantially or materially from those shown on the plans or indicated in the Contract Documents either the Contractor or the City may request an equitable adjustment in the Contract Price applying to Work affected by the differing site conditions. A request for such an adjustment shall be in writing and shall be delivered by the party making such claim to the other party as soon as possible after such conditions are discovered. Upon receipt of such a claim from the Contractor, or upon its own initiative, the City shall make an investigation of such physical conditions, and, if they differ substantially or materially from those indicated in the Contract Documents or from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents and are of such a nature as to cause an increase or decrease in the cost of the Work, the contracting Authority shall make an equitable adjustment in the Contract Price and the Contract shall be modified in writing accordingly. 12.3 Claims for Additional Cost 1.1.1 If the Contractor wishes to make a claim for an increase in the Contract Sum, he shall give the Director written notice thereof within twenty days after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work, except in an emergency endangering life or property in which case the Contractor shall proceed in accordance with Paragraph 10.3. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined by the Director. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order. 1.1.2 If the Contractor claims that additional cost is involved because of, but not limited to, (1) any written interpretation pursuant to Subparagraph 2.2.8, (2) any order by the Owner to stop the Work pursuant to Paragraph 3.3 where the Contractor was not at fault, (3) any written order for a minor change in the Work issued pursuant to Paragraph 12.4, or (4) failure of payment by the Owner pursuant to Paragraph 9.7, the Contractor shall make such claims as provided in Subparagraph 12.3.1, except as set forth in Subparagraph 3.3.2 of the Supplementary Conditions. 12.4 Minor Changes in the Work 1.1.1 The Director will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time and not consistent with the intent of the Contract Documents. Such changes shall be effected by written order, and shall be binding on the Owner and the Contractor. The Contractor shall carry out such written orders promptly. ARTICLE 13 - UNCOVERING AND CORRECTION OF WORK 13.1 Uncovering of Work GENERAL CONDITIONS - 36 1.1.1 If any portion of the Work should be covered contrary to the request of the Director or to requirements specifically expressed in the Contract Documents, it must, if required in writing by the Director, be uncovered for his observation and shall be replaced at the Contractor's expense. 1.1.2 If any other portion of the Work has been covered which the Director has not specifically requested to observe prior to being covered, the Director may request to see such Work and it shall be uncovered by the Contractor. If such Work be found in accordance with the Contract Documents, the cost of uncovering and replacement shall, by appropriate Change Order, be charged to the Owner. If such Work be found not in accordance with the Contract Documents, the Contractor shall pay such costs unless it be found that this condition was caused by the Owner or a separate contractor as provided in Article 6, in which event the Owner shall be responsible for the payment of such costs. 13.2 Correction of Work 1.1.1 The Contractor shall promptly correct all Work rejected by the Director as defective or as failing to conform to the Contract Documents whether observed before or after Substantial Completion and whether or not fabricated, installed or completed. The Contractor shall bear all costs of correcting such rejected Work, including compensation for the Director's additional services made necessary thereby. 1.1.2 If, within one year after the Date of Substantial Completion of the Work or designated portion thereof or within one year after acceptance by the Owner of designated equipment or within such longer period of time as may be prescribed by law or by the terms of any applicable special warranty required by the Contract Documents, any of the Work is found to be defective or not in accordance with the Contract Documents, the Contractor shall correct it promptly after receipt of a written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. This obligation shall survive termination of the Contract. The Owner shall give such notice promptly after discovery of the condition. 1.1.3 The Contractor shall remove from the site all portions of the Work which are defective or non-conforming and which have not been corrected under Subparagraphs 4.5.1, 13.2.1 and 13.2.2, unless removal is waived by the Owner. 1.1.4 If the Contractor fails to correct defective or nonconforming Work as provided in Subparagraphs 4.5.1, 13.2.1 and 13.2.2, the Owner may correct it in accordance with Paragraph 3.4. 1.1.5 If the Contractor does not proceed with the correction of such defective or non- conforming Work within a reasonable time fixed by written notice from the Director, the Owner may remove it and may store the materials or equipment at the expense of the Contractor. If the Contractor does not pay the cost of such removal and storage within ten days thereafter, the Owner may upon ten additional days' written notice sell such Work at auction or at private sale and shall account for the net proceeds thereof, after deducting all the costs that should have been borne by the Contractor, including compensation for the Director's additional services made necessary thereby. If such proceeds of sale do not cover all costs which the Contractor should have borne, the difference shall be charged to the Contractor and an appropriate Change Order shall be GENERAL CONDITIONS - 37 issued. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner. 1.1.6 The Contractor shall bear the cost of making good all work of the Owner or separate contractors destroyed or damaged by such correction or removal. 1.1.7 Nothing contained in this Paragraph 13.2 shall be construed to establish a period of limitation with respect to any other obligation which the Contractor might have under the Contract Documents, including Paragraph 4.5 hereof. The establishment of the time period of one year after the Date of Substantial Completion or such longer period of time as may be prescribed by law or by the terms of any warranty required by the Contract Documents relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which his obligation to comply with the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability with respect to his obligations other than specifically to correct the Work. 13.3 Acceptance of Defective or Non-Conforming Work 1.1.1 If the Owner prefers to accept defective or nonconforming Work, he may do so instead of requiring its removal and correction, in which case a Change Order will be issued to reflect a reduction in the Contract Sum where appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made. 13.4 Special Guarantees and Warranties 1.1.1 All guarantees and warranties required in the various Sections of the Specifications which originate with a Subcontractor or manufacturer must be delivered to the Director before final payment to the Contractor may be made for the amount of that subtrade or for the phase of Work to which the guarantee or warranty relates. 1.1.2 The failure to deliver a required guarantee or warranty shall be held to constitute a failure of the Subcontractor to fully complete his Work in accordance with the Contract Documents. 1.1.3 The Contractor's obligation to correct Work as set forth in Paragraph 13.2 is in addition to, and not in substitution of, such guarantees or warranties as may be required in the various Sections of the Specifications. ARTICLE 14 - TERMINATION OF THE CONTRACT 14.1 Termination by the Contractor 1.1.1 If the Work is stopped for a period of 30 days under any order of any court or other public Authority having jurisdiction or as a result of an act of government, such as a declaration of a national emergency make materials unavailable, through no act or fault of the Contractor or a Subcontractor, or their agents or employees, or any other person performing any of the Work under a contract with the Contractor, then the Contractor may, upon seven additional days' written notice to the Owner and Director, terminate the Contract and recover from the Owner payment for all Work executed and for any proven GENERAL CONDITIONS - 38 loss sustained upon any materials, equipment, tools, construction equipment and machinery, including reasonable profit and damages. 14.2 Termination by the Owner 1.1.1 If the Contractor is adjudged a bankrupt, or if he makes a general assignment for the benefit of his creditors, or if a receiver is appointed on account of his insolvency, or if he persistently or repeatedly refuses or fails, except in cases for which extension of time is provided, to supply enough properly skilled workmen or proper materials, or if he fails to make prompt payment to Subcontractors or for materials or labor, or persistently disregards laws, ordinances, rules, regulations or orders of any public authority having jurisdiction, or otherwise is guilty of a substantial violation of a provision of the Contract Documents, then the Owner, upon certification by the Director that sufficient cause exists to justify such action may, without prejudice to any right or remedy and after giving the Contractor and his surety, if any, seven days' written notice, terminate the employment of the Contractor and take possession of the site and of all materials, equipment, tools, construction equipment and machinery thereon owned by the Contractor and may finish the Work by whatever method he may deem expedient. In such case the Contractor shall not be entitled to receive any further payment until the Work is finished. 1.1.2 If the unpaid balance of the Contract Sum exceeds the costs of finishing the Work, including compensation for the Director's additional services made necessary thereby, such excess shall be paid to the Contractor. If such costs exceed the unpaid balance, the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or to the Owner, as the case may be, shall be certified by the Director, upon application, in the manner provided in Paragraph 9.4, and this obligation for payment shall survive the termination of the Contract. SUPPLEMENTARY CONDITIONS PART 2 - ADDITIONAL CONDITIONS Articles set forth under Part 2 of this section are additional conditions not covered in the A.I.A. General Conditions. ARTICLE 15 - LABOR REQUIREMENTS OF THE COMMONWEALTH OF MASSACHUSETTS 15.1 Labor Laws 1.1.1 The Contractor and the Subcontractors shall conform to applicable provisions of M.G.L. Chapter 149, as amended. 1.1.2 No laborer, workman, mechanic, foreman or inspector working in the employment of the Contractor, Subcontractor or other person doing or contracting to do the whole or part of the Work contemplated by this Contract, shall be required or permitted to work any more than eight hours in any one day, or more than 48 hours in any one week, or more than six days in any one week, except in cases of emergency. GENERAL CONDITIONS - 39 1.1.3 Every employee on the Work shall lodge, board, and trade where and with whom he elects, and the Contractor and any Subcontractor shall not directly or indirectly require, as a condition of employment in said Work, that an employee lodge, board, or trade at a particular place or with a particular person. 1.1.4 The Contractor and each Subcontractor shall give preference in employment of mechanics, apprentices, teamsters, chauffeurs and laborers, first to citizens of the Commonwealth who have been residents of the Commonwealth for at least six months at the commencement of their employment and who are veterans as defined in clause 43 of Section 7 of Chapter 4 of the General Laws, and who are qualified to perform the Work to which the employment relates; and secondly, to citizens of the Commonwealth generally, and if they cannot be obtained in sufficient numbers, then to citizens of the United States. 15.2 Executive Orders 1.1.1 The Contractor shall comply with the provisions of M.G.L. Chapter 151B; Executive Order No. 227, Governor's Code of Fair Practices, amending and Revising Executive Orders No. 116 and 117; Executive Order No. 237 pertaining to minority and women business development; Executive Order No. 246 pertaining to the handicapped and all regulations promulgated pursuant thereto. The aforementioned law, Executive Orders, and regulations are incorporated herein by reference and made a part of this Contract. GENERAL CONDITIONS - 40 TABLE OF CONTENTS ARTICLE 1 - CONTRACT DOCUMENTS 1.1 Definitions A. The Contract Documents B. The Contract C. The Work D. The Project 1.2 Execution, Correlation and Intent 1.3 Ownership and Use of Documents ARTICLE 2 – DIRECTOR 2.1. Definition 2.2 Administration of the Contract ARTICLE 3 - OWNER 3.1 Definition 3.2 Information and Services Required of the Owner 3.3 Owner's Right To Stop The Work 3.4 Owner's Right To Carry Out the Work 3.5 Partial Occupancy ARTICLE 4 - CONTRACTOR 4.1 Definition 4.2 Review of Contract Documents 4.3 Supervision and Construction Procedures 4.4 Labor and Materials 4.5 Warranty 4.6 Taxes 4.7 Permits, Fees and Notices 4.8 Allowances (intentionally deleted) 4.9 Superintendent 4.10 Progress Schedule 4.11 Documents and Samples at the Site 4.12 Shop Drawings, Product Data and Samples 4.13 Use of Site 4.14 Cutting and Patching of Work 4.15 Cleaning Up 4.16 Indemnification ARTICLE 5 - SUBCONTRACTORS 5.1 Definition 5.2 Award of Subcontracts and Other Contracts For Portions of the Work 5.3 Subcontractural Relations ARTICLE 6 - (INTENTIONALLY DELETED) ARTICLE 7 - MISCELLANEOUS PROVISIONS GENERAL CONDITIONS - 41 7.1 Governing Law 7.2 Successors and Assigns 7.3 Written Notice 7.4 Claims For Damages 7.5 Performance Bond and Labor And Material Payment Bond 7.6 Rights And Remedies 7.7 Tests 7.8 Interest 7.9 Disputes 7.10 Record Keeping and Management Controls ARTICLE 8 - TIME 8.1 Definitions 8.2 Progress and Completion 8.3 Delays and Extension of Time ARTICLE 9 - PAYMENTS AND COMPLETION 9.1 Contract Sum 9.2 Schedule of Values 9.3 Application for Payment 9.4 Certificates For Payment 9.5 Progress Payments 9.6 Payments Withheld 9.7 Failure of Payment 9.8 Substantial Completion 9.9 Final Completion and Final Payment ARTICLE 10 - PROTECTION OF PERSONS AND PROPERTY 10.1. Safety Precautions and Programs 10.2. Safety of Persons and Property 10.3. Emergencies ARTICLE 11 - INSURANCE 11.1. Contractor's Liability Insurance 11.2. Owner's Liability Insurance 11.3. Property Insurance 11.4. Loss of Use Insurance ARTICLE 12 - CHANGES IN THE WORK 12.1. Change Orders 12.2. Concealed Conditions 12.3. Claims for Additional Cost 12.4. Minor Changes in the Work ARTICLE 13 - UNCOVERING AND CORRECTION OF WORK 13.1 Uncovering of Work 13.2 Correction of Work 13.3 Acceptance of Defective or Non-Conforming Work 13.4 Special Guarantees And Warranties GENERAL CONDITIONS - 42 ARTICLE 14 - TERMINATION OF THE CONTRACT 14.1 Termination By the Contractor 14.2 Termination By The Owner ARTICLE 15 - LABOR REQUIREMENTS OF THE COMMONWEALTH OF MASSACHUSETTS 15.1 Labor Laws 15.2 Executive Orders GENERAL CONDITIONS - 43 Certificate by Corporation to Sign Contract At a duly authorized meeting of the Board of Directors of the held on (Name of Corporation) (Date) At which all the Directors were present or waived notice, it was voted that, (Name) (Officer) of this company, be and he hereby is authorized to execute contracts and bonds in the name and behalf of said company, and affix its Corporate Seal thereto, and such execution of any contract or obligation in this company's name on its behalf by such under seal of the company, (Officer) shall be valid and binding upon this company, A TRUE COPY, ATTEST: (Clerk) PLACE OF BUSINESS DATE OF THIS CONTRACT I hereby certify that I am the clerk of the that is the duly elected of said company, and the above vote has not been amended or rescinded and remains in full force and effect as of the date of this contract. (Clerk) (Corporate Seal) GENERAL CONDITIONS - 44 Tax and Reporting Compliance Certification Pursuant to M.G.L. Chapter 62C, Section 49A, I certify under the penalties of perjury that I have, to my best knowledge and belief, complied with the law of the Commonwealth relating to taxes, reporting of employees and contractors, and withholding and remitting child support. Social Security Number or Signature of Individual or Federal Identification Number Corporate Name by: Corporate Officer (if applicable) GENERAL CONDITIONS - 45 Foreign Corporation Certification AFFIDAVIT OF COMPLIANCE Form AF-4A 1/78 EXECUTIVE OFFICE FOR ADMINISTRATION AND FINANCE The Commonwealth of Massachusetts MASSACHUSETTS BUSINESS CORPORATION NON-PROFIT CORPORATION FOREIGN (non-Massachusetts) Corporation 1. , President Clerk of whose principal office is (Name of Corporation) located do hereby certify that the above named Corporation has filed with the State Secretary all certificates and annual reports required by Chapter 156B, Section 109 (Business Corporation), by Chapter 181, Section 4 (Foreign Corporation), or by Chapter 180, Section 26A (non-profit Corporation) of the Massachusetts General Laws. SIGNED UNDER THE PENALTIES OF PERJURY THIS day of , 19 . Signature of responsible Corporate Officer