NHS_BBT_Field Report_2_2012-10-01M:\12040 - NHS Black Box Theater\NHS_BBT_Field Report_2_2012-10-01.docx Page 1 of 1
TIME: 5:30pm WEATHER: 70’s, Sunny
PRESENT: Steve Zucchino, General Contractor & Bruce Lathrop, Lead Parent Coordinator
In accordance with 780 CMR116.0, I have completed field visits and observed the following work:
OBSERVATIONS:
Due to a flood caused by a pipe burst in a water fountain in the theater on September 20th, the newly installed laminate
floor & the existing rubber floor had to be removed. The seating risers had to be dismantled, and the soggy insulation
removed. The concrete floor was thoroughly cleaned and dried. A new Masonite floor on plywood & sleepers will be
installed. Fire blocking will be provided every 10 and sloped transitions will be provided at flooring transitions. The seating
risers are being rebuilt to accommodate the new floor and new insulation is being installed inside the risers. Seating will be
reinstalled on the risers. Panic hardware remains to be purchased and installed.
Northampton High School to provide narrative on Egress Procedure.
The building committee anticipates completing the work in the next two weeks.
If you should have any comments, questions or corrections, please contact me.
Aelan B. Tierney, AIA, LEED AP
Kuhn Riddle Architects
TO Louis Hasbrouck, Northampton Building Commissioner DATE : OCTOBER 10, 2012
Puchalski Municipal Building
212 Main Street, Northampton, MA 01060
PROJECT: NORTHAMPTON HIGH
SCHOOL BLACK BOX THEATER
cc: Steve Zucchino, Stephen Eldridge, Bruce Lathrop PROJECT NO.12040
SUBJECT: PROGRESS
FIELD REPORT #2