Loading...
38B-006 (92) The Pike Company, Inc. MEETING MINUTES 2 Penn Plaza No. SM017 Suite 1500 New York,NY 10121 Phone: (413)585-2440 Fax:(212)269-4568 PROJECT TITLE: Smith College Co-Gen LOCATION: Smith College Con£ Rm MEETING DATE: October 25, 2007 SUBJECT: Subcontractor Status Meeting „ V77 . J � / AF 1 T Darren Bentley Abington Group Don Leavitt Jr. Abington Group Sean Bent Abington Group Barry Hi ins Collins ElectricCOLLINS BH Herm Ha eman Collins Electric COI-I INS HH Jeff Bean MJi Moran Mechanical Contractors MTM JB Gaa Hartwell S `th Col le e PC GIq David Perkins ompany,Inc. PIKE DP David M. Crudo Th' Pike Company, Inc. PIKE T) C Bill Donald va elm Engineers V7 RD F Abington 00001 A. Setting remaining HRSG pieces next week,crane scheduled OPN PIKE DP for setup this Friday. B.Working on control room and handrails.Handrails need to be painted yellow per the college direction. stn C. Change sheetrock to metal under the stairs-RFI was rejected by vanZelm, continue with sheetrock as shown on the drawings. OCT 201 D. Clean up misc. debris in basement. (OLD) E.Hydro of package boiler is scheduled for the 25th,Abington to schedule Al. P` r *Need 70-120 degree water,test at 375 degrees *Want to fill 1-2 days prior to hydro,water source fdom boilers 4 and 5 F. Door on side of the HRSG with the steam lines on the oil pumps,Pike to look at corrective action. (OLD) G.Per Smith College add fiberglass sound insulation in the control room walls and ceiling.NO Rock wool. Change order to follow. Form 22f Page 1 of 3 ---i— -A_ % The Pike Company, Inc. MEETING MINUTES 2 Penn Plaza No. SM017 Suite 1500 New York,NY 10121 Phone: (413)585-2440 Fax:(212)269-4568 , sTA a� E ►�, ;. c MJ Moran - Piping, Misc. 00002 A. Mounting plate for the opacity monitor does not have a OPN PIKE DP weather hood.ABLE to send CO. B. OK to furnish and install 3"fiberglass insulation,starting today. C. MJM is responsible to ensure Solar breeching is cleaned per Solar specs prior to installation.Kleeburg is taking back to the shop today to clean and weather seal. D.MJ Moran to change existing vent per state inspector. E.Working on extra air piping and soot blower steam.FGR duct to be insulated first. Collins-Electric 00003 A.Need fire alarm narrative and sketch. (OLD) OPN PIKE DP B.Need vz/fire dept.to walk through to determine lighting/ strobes,pull stations,heat detectors,etc....System to be restored to original condition?Per vanZelm,Phil Sherman,restore the fire alarm system back to the original condition. Smith to follow up with vanZelm. C. Some items are backed up on the boiler 3 generator and:some are not.vZ/Smith/Pike/Collins to review. D.Underground wiring is all pulled,high voltage testing being scheduled. E.Factory test on Russ Electric gear changed to 10-26. F.BOP panel from ABLE will be on-site by the end of the month. Need location,RFI to vanZelm. G.Working on fire alarm controls for boiler 3,moved the]panel. Simplex said its full and any additions to the system will require a new panel. (OLD) H.Collins stated that ground grid in manholes is unuseable, Smith College(Jack)wants a price to replace everything. Change order pending. (OLD) I. Collins is installing permanent lighting where they can vs. temporary lighting. J.vanZelm to determine the load capability on the generator. K.HPP Panels-current drawing shows there is a neutral in;the panel where the wires are to be fed,there is not.RFI to vanZelm. Form 22f M Page 2 of 3 The Pike Company, Inc. MEETING MINUTES 2 Penn Plaza No. SM017 Suite 1500 New York,NY 10121 Phone: (413)585-2440 Fax:(212)269-4568 General 00004 A. Smith/Pike to review instrumentation-control issues.:Need OPN O&M manuals from ABLE.(OLD) B. Smith College wants: (OLD) *Alternate steam source for soot blower steam supply *Re-Design of valve arrangement for soot blowers(will affect boiler hydro) *Use scavenge air for sightglass supply and soot blowers-In Progress *Temp lighting as needed for plant operations C.Pike to coordinate schedules for installation and start up with CA. These minutes are intended to be an accurate representation of the discussions held at the indicated meeting. If you note any discrepancies,please notify sender within 24 hours with comments or changes. Otherwise,parties are to proceed accordingly. Prepared By: The Pike Company, Inc. Signed: David Perkins Dated: 25-Oct-07 Expedition L Form 22f Page 3 of 3