Loading...
RTP Final Report for Lake Boardwalk Installation 1 Recreational Trails Program - Massachusetts Final Report Form Report Period: July 1, 2016 to April 30, 2017 Date Submitted: May 31, 2017 Project Name: Bridge, Boardwalk & Dock Rehabilitation at the Fitzgerald Lake Conservation Area Organization: Broad Brook Coalition Contact Person and Title: Robert Zimmermann, President, Broad Brook Coalition Address: 549 North Farms Road, Florence, MA 01062-1043 Telephone: 413-585-0405 Email: raz@umass.edu Effective Date of Contract: October 30, 2015 End Date of Contract: December 31, 2017 Project Completion Date: April 30, 2017 Total Project Cost/Value: $88,500 Federal Share $50,000 Match $38,500 Value of contributed volunteer time: 582 hours @ $29.88/hr (independent Sector) $ 17,390 Narrative (Please provide a complete and detailed narrative final report on the project, limited in length to three pages, not including supporting materials. Include all progress made, problems encountered, resolution to those problems, changes in expenditures or project scope, and the final status of the project. Attach additional sheets as necessary. Attach any relevant photographs, expenditure spreadsheets or other documentation that helps demonstrate the final status of the project and its impact on the Massachusetts trail system as a whole, from the community/local level to the statewide level. (If your grant involved the purchase of large equipment and requires equipment reporting as stipulated in your grant agreement, see page 2): BRIDGE, BOARDWALK & DOCK REHABILITATION AT THE FITZGERALD LAKE CONSERVATION AREA FINAL REPORT TO THE RECREATIONAL TRAILS PROGRAM, MA DCR MAY 2017 The Recreational Trails Program of the Massachusetts Department of Conservation and Recreation provided funds for the replacement of the bridge-over-the-brook, rehabilitation of the boardwalk, and construction of a boardwalk extension with a new dock at the Fitzgerald Lake Conservation Area in Northampton, Massachusetts. The budget for the entire undertaking was $88,500. In fall 2015, the Recreational Trails Program awarded Broad Brook Coalition $50,000 toward the project, while matching funds were provided by a $30,000 grant from the Northampton Community Preservation Committee, a $7,500 contribution from Broad Brook Coalition (BBC), and a $1,000 gift from the Norcross Wildlife Foundation. BBC volunteers also contributed 582 hours of work to the project, a value of $17,390 according to the volunteer equivalency rate of $29.88/hr in Massachusetts (see http://Independentsector.org, 2016 data). To accommodate the financial regulations and procedures of the City of Northampton, Wayne Feiden, Director of the Office of Planning and Sustainability, generously agreed to serve as fiscal agent for the management and disbursement of funds from the three main grants. Dick O'Brien, Conservation Works LLC, provided day-to-day supervision of the work on site. The project unfolded in three separate, more or less sequential phases. The first phase entailed demolition of the old bridge and construction of the new bridge and its approach ramps. The second was the rehabilitation of the boardwalk and the third, extension of the boardwalk with a new dock at the end. RTP funds were used in all phases of the work, which is now complete. Photos illustrating various stages of the project are included at the end of this report. Phase 1. Bridge components were made of precast, fiber-reinforced polymer members manufactured in Pennsylvania and trucked to the site early in July 2016. The existing bridge was demolished by a crew of volunteers on July 15 and 16 in preparation for the arrival of a five-person crew from the Student Conservation Association Massachusetts Americorps (SCA) on July 18. The SCA crew was mainly responsible for assembling the 30-foot bridge and building the two ~40-foot approach ramps. After the SCA crew had pitched their tents and settled in, the first order of business was to lay the foundations for the bridge and ramps, which consisted of Diamond Piers, and erect the posts that support the superstructure. The bridge was then assembled from its components and, by the end of the week, placed on its supports. Construction of frames for the approach ramps on each side of the bridge was started, and decking was installed on the bridge, prior to the departure of the SCA crew on July 27. In the ensuing weeks, the ramp frames were completed and decked, and equipped with sturdy handrails, all by volunteers. The final step was to attach stiff wire netting to the handrails to eliminate the possibility of falls from the ramp in conformity with standards prescribed by the federal Americans With Disabilities Act (ADA). The bridge was officially opened for pedestrian traffic on August 24. Phase 2. On July 8 and 9, volunteers cleared brush and grass from the sides of the boardwalk in order to allow access to the horizontal sleepers on which the boardwalk frames were laid. On August 8-10, Terramor LLC winched sections of the existing boardwalk to level height, roughly 18" above ground, and installed new supports that consisted of pairs of 4" x 4"posts driven into the ground at 10-foot intervals onto which two 2" x 6" cross beams were bolted. Raising and leveling the boardwalk was finished on September 12-14 by Douglas Thayer Woodworking and Design who found it more efficient to jack rather than winch the boardwalk to level height. Between September 15 and 23, 5" curbing was installed by volunteers along the entire length of the boardwalk to comply with ADA standards for wheelchair use. Phase 2 was completed on September 26. Phase 3. A 100-foot extension of the boardwalk was added by Douglas Thayer Woodworking and Design in November 2016. Here again, pairs of 4" x 4" posts were driven into solid ground at 10- foot intervals, and two 2" x 6" cross beams attached to each pair. Frames for the boardwalk were then constructed and attached to the cross beams, and the decking was installed. Stabilizing cross pieces were added to the posts and frames as necessary. The boardwalk terminates in a 10- by 20-foot viewing platform and boat launching dock. Finally, 5" curbing was installed along the newly constructed section of boardwalk and platform. This phase of the work was completed on November 28. In April, 2017, two 8-foot benches with mahogany seats and back rests were installed on the dock by Thayer Woodworking, funded in part by a generous donation from the Norcross Wildlife Foundation. The structures described above have been designed to provide safe passage to all visitors to the FLCA and have been built to the specifications of the Americans With Disabilities Act. We believe that these structures will require only minimal maintenance over the next 15-20 years but, when necessary, upkeep will be provided or organized by Broad Brook Coalition volunteers. Completion of the rehabilitated bridge, boardwalk and dock was celebrated by a reception at the site on April 23, 2017, attended by BBC members, friends and volunteers; Dick O'Brien; Douglas Thayer; Kevin Lake, chair of the Northampton Conservation Commission; and Representative Peter Kocot. We are very pleased to have been able to enhance the environment of the Fitzgerald Lake Conservation Area for the many visitors from the community and elsewhere who use the bridge, boardwalk and dock throughout the year. The new dock, with its comfortable benches, has proven particularly popular as it offers an opportunity to sit "in" the lake with a 360-degree view of the terrestrial and aquatic surroundings. We are most grateful to the Recreational Trails Program, along with our other supporters, for making this project possible. Robert A. Zimmermann President Broad Brook Coalition May 31, 2017 BUDGET SUMMARY RTP AWARD RTP Contract $ 50,000.00 RTP EXPENDITURES Vendor Purpose Amount Kelcom Storage trailer rental $ 475.00 Starlift Equipment Forklift rental 665.05 Northampton DPW, etc. Tipping fees for debris 514.89 SCA Massachusetts Student volunteer stipends 7,400.00 E. T. Techtonics FRP bridge (in part) 1,377.96 Conservation Works Lumber, hardware, supplies 9,157.91 equipment rental for bridge and boardwalk rehabilitation (reimbursement) Terramor LLC Raising and resetting boardwalk 9,932.50 Douglas Thayer Woodworking Raising and resetting boardwalk 8,300.00 Cowls Building Supplies Lumber, hardware, supplies, 2,964.67 equipment rental for boardwalk extension Douglas Thayer Woodworking Construction of boardwalk 5,900.21 extension (in part) Conservation Works Clerk of Works 3,311.81 __________ RTP Total $ 50,000.00 MATCHES Northampton Community Preservation Act Funds $ 30,000.00 Broad Brook Coalition 7,700.00 Norcross Wildlife Foundation 1,000.00 VALUE OF VOLUNTEER TIME CONTRIBUTED TO PROJECT Volunteer time: 582 hours @ $29.88/hr (independent Sector) $ 17,390.00 Opening the NFR Entrance for Deliveries The Bridge Arrives, in Pieces Demolition of the Old Bridge SCA Crew Settles in Putting in Diamond Piers Preparing the Decking Assembling the Bridge Erecting Support Posts on Piers Setting Assembled Bridge on Sleepers Placing Beams for Approach Ramp Building Frames for Approach Ramp SCA & BBC Crews: Almost Done A-Frame for Winching up Boardwalk Pounding in New Boardwalk Supports Using Jack to Raise Boardwalk New Boardwalk Support System Installing New Boardwalk Curbing Dick O'Brien at Rest, at Last Positioning Frames for Extension Decking Boardwalk Extension Installing Frames for Dock Putting Finishing Touches on Dock Measuring Up for Bench Backrests Benches: Final Stages New Boardwalk Extension in Use New Bench on the Dock New Bridge and its Setting