Meeting notes 2-6-2018Crocker Building Company Inc. Meeting Notes Project: CheckWriters (Gaiwith Hall) Date: February 6, 2018 Location: 46 Round Hill Rd Northampton, MA Current Construction Status: • Structural improvements continue. • Steel framing is nearly complete in the North wing. • M.J. Moran is working on the HVAC design. • Attached to these notes is the latest field report from GNCB. • The Northampton Building Official conducted an informal walk thru on Feb, 9th. Current Items: • We are requesting a schedule for the completion of the Architectural and Structural drawings. The schedule for construction drawings is February 19. 2/6/18. • A complete Building Permit will be issued after the completion of the drawings and final code review. 2/9/18. • A discussion and review or the proposed rod bracing for the 3rd floor West wing took place. A decision was made to use wood collar ties and provide a flat ceiling a high as possible. Item Closed 2/6/18. • Some HVAC unit and ductwork locations remain to be determined. We will request M.J. Moran attend the next project meeting to review. 1/30/18. Additional review is required to determine the feasibility of locating a large HVAC unit on the third floor roof and ducting down for the third and second floors? 2/6/18. • Temp heat was discussed. At this time the Gas Company will not provide service until a more definitive service size is determined. No additional temp heat is proposed at this time. Item Closed as of 2/6/18. • Proposals for a (temporary /construction) fire alarm system were reviewed. The decision was made to not install unless required by the Building Officials. Item Closed 2/6/18. Open Items: • Exterior ADA ramp to remain at the former front entry. The rails will be reviewed for compliance. 1/30/18 • Max Hebert will check with the backup generator supplier for serviceability of the existing unit. 1/30/18. Owner / Contractor Items: • Contract remains open pending a legal review. • The Performance and Payment Bond have been issued and provided to the Owners. • Preliminary invoicing for work thru Jan 30th was submitted on Feb 9th. Next meeting schedule, Tuesdays Feb 13th, at 9:30 AM. Field Report: #2 Sent Via: douglas@tdouglasarchitects.com Page 1 of 3 Date: January 31, 2018 Attention: Tom Douglas Thomas Douglas Architects Northampton, MA Project: Checkwriters Job Number: 15137 Weather: Cold, Low 30s Present: Amy Jagaczewski (GNCB), Nate (Crocker Building Company) GNCB visited the site on Monday, January 29, 2018 from 3:30 pm to 4:30 pm to review the progress of construction. A Key Plan of the building is provided to the left to assist the Reader. The following was reviewed and discussed: 1. The floor sistering is in progress at all levels. 2. The steel installation is almost complete at the east building. The new W10x along Grid E2 at the second and third floors was discussed. The new beams are only supporting the hallway joists at these locations. The new steel can be substituted for a header consisting of 2-1 ¾” x 9 ¼” LVL. All existing joists must be fastened to the new LVLs with Simpson hangers or 2-A35 clips at each end. 3. The gable roof at the northeast corner of the east building was discussed. The existing girder supporting the gable roof consists of 3, 14” deep members, not two as called out in the structural drawings. The new sisters at this location are not needed. All rafters should have studs down to the existing triple. Submitted by: Amy Jagaczewski Copies to: Sent via: James F. Norden (GNCB) Scott Laidlaw (TDA) Bill Crocker (Crocker) Mike Longo (Specialized) Shannon Danylieko (Dublin) norden@gncbengineers.com scott@tdouglasarchitects.com bcrocker@crockerbuilding.com mike@specializedconst.net Shannon@dublinsteel.net Checkwriters Field Report #2 January 31, 2018 Page 2 of 3 Photo P01: Steel installation at east building. Photo P02: Location of potential conversion from steel to wood header at second and third floor of east building. Photo P03: Gable roof supported on existing triple at northeast corner of east building. Checkwriters Field Report #2 January 31, 2018 Page 3 of 3 Photo P04: Sistering in progress at west building. Photo P05: Sistering in progress at south building.