011000MSBA Accelerated Repair Program RK Finn/Ryan Road and Leeds Elementary Schools Northampton, Massachusetts Summary of the Work 01 10 00-1 SECTION 01 10 00 SUMMARY OF THE WORK 1.01 GENERAL CONDITIONS A. The "Standard Form of Agreement," AIA Document A101, 1997 Edition, Electronic Format, as published by The American Institute of Architects, together with all Amendments and Supplements as hereinbefore listed, shall apply and are hereby made a part of this section of the Specifications. B. The Sections of these Specifications entitled "Special Conditions, "Minimum Wage Determination," and Division 1 "General Requirements" shall apply and are hereby made a part of this section of the Specifications. 1.02 LOCATION OF WORK The work of this contract shall be performed at two schools; the RK Finn Ryan Road School - 498 Ryan Road, Northampton Massachusetts, 10160 and the Leeds Elementary School – 20 Florence Street, Leeds, Massachusetts 01053. 1.03 CONTRACT DESCRIPTION A. The work consists of: 1. Roof system replacement for two (2) schools. a. Leeds Elementary School Roof: Remove existing adhered membrane roofing systems and portions there of as described down to the metal decks at roof locations indicated. Install new vapor-barrier, insulation board, tapered insulation, cover board and 90 mil EPDM membrane as specified. b. R K Finn Ryan Road School: Remove existing ballasted and adhered membrane roofing systems and portions there of as described down to the metal decks at roof locations indicated. Install new vapor-barrier, insulation board, tapered insulation, cover board and 90 mil EPDM membrane as specified. The roofer shall be an authorized Firestone applicator or shall hire a Firestone licensed applicator to complete the tie-in portion of work adjacent to the existing roof not in contract. The required tie-in detail is to be reviewed and accepted by Firestone and to be inspected by their field technical representative for acceptance. Verification that Firestone has reviewed and accepted the tie-in work and that it is included in the new warranty and that the existing 30-year warranty for the adjacent roof remains in full effect will be required. 2. Remove/replace all perimeter metal fascias throughout where new membrane roof system is indicated. 3. Install new nailers and blockings where indicated. Portions of exiting blocking to be retained and to be reused. 4. Remove and replace all scuppers, gutters and downspouts where noted. 5. Replace strainers and clamp rings at roof drains where indicated. Clean and reutilize all existing roof drains except where noted to be replaced. Replace entire drain if discovered to be damaged through unit pricing. 6. Install ballasted guard safety railings at perimeter roof edges at Courtyards and where noted. 7. Install new roof access ladders where noted.. 8. Remove and reinstallation existing exhaust fans, Louver Housings, intake hoods, roof and condensing units, etc. as required to install new roof flashings. Work also includes modification of curbs as necessary to meet minimum flashing height requirements. 9. Remove and install new metal panel at masonry opening at the RK FINN Ryan Road School. MSBA Accelerated Repair Program RK Finn/Ryan Road and Leeds Elementary Schools Northampton, Massachusetts Summary of the Work 01 10 00-2 10. Other work as indicated on drawings 1.04 GENERAL SCOPE OF WORK A. The work to be done consists of roof replacement at two schools; the RK Finn Ryan Road School - 498 Ryan Road, Northampton Massachusetts, 10160 and the Leeds Elementary School – 20 Florence Street, Leeds, Massachusetts 01053 as shown and specified on the contract drawings and project manual entitled: RK Finn Ryan Road School Roof Replacement Project 498 Ryan Road, Northampton Massachusetts, 10160 Leeds Elementary School Roof Replacement Project 20 Florence Street, Leeds, Massachusetts 01053 B. The General Contractor shall furnish and do everything, except as otherwise provided by specified indications herein or on the drawings, necessary to complete the work in accordance with the plans and specifications. He/she shall furnish all plant, labor, materials, supplies, tools, water, machinery, implements, light, power, transportation, and other facilities required, and do all work necessary for the complete execution and completion of the contract, except that work or materials specifically stated to be done or furnished by others. C. All work and materials furnished and installed shall be of the best quality and workmanship, and to the satisfaction of the Architect. There shall be no defect in the work or the operation thereof due to inferior materials or the workman like placing of any part. The work under this contract shall be performed at such times as may be necessary to facilitate the orderly progress of the work, and so as not to interfere with the continued use of the building for school purposes. It is the intention of these specifications and plans to cover all work necessary and incidental to the completion of this project, including all trades, as shown on the drawings or specified. D. It is required that the general contractor provide, for the project duration, a competent full-time project superintendent who is a Licensed Construction Supervisor in the state of Massachusetts. E. Contractor shall do all necessary cutting and patching of structural and finish work as necessary to provide the finished results shown on the contract drawings and as herein specified. 1.05 PROJECT CONSTRUCTION COST ACCOUNTING A. The contractor shall prepare a Schedule of Values to be used for establishing the breakdown of costs and for determining percentages of completion for monthly payments for this project. B. The Schedule of Values shall include a complete breakdown of the costs for labor and material, separately, by roof area of the various trades with further breakdown of each trade as required by the Architect. These Schedules of Values shall be submitted to and approved by the Architect prior to the submission by the contractor for the first Application for Payment and shall be used for all subsequent applications. END OF SECTION