10-006 2017 03 16 Basis of Design - RMB.pdfGZA
March, 2017
Abbreviated Basis of Design Discussion
Roberts Meadow Brook Channel Rehabilitation Project
As shown on the Project drawings, rehabilitation of the Roberts Meadow Brook channel segment
at the Site is extensive in scope and character. The affected channel segment is not a natural
channel. In 1871, Roberts Meadow Brook was relocated during the construction of the Lower
Roberts Meadow Reservoir and its associated dam, which is at the upstream end of the Project
Site. The realigned, man-made channel has conveyed flow fromthe dam’s spillwayto the Roberts
Meadow Brook downstream of Reservoir Road. During the 1955 flooding resulting from Hurri-
caneDiane, thedamwas breachedandtheReservoir Roadbridgewaswashedout. Thesubsequent
repairs involved additional channel stabilization in the brook between the dam and bridge, and a
new bridge constructed in a slightly different location. Since that time, the brook planform and
profile have shown signs of instability. In recent years, the brook has exhibited extreme erosion
of the left bank, threatening private property and downstream areas including Reservoir Road and
the bridge.
Project Goals
A careful examination of the affected channel segment indicates that the reach is characterized by
a very steep gradient (2.7%), with little in the way of stable bedform materials and structure to
provide positive grade control. Recognized needs include:
Establish grade control
Reduce streambank erosion
Enhance fish habitat
Maintain width/depth ratio
Maintain river stability
Dissipate excess energy
Withstand large floods
Maintain channel capacity
Be compatible with natural channel design, and
Be visually acceptable to the public.
Structural Measures
Inorderto accomplishthe above goals, the channel rehabilitationofthis reachofRoberts Meadow
Brook has been designed in accordance with the tenets presented in these and other references:
Rosgen, D.L. 2001 The Cross-Vane, W-Weir and J-Hook Vane Structures…Their
Description, Design and Application for Stream Stabilization and River Restora-
GZA
March, 2017
tion Proceedings of the 2001 Wetlands Engineering & River Restoration Confer-
ence held in Reno, Nevada, August 27-31.
USDA– NRCS Part 654StreamRestorationDesign– NationalEngineering Hand-
book, August, 2007; Chapter 11: Rosgen Geomorphic Channel Design.
The primary structure to be utilized in the Roberts Meadow Brook Channel Rehabilitation Project
is the Cross-Vane structure. The Cross-Vane is a grade control structure that decreases near-bank
shear stress, velocity, and stream power, but increases the energy in the center of the channel. The
structure can establish grade control, reduce bank erosion, create a stable width/depth ratio, and
maintain channel capacity, all while maintaining sediment transport capacity and sediment com-
petence. The Cross-Vane also provides for secondary circulation patterns corresponding with
channelpatterns, but with high velocitygradients and boundarystress shifted away fromthe banks
of the channel. The Cross-Vane is also recognized as a stream habitat improvement structure.
The vane arm portion of the Cross-Vanes for the Roberts Meadow Brook rehabilitation have been
specified with a relatively shallow angle of about 20 degrees to the bank, which provides for a
long vane length and protects the greatest length of streambank. The vane slope is approximately
7 percent and provides for a 2’-0”± drop from “bankfull height” to the center, deepest portion of
the vane. Where the valley width is sufficient, a “Bankfull Bench” has been provided adjacent to
the existing higher banks, and the Cross-Vane structure is integrated into the bench with a sill of
large boulders.
The size of the individual boulders which make up the Cross-Vane structure was determined by
an empirical relationship corresponding with bankfull shear stress, calculated for the existing
stream channel. The bankfull shear stress of about 3.4 lb/ft
2 (16.5 kg/m
2) indicates a boulder size
of at least 43” (1.1 m) is required; thus, a minimum boulder size of 48” in anydimension has been
specified.
The channel bottom will consist of the small boulders, cobbles, and gravel present throughout the
affected stream reach. At each Cross-Vane, the invert boulders will have a surface protrusion of
about 12” and the footer boulders will be embedded 3’-0” below the channel bottom. Except as
described below for the large Cross-Vane boulders, the same existing channel materials will be
utilized for all work within the channel and up to three feet above the channel bottom. Thus, only
the “natural” channel materials will be utilized below the Mean Annual High Water Line
(MAHWL), which is judged to be approximately 2’-6” above the channel bottom. As indicated
on the drawings, should additional “off-site” materials be required to attain the grades and dimen-
sions shown, any materials used within three vertical feet of the channel bottom will consist of
natural, rounded boulders, cobbles, and gravel consistent in character and appearance with the
existing stream bed materials.
As stated above, the Cross-Vanes will be constructed using boulders a minimum of 48” (4’-0”) in
any dimension. Assuming a spherically-shaped boulder, this translates to a minimum weight of
about 5,500 pounds (2.75 tons). Approximately 135 such boulders will be required to construct
the four Cross-Vanes. The existing channel section is composed of boulders, cobbles, gravel, and
sand, yet there does not appear to be sufficient large-boulder material to construct the required
Cross-Vanes. The lack of such boulders in the existing stream channel may be an indicator of
GZA
March, 2017
inherent instabilityin the channel as originallyconstructed ca. 1871. As such, geologically-appro-
priate boulders, rounded and natural in appearance, will be sourced from off-site areas and im-
ported to the Site for the construction of the Cross-Vanes.
The distance between Cross-Vanes was selected based on the overall channel slope, in percent,
whichwasrevealed bytopographicsurveyto beapproximately2.7%. BasedonRosgen’s negative
power function relationship between the ratio of pool/cross-vane spacing and bankfull width, a
spacing of93 feet is indicated. As shownonthe drawings, spacing ofthe four (4) new Cross-Vane
structures is 95 feet, indicated on the drawings by stationing along the construction baseline.
At this reach of Roberts Meadow Brook, both banks are eroding due to confinement (lateral con-
tainment) and entrenchment (vertical containment). The Cross-Vane is ideally suited for this ap-
plication because the structure decreases the stream power and shear stress concurrently on both
banks. This avoids lining or hardening both banks through the reach to provide protection. The
areas of the left bank above the MAHWL will be armored with stone revetment to maintain pro-
tection for up to and including the 100-year flood event.
Cross-Vane structures can be implemented to maintain or enhance river stability and can facilitate
multiple objectives. These structures have been successfully applied in natural channel design for
river restoration, bank stabilization, grade control, irrigation diversions, fish habitat enhancement,
bridge protection, and recreational boating. Cross-Vanes can be applied to meet the ever-increas-
ing demand for environmentally “softer” structures that meet multiple objectives, including the
goals of the Roberts Meadow Brook Channel Rehabilitation Project.
Plantings
Plantings have been specified for the “Bankfull Bench” areas and the upland areas above the re-
vetment slopesadjacent totheundisturbedwoodedareas. Allspeciesofplantswereselectedbased
on their prevalence within this reach of Roberts Meadow Brook and its immediately-surrounding
areas. Theplantsselectedfor the“Bankfull bench” areasarethesame nativeplantsobservedalong
the banks of the brook and at the cobble/gravel bars that have developed and include a mix of
herbaceous and shrub species including Lurid Sedge, Fringed Sedge, Grass-Leaved Goldenrod,
Winterberry, Silky Dogwood, and Speckled Alder. For the upland areas, Red maple, Red Oak,
and Witch Hazel have been specified.
Maintenance Plan
To ensure that the implemented design is successful, a maintenance plan will be exercised to en-
sure the following:
Survival of the riparian vegetation. It is anticipated that volunteer species will help
establish vegetation within the “Bankfull Bench” areas to supplement the planting spe-
cifically included in the Project. These areas will be inundated several times during the
year and survival may be spotty initially. The larger trees in the upland area will be
nursery-grown and will carrya warrantythrough the construction procurement process.
Structure stability. Post-storm inspections will be conducted of the Cross-Vane struc-
turesfor grade control, bank stabilization, and habitat enhancement. Maintenance needs
will be assessed and implemented to prevent future failures and secure proper function.