Project!'Site Name: Beaver Brook Condo'Multifamily Development for Parcel 24
Project Street or Location/Assessor ID: Haydenvilie Rd.,Leeds,MA/Map 06 Parcel 62
Applicant Name: Patrick J. Melnik
Applicant Address/Phone: 311 Chesterfield Rd., Leeds, MA/ 584-6750
Application Submission Date: 3,/21/2006
Total Lot Size(f')_ 244,398 _ Estimated Area to he Disturbed (ft2):25,600
THE FOLLOWING DECISION BY THE NORTHAMPTON DEPARTMENT OF
PUBLIC WORKS HAS BEEN MADE ON THIS WAIVER APPLICATION BASED ON
INFORMATION PRESENTED:
X Disapproval of the Stormwater Management Permit Waiver Application
based upon a determination that the proposed project shall require an
approved Stormwater Management Permit as specified in the Northampton
Stormwater Management Ordinance(Chapter 22 Article 5).
Approval of the Stormwater Management Permit Waiver Application subject
to any conditions required by the Northampton Department of Public Works
(see conditions below). The Northampton DPW has determined that the
project described above is exempt from meeting the stormwater performance
standards as outlined in the Northampton Stormwater Management
Ordinance(Chapter 22 Article 5)for the following reason:
Signature of City Engineer Date
cc. Planning Board c/o Office of Planning and Development
Building Department
Conservation Commission c/a Office of Planning and Development
E:\Stomtwater Permits\Stonnwater Permits\Waiver Decisions\Haydenville Rd._Waiver Decision doe
Page 1 of 1
0 C (off
-i c STORMWATER MANAGEMENT PERMIT
APPEIC, ION DECISION
City of Northampton
Department of Public Works --' i
li
2008
s
Project/Site Name: Beaver Brook Estates— Multifamily Development Plan for Parcel 24
Project Street/Location: Haydenville Road—Route 9 _
Applicant Name: Patrick J. Melnik Es..
Applicant Address/Phone: t t l King Street, Northampton, MA/584-6750
Application Submission Date: 4/4/2006
THE FOLLOWING ACTION BY THE NORTHAMPTON DEPARTMENT OF PUBLIC
WORKS HAS BEEN TAKEN ON THIS APPLICATION BASED ON INFORMATION
PRESENTED:
X Disapproval of the Stormwater Management Permit Application based on a
determination within seven days of the receipt of the application that the
application is administratively incomplete (see attached documentation).
Approval of the Stormwater Management Permit Application.
_ Approval of the Stormwater Management Permit Application subject to any
conditions, modifications or restrictions required by the Department of
Public Works.
Disapproval of the Stormwater Management Permit Application based upon
a determination that the proposed plan,as submitted,does not meet the
purposes set forth in the Northampton Stormwater Management.
J2 h/°‘
Signature of City Engineer Date
cc. Planning Board do Office of Planning and Development
Building Department
Conservation Commission do Office of Planning and Development
NORTHAMPTON DEPARTMENT OF PUBLIC WORKS
NOTICE OF INCOMPLETE APPLICATION
STORMWATER MANAGEMENT PERMIT
Project/Site Name: Beaver Brook Estates—Multifamily Development Plan for Parcel 24
Project Street/Location: Haydenville Road—Route 9
Applicant Name:Patrick J. Melnik-.Esq.
Applicant Address/Phone: 111 King Street Northampton, MA / 584-6750
Application Submission Date: 4/4/2906
The Northampton Department of Public Works (DPW) is in receipt of the
application for a Stormwater Management Permit for the above referenced project.
The application has been found to be incomplete.The timeline for application
review and final action by the Northampton DPW will begin once a complete
application has been submitted. The application is incomplete fot the following
reason(s):
X The Stormwater Management Permit Application is not complete and/or
signed.
X The Permit Review and Inspection Fee is not paid.
The Operation, Maintenance, and Inspection Agreement was not submitted
and/or is not complete.
The Stormwater Management Plan and Erosion and Sediment Control Plan
are not complete.The following information has not been submitted and/or
is not complete:
Identify all operators for the project site and the potions over which each operator
has control.
All plans submitted have been prepared and stamped by a professional engineer
licensed by the Commonwealth of Massachusetts
The applicant has certified on the drawings that all clearing,grading,drainage,
construction,and development shall be conducted in strict accordance with he plan
Locus map
The existing zoning, and land use at the site
The proposed land use
The location of existing and proposed casements
The location of existing and proposed utilities
The site's existing&proposed topography with contours at 2 foot intervals
Soils investigation (by a Certified Soil Evaluator or Certified Professional Soil
Scientist)including borings or test pits, to a depth greater than 4 ft. below estimated
seasonal ground water for areas where construction of infiltration practices will
Occur.
Estimated seasonal high groundwater elevation (November to April) in areas to be
used for storm water retention,detention,or infiltration (by a Certified Soil
Evaluator or Certified Professional Soil Scientist).
_. A description&delineation of existing stormwater conveyances,impoundments,
and wetlands on or adjacent to the site or into which storm water flows.
A delineation of 100-year flood plains,if applicable.
The existing and proposed vegetation and ground surfaces with runoff coefficient
for each.
_ _ A drainage area map showing pre and post construction watershed boundaries,
drainage area,storm water flow paths,and receiving water.
A description and drawings of all components of the proposed drainage system
including;
1) the structural details for all components of the proposed drainage systems and
storm water management facilities (including size,inverts,and grade);
2) all measures for the detention,retention or'infiltration of water;
3) all measures for the protection of water quality;
4) notes on drawings specifying materials to be used,construction specifications,
and ttpicals;
5) the existing and proposed site hydrology-with supporting drainage calculations
(including the 1,2,10,and 100 year NRCS design storms);
6) proposed improvements including location of buildings or other smtaures,
impervious surfaces,and drainage facilities,if applicable;
7) location,cross sections,and profiles of all potentially impacted brooks, streams,
drainage swales and their method of stabilization;and
8) proposed ownership of drainage system structures.
Estimate of the total area expected to be disturbed b-excavation,grading or other
construction activities.
A description and location of all measures (i.e., Best Management Practices) that ryill
be implemented as part of the construction activity to control pollutants in storm
water discharges.A description of when each control measure will be implemented
in the construction schedule,which operator is responsible for the implementation
of each control measure and a maintenance and inspection schedule for each
control measure during construction.
_ A description of construction and waste materials expected to be stored tar-sire,and
a description of controls to reduce pollutants from these materials including storage
practices to minimize exposure of the materials to storm water,and spill prevention
and response.
Timing, schedules, and sequence of development including clearing, snipping,
rough grading,construction,final grading,and vegetative stabilization_
Please submit the necessary items to the Northampton Department of Public Works as soon
as possible to start the application review process. For additional information contact Doug
McDonald at 413-587-1582 x308 or e-mail at dmcdonald@nohodpw.org.