32A-153 (23) -2- Item# DESCRIPTION ACTION BY 8.6 Excavation: R. Weber also noted that their engineer specifically says that the excavation Weber shall be done incrementally and not all at once. D. Clark will review this with the shoring contractor. 10/18: D. Clark noted that the report says that incremental excavation might be required, not necessarily. 13.1 Garage doors: M. Sissman should review the shop drawing submittal for the garage Sissman/ doors. Gillen 11/22: This must be done soon. 12/13: Sissman will review the shop drawing submitted to see if it is acceptable as an equal to the door specified. Doors submitted are not by Designer Doors which are so- named on the elevations. Gillen and Sissman will determine if the submission meets the Specifications. 13.4 Excavation is scheduled to begin 11/18/02. FYI 11/22: Will begin 11/25/02. 12/6: Piles will be driven for the shoring on 12/1-0/02 12/13: Excavation will begin after the piles are finished and probably not until January since Dietz shuts down between Christmas and New Year's. 14.2 Granite: We requested granite submissions from Chabot. Should be a blue gray granite. Chabot 14.4 Greenfield Glass: I will be happy to meet with Greenfield Glass to review their shop FYI drawings before they resubmit. 12/6: Maybe next week. 12/13: Maybe next week. NEW BUSINESS 16.1 Work done last week: Piles for the shoring are about half done. FYI 16.2 The building's new corner has been located by the surveyor: approx. 2-1/4" south of the FYI northwest property corner. The building ends 3' north of the southwest property line. It is setback 4" from the Strong Ave. line. 16.3 Electric strike: Shop drawing was approved. Clark noted that he will provide adequate FYI blocking, as required, so as to be able to house the electric strike in the wood frame. 16.4 Three sample brick panels were on the job, one reported to be a different brick. Is a credit Chabot offered for this different brick? The sample panel has very heavy joints resulting in a 3 in 8"brick coursing which results in a 5/8"joint in places. We want a joint not to exceed 3/8". Should be 3 in 7-1/2". 16.5 In accordance with Specifications 03300, par. 1.06B, a qualified testing agency for testing FYI and inspection shall be paid directly by the owner. B. Gillen will contact Allied Testing to provide the concrete testing. M. Sissman should note the testing will be an expense directly to the owner. One test per 50 cu. yds. is a state code requirement. 16.6 I approved and signed Pay Requisition No. 3 ($56,793). This represents work completed to FYI date at 11%. 16.7 Next meeting: 10:00 a.m., December 20, 2002, at the site. FYI William V. Gillen RJ;2026\Mtg 16 Email: Michael G. Sissman (Owner), David Clark,Pete Juliak(Western Builders), Bill Hagen (Foley &Buhl), Richard Weber(Weber Engineering),Kathy Ford (Ford Gillen) FORD GILLEN ARCHITECTS,, 409 Main Street Amherst,MA 01002 Tel 413-253-2528 Fax 413-256-1553 MEETING NO. 16 fgaoffice@fordgillen.com Kathleen E.Ford,AIA William V. Gillen,AIA RE: 10 Strong Avenue PRESENT: Dave Clark(Western Builders),Michael G. Sissman(Owner), Bill Gillen (Ford Gillen) DATE: 12/13/02 JOB NO.: 2026 Item# DESCRIPTION ACTION OLD BUSINESS BY 1.15 Mass Electric: FYI 10/18: Getting in touch with B. Nestor and getting him to do his work is getting to be a real problem, says D. Clark. 10/25: Shoring is expected to be installed by Monday,Nov. 4, 2002. The overhead wire poles with cable,phone and Verizon lines will be a major problem, if they are still there. D. Clark is still trying to move Nestor. 11/1: Poles are to be set on Wednesday(11/6/02). Hope the wires will also be moved. 11/8: The poles are being set today. It is hoped the wires will be done by the same team. 11115: Telephone wires have been relocated to new temporary poles. The electric company has been scheduled for relocating the remaining street light wiring next week. 11/22: The street light location is almost finished--not a problem, says D. Clark. 12/6: In progress. 12/13: Still in progress: hand digging out of plastic conduits approx. 4' below the surface with the idea of hanging them up or moving them over and not relocating them. 2.6 Financing: FYI 10/18: Expected shortly. 11/1: M. Sissman has brought in two additional partners. He expects the bank to approve his loan 11/6/02. 11/8: Next week. 11/15: Construction financing loan approved by E'ton Savings Bank. Closing is 12/15/02. 11/22: Financing is on schedule. 12/13: Financing is scheduled to close 12/19/02. 2.7 Upgrade of electric capacity: Sissman 10/18: Awaiting a quote from Buster since 9/4/02. 11/8: Will be in the mail. D. Clark says that it includes panel boards which should not be in there. Ignore the number; he'll have it refigured by Buster. 11115: Quotes from Buster to increase the 200 amp service for the residential is $2,881. Amount to increase the retail is $6,074. Clark said that a decision must be made by 1/1/03. This is now in Sissman's court to make a decision. 12/13: Decision is needed by 2/1/03. 5.1 Sprinkler drawings: D. Clark asked for a copy of the sprinkler for coordination purposes. Sissman 10/2: D. Clark has the sprinkler drawings, however, M. Sissman would like to convert from a dry to a wet system. This will save money and space. 11/8: We may possibly maintain the wet system&provide adequate heat in the garage & the building to have a wet system not a dry one. Sissman will find out what the estimate would be for a dry system so this can be compared to the heating expense of the garage. 3aW -/s3 Ford Gillen Architects, inc. 409 Main Street Amherst, MA 01002 Tel 413-253-2528 Fax 413-256-1553 fgaoff ice @ford;illen.com CONTROLLED CONSTRUCTION REPORT NO. 1 Kathleen E. Ford William V.Gillen RE: 10 Strong Ave. DATE: 12/13/02 JOB NO.: 2026 1. Work ongoing: a. Hand excavating and relocating telephone and cable wiring underneath the sidewalk to get it out of the way of the shoring piles. b. Piles are being driven--about half complete. 2. Shoring will be completed the end of this week, however, excavation will not begin until January. 3. For additional information see notes of Meeting#16, attached. 4. The work appears to be in order and in conformance with the plans and specifications. William V. Gillen RJ;2026\Control 1 cc: Tony Patillo (Building Commissioner) Dave Clark(Western Builders) Michael G. Sissman(Owner) Ford Gillen Architects, inc. 409 Main Street Amherst,MA 01002 Tel 413-253-2528 Fax 413-256-1553 fgaoffice@fordgillen.com Kathleen E.Ford William V.Gillen May 2, 2002 RE: Clarifications to Planning Board Application For Site Plan Review Strong Avenue Block Northampton MA 01030 1. Storm Drainage: Roof drainage (interior roof leaders) and foundation drainage collect in a storm line leaving the building in an 8" storm drain(shown on dwg. P.1)and gravity fed into an existing 60"city storm line located in the street. It has been documented in a geo-technical report prepared for this project that the water table has been consistently lower that the proposed basement level, indicating minimal, if ever,need for foundation drainage. 2. Landscaping: Existing trees and shrubs not located in the proposed footprint of the building will remain and be protected during construction. Three (3)new 3" caliper Little Leaf Linden trees will be located in the tree belt at the front of the building. Other landscaping consists of a grassed area at the south side of the building and an 18"wide 3/4" stone border along the entire east side of the building. 3. Site Lighting: Drawing E.l shows specifications for the following site lighting: - Front(west)of building shows five (5)new fixtures as per city street lighting standard (fixture specification on E.2). - Back(east) of building along Nagle walkway shows three(3) existing decorative street light fixtures to remain& one (1)new utility pole for walkway light with Meco flood light. - Individual fixtures shown at back door locations will be in keeping with the historic character of the city's existing decorative lighting. 4. Parking: A total of 13 parking spaces are required(7.06 for retail and 6 for residential). 5 new garage spaces are provided as per recommendations provided by Fuss&O'Neill Inc. (report attached). Owner intends to provide payment in lieu of the additional 8 spaces required. 5. Open Space Calculation: 5%open space is required, and 5.5% is provided. Open space will consist of the grassed area to the south of the building and a portion of the 18"wide stone border at the east side of the building. 6. Sidewalk: New curb and sidewalk are proposed to be granite, concrete and brick as per city specifications. To: The Building Dept. Northampton, MA From: The Strong Block Partners, LLP Re: The Building Permit for Unit 14-30 Strong Ave. (5 retail units). - Expressly concerning the bathrooms therein. Dear Sirs, Commercial and retail spaces that provide public toilet rooms must provide accessible toilet rooms. The retail shops at The Strong Block will not provide public toilet rooms. If a tenant desires to provide a public toilet room(s), or if a tenant is required to provide a public toilet room(s), then the existing toilet room will be rebuilt to accommodate Handicapped Access and comply with CMR 521, the state handicap code. The Strong Block Condominium Association excludes restaurant or food use as tenants. It is expected that none of the retail tenants will provide public restrooms. Thank you, _0,;4 kchael Sissman Managing partner— Strong Block Partners, LLP J N a N Cr.4AD LAJ R ►J � � ® , � MWe 3r V) �u Go 4z LLJ LJ Li = x U 1 tTi ► y ce La O m _ CO�C O a W 0 N G G XL, U cl- W M N W U ec O WC �Y a- ^ cu C / 8 ^C3 M 'f 1ff fD 1" CO Me Q O � M Rai CITY OF NORTHAMPTON DEPARTMENT OF PUBLIC WORKS DIVISION OF WATER SUPPLY APPLICATION FOR INSTALLATION BACKFLOW PREVENTION DEVICE DESIGN DATA SHEET I, Owner's Name Z t lI .f ;5' G Address y��' •; 4:�? ,f"' ,r1? �,�,2tr'%�':2�L � Telephone No. 11. FACILITY (a) Name — (b) Address — (c) Contact Person/Agent (d) Telephone No. of facility contact pe!•son �; " (e) New Facility iL� l7✓ _Existing Facility General description for the need of the installation of'a backflow device lit. DEVICE DATA (a) Manufacturer Name_._ Model No. (b) RPBP or Double Check Valves (c) Hot or Cold Water Unit _By-pass Arrangement: Yes or No--Z,— (d) Exact Location of Devices ✓ (e) Water Usage Down Stream of Device (f) Gate Valve -efl ' Ball Valve Butterfly Valve X, IV. PLANS AND SPARE PARTS REQUIRED I. The installation contractor is responsible fir supplying a spate rubberparts kit fQr each device 2, A fully labeled, detailed schematic of the potable and non-potable water piping immediately surrounding the backflow prevention device installation showing: (a.) height above floor of the device (h.) distance from wall of the device (c.) type of chemical(s) used (if-Lny) and the type of equipment upstream, and downstream of the device Please note: The schematic drawing must lie at least 8 1/2 by 1 I inches with the following information in the g9 1n eted t; CIS• Submitted by: � Plumber's Signature: �� - Plumber's License N: Owner/Agent Signature: /W Date: , -'/_ej'y All Information listed above must be Included on schematic drawing. In addition, a fee of 565.00. made payable to city of Northampton for each device application must be submitted to the P.P.W. b lication will be processed. A permit from the plumbing inspector may he necessary for the installation of these devices. Aff 9. All water lines shall be color coded according to the State plumbing code, except that water filtration plants, pumping stations, sewage treatment plants and sewage pumping stations shall label all water lines in lieu of color coding. In addition, the City of Northampton Department of Public Works requires that the installation be completed within sixty(60)days after the receipt of this letter. Following installation,you must contact this office to make arrangements for the initial inspection and test. A permit from the Northampton Plumbing Inspector is necessary for the installation of each device. As the owner of this cross connection,you must be aware of the importance of maintaining these device(s). Unprotected cross connections can and have resulted in the loss of water supply and public health damage. You are responsible for compliance with Massachusetts Drinking Water Regulations, 310 CMR 22.0. Failure to take any action deemed appropriate by the Department of Environmental Protection or its designee, City of Northampton Department of Public Works or otherwise failure to remain in compliance in the future with the applicable requirements, could subject you to legal action including, but not limited to, criminal prosecution, court-imposed civil penalties or civil administrative penalties. A civil administrative penalty may be assessed by the Department of Environmental Protection for each day you are in noncomplinace with the requirement referred to above. If you have any questions regarding this decision, please contact the City of Northampton Department of Public Works at 587-1570. Very,truly yours, l p George Andrikidis, P.E. Director of Public Works CITY Or NORTHAMPTON, MASSACHUSETTS DEPARTMENT OF PUBLIC WORKS 125 LOCUST STREET { r€ NORTHAMPTON, MA 01060 413-587-1570 FAX 413-587-1576 George Andrikidis, P.E. Direclor gfPuhlie 1l urks 2/18/2004 Strong Avenue Block 134 South Street Northampton, MA 01060 Attn. Strong Block Partners, LLP Re: PROPOSED CROSS CONNECTION INSTALLATION The City of Northampton Department of Public Works has reviewed your application and plan for the proposed cross connection installations. The information submitted is attached at the end of this notice. In accordance with Chapter 111, Section 160A of Massachusetts General Laws and 310 CMR 22.22 of the Massachusetts Drinking Water Regulations, the City, hereby grants approval for the installation with the following provisions: 1. Drinking and domestic water lines, lines for safety showers, and lines for eyewash units must be taken off the upstream side of the backflow preventer for devices installed as in-plant protection. 2. The backflow preventer shall be located so as to permit easy access and provide adequate and convenient space for maintenance, inspection and testing. 3. Tightly closing valves must be installed at each end of the device. 4. The device must be protected from freezing, flooding and mechanical damage. 5. The owner or owner's agent must maintain a spare parts kit and any special tools required for removal and re- assembly of the device. 6. The owner or owner's agent must provide the necessary labor to assist the City or its Agent in the inspection and testing of the installed device. 7. The owner of the device shall be able to shut down water lines after reasonable notice during normal business hours to permit necessary testing and maintenance of the device. If it is not possible to meet this requirement,a by-pass line equipped with an approved type of backflow preventer shall be installed. 8. Any reduced pressure backflow preventer or double check valve assembly and shut-off valves must be installed in horizontal alignment between three and four feet from the floor and a minimum of twelve inches from any wall. If a reduced pressure backflow preventer is to be installed on a hot water line, a device approved for use at the elevated temperature must be used. FROM FORD GILLEN ARCHITECTS FAX NO. : 413 256 1553 Mar. 13 2003 03:55AM P7 ALLIED TESTING LABORATORIES, INC. 115 St.George Road • Springfield, Massachusetts 01 104 Phone:(413) 736-1846 Fax.(413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL_CONCRETE SPECIMENS —ASTM C39 REPORT NO: 6 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Footing, 6 Line, A Line, B Line 6-11 REPORTED TO: Michael G. Sissman DATE: 2/28/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Its) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO_ U-230 U-231 U-232 U-233 Specimen No. A B C D Slump (in) 411 Entrained Air Content (96) 4.8' Concrete Temp, 58°F Date Sampled 1131/03 1/31/03 1/31/03 1/31/03 Date Received 2/3/03 2/3/03 2/3/03 2/3/03 Date Tested 217/03 2/28/03 2/28/03 2/28/03 Age at Test (days) 7 28 28 28 Dimensions (in) 6x12 6x12 6x12 6x12 Area (sq in) 28.3 28.3 28.3 28.3 Wgt. of Specimen (lbs) 30.0 30.1 30.0 30.1 Total Load (Ibs) 64,980 113,025 105,145 107,540 COMPRESSIVE STRENGTH (psi) 2300 3990 3720 3800 Remarks. Respectfully submitted, ALLIED TESTING LxABORATORIES, INC. Copy: By: Chester V. Dawicki FROM : FORD GILLEN ARCHITECTS FAX NO. : 413 256 1553 Mar. 13 2003 03:55AM P6 ALLIED TESTING LABORATORIES, INC. 115 St.George; Road a Springfield,Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS—ASTM C39 REPORT NO: 5 CLIENT: Michael G. Sissman PROJECT. 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Footing, I- Line, 11-6 REPORTED TO: Michael G. Sissman DATE: 2/27/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (lbs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-226 0-227 U-228 U-229 Specimen No. A B C D Slump (in) 4" Entrained Air Content (%) 4.7% Concrete Temp_ 590F Date Sampled 1/30/03 1/30/03 1/30/03 1/30/03 Date Received 1/31/03 1/31/03 1/31/03 1/31/03 Date Tested 2/6/03 2/27/03 2/27/03 2/27/03 Age at Test (days) 7 28 28 28 Dimensions (in) 6x12 6x12 6x12 6x12 Area (sq in) 28.3 28.3 28.3 28.3 Wgt. of Specimen (Ibs) 28.2 28.3 28.4 28.3 Total Load (Ibs) 78,720 111,975 115,415 104,710 COMPRESSIVE STRENGTH (psi) 2780 3960 4080 3700 Remarks. Respectfully submitted, ALLIED TESTING 17SABORATORIES, INC. Copy: 4" ,(//J By- Chester V. Dawicki FROM FORD GILLEN ARCHITECTS FAX NO. : 413 256 1553 Mar. 13 2003 03:55AM P5 ALLIED TESTING LABORATORIES, INC. 1 15 St,George Road 9 Springfield.Massachusetts 01 104 Phone: (4 13) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS—ASTM C39 REPORT NO_ 4 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT:Footing-Line A, 1-4; Line A-E, 1-3; Line E, 1-3 REPORTED TO: Michael G. Sissman DATE: 2/18/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement t ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-329 Specimen No. A Slump (in) 411 Entrained Air Content M 5.5% Concrete Temp. 61°F Date Sampled 2110/03 Date Received 2/11/03 Date Tested 2/18/03 Age at Test (days) 8 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 30.3 Total Load (Ibs) 78,785 COMPRESSIVE STRENGTH (psi) 2790 Remarks. Respectfully submitted, ALLIED TESTING BORATORIES, INC. Copy: By- Chester V. Dawicki FROM : FORD GILLEN ARCHITECTS FAX NO. : 413 256 1553 Mar. 13 2003 03:54RM P4 ALLIED TESTING LABORATORIES, INC. I 15 St.George Road • Springfield,Massachusetts 01 104 Phone: (413) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS-ASTM C39 REPORT NO- 3 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT Footing-Lines O • s5-4, B-E; Line E, 6-3.1 REPORTED TO' Michael G. Sissman GATE: 2/12/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement. (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. u-274 Specimen No. --� Slump (in) 3 1/2" Entrained Air Content N Concrete Temp. 56°F Date Sampled 2/5/03 Date Received 2/6/03 Date Tested 2/12/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 30.4 Total Load (Ibs) 71,240 COMPRESSIVE STRENGTH (psi) 2520 Remarks Respectfully submitted. ALLIED TESTING LhBORATORIES, INC. ��Lf�L.ld Copy: By: Chester V. Dawick► FROM FORD GILLEN ARCHITECTS FAX NO. : 413 256 1553 Mar. 13 2003 03:54AM P3 ALLIED TESTING LABORATORIES, INC. I I S St.George Road • Springfield,Massachusetts 01 104 Phone: (4 13) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS— ASTM C39 REPORT NO: 2 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block. Northampton, MA LOCATION OF CONCRETE PLACEMENT: Footing, 6 Line, A Line, B Line 6-11 REPORTED TO: Michael G. Sissman DATE: 2/7/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard ._ ....._::....,;,_ .;..;:Cement (lbs Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-230 Specimen No. A Slump (in) 41 Entrained Air Content M 4.8% Concrete Temp. 58°F Date Sampled 1/31103 Date Received 2/3103 Date Tested 2/7/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 30.0 Total Load (lbs) 64,980 COMPRESSIVE STRENGTH (psi) 2300 Remarks. Respectfully submitted, ALLIED TESTING WORATORIES, INC. Copy: 4 By: Chester V_ Dawicki FROM FORD GILLEN ARCHITECTS FAX N0. : 413 256 1553 Mar. 13 2003 03:53AM P2 ALLIED TESTING LABORATORIES, INC. I IS St George Road e Springfield,Massachusetts 01 104 Phone:(413) 736-1846 Fax*(413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS— ASTM C39 REPORT NO: 1 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Footing, E Line, 11-6 REPORTED TO: Michael G. Sissman DATE: 2/6/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) i Coarse Aggregate (Ibs) Water (gals) n 2Cr' Admixture (oz) LABORATORY NO. U-226 Specimen No. A Slump (in) 4" Entrained Air Content (°i6) 4.7% Concrete Temp. 590F Date Sampled 1/30/03 Date Received 1/31/03 Date Tested 2/6/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt.of Specimen (Ibs) 28.2 Total Load (Ibs) 78,720 COMPRESSIVE STRENGTH (psi) 2780 Remarks. Respectfully submitted, ALLIED TESTING 12.ABORATORIES, INC. Copy: By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 23 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, Line 6 REPORTED TO: Michael G. Sissman DATE: 4/28/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. W-203 Specimen No. A Slump (in) 4 1/4" Entrained Air Content (%) 5.17. E �r,'s - U Concrete Temp. 70°F - Date Sampled 4/21/03 Date Received 4/22/03 Date Tested 4/28/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 30.0 Total Load (Ibs) 73,590 COMPRESSIVE STRENGTH (psi) 2600 Remarks. Respectfully submitted, ALLIED TESTING BORATORIES, INC. Copy: Mr. Dave Clark, Western Builders Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 115 St.George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS —ASTM C39 REPORT NO: 22 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, Line 3.2-4.2, A Line REPORTED TO: Michael G. Sissman DATE: 4/25/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) - Fine Aggregate (Ibs) Coarse Aggregate (Ibs) h� ti� _ I Water (gals) Admixture (oz) LABORATORY NO. U-752 U-753 U-754 U-755 Specimen No. A B C D Slump (in) 4" Entrained Air Content (%) 4.8% Concrete Temp. 68°F Date Sampled 3/28/03 3/28/03 3/28/03 3/28/03 Date Received 3/31/03 3/31/03 3/31/03 3/31/03 Date Tested 4/4/03 4/25/03 4/25/03 4/25/03 Age at Test (days) 7 28 28 28 Dimensions (in) 6x12 6x12 6x12 6x12 Area (sq in) 28.3 28.3 28.3 28.3 Wgt. of Specimen (Ibs) 29.5 29.4 29.5 29.4 Total Load (Ibs) 57,510 93,225 97,625 89,480 COMPRESSIVE STRENGTH (psi) 2030 3300 3450 3160 Remarks. Respectfully submitted, ALLIED TESTING L.ABORATORIES, INC. Z"Co PY:Mr. Dave Clark, Western Builders v Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 21 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Walls Line 2, Line 4, Line E 3.2-4.2 REPORTED TO: Michael G. Sissman DATE: 4/24/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) MA Y c3 Water (gals) �vnLj Admixture (oz) LABORATORY NO. W-166 Specimen No. A Slump (in) 4" Entrained Air Content (%) 4.7% Concrete Temp. 66°F Date Sampled 4/17/03 Date Received 4/18/03 Date Tested 4/24/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 29.8 Total Load (Ibs) 72,455 COMPRESSIVE STRENGTH (psi) 2560 Remarks. Respectfully submitted, ALLIED TESTING LAABORATOR IES, INC. e+ Copy: Mr. Dave Clark, Western Builders Mr. Bill Hagen, Foley S Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St.George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 20 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Walls, B Line REPORTED TO: Michael G. Sissman DATE: 4/22/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (fbs) Fine Aggregate (Ibs) . Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-652 U-653 U-654 U-655 Specimen No. A B C D Slump (in) 4" Entrained Air Content (%) 5.4% Concrete Temp. 67°F Date Sampled 3/25/03 3/25/03 3/25/03 3/25/03 Date Received 3/26/03 3/26/03 3/26/03 3/26/03 Date Tested 4/1/03 4/22/03 4/22/03 4/22/03 Age at Test (days) 7 28 28 28 Dimensions (in) 6x12 6x12 6x12 6x12 Area (sq in) 28.3 28.3 28.3 28.3 Wgt. of Specimen (Ibs) 30.0 29.9 29.8 29.9 Total Load (Ibs) 65,680 89,000 86,375 94,840 COMPRESSIVE STRENGTH (psi) 2320 3150 3060 3350 Remarks. Respectfully submitted, ALLIED TESTING BORATORIES, INC. Copy: Mr. Dave Clark, Western Builders Lath k 4.z- Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 19 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, Lines 1 & 3, E 2.5-3.5 and Line E, 1-1.5 REPORTED TO:Michael G. Sissman DATE: 4/21/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. W-032 Specimen No. A Slump (in) 4 1/4" Entrained Air Content N) 5.1% Concrete Temp. 65°F ry Date Sampled 4/14/03 Date Received 4/15/03 Date Tested 4/21/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28,3 Wgt. of Specimen (Ibs) 28.2 Total Load (Ibs) 80,625 COMPRESSIVE STRENGTH (psi) 2850 Remarks. Respectfully submitted, ALLIED 1 TESTING BORATORIES, INC. Copy:Mr. Dave Clark, Western Builders L,A 4 v Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 18 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, Line B, 7-10 and Wing Wall, Line 8.5 REPORTED TO: Michael G. Sissman DATE: 4/17/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Yes Coarse Aggregate Ibs '''�Y' ( ) � „�s - 9 Cui33; Water (gals) Admixture (oz) LABORATORY NO. U-602 U-603 U-604 U-605 Specimen No. A B C D Slump (in) 4 1/4" Entrained Air Content N) 4.9% Concrete Temp. 63°F Date Sampled 3/20/03 3/20/03 3/20/03 3/20/03 Date Received 3/21/03 3/21/03 3/21/03 3/21/03 Date Tested 3/27/03 4/17/03 4/17/03 4/17/03 Age at Test (days) 7 28 28 28 Dimensions (in) 6x12 6x12 6x12 6x12 Area (sq in) 28.3 28.3 28.3 28.3 Wgt. of Specimen (Ibs) 29.5 29.4 29.5 29.3 Total Load (Ibs) 70,125 97,960 99,035 91,850 COMPRESSIVE STRENGTH (psi) 2480 3460 3500 3250 Remarks. Respectfully submitted, ALLIED TESTING BO. R�ATORIES, INC. Copy: Mr. Dave Clark, Western Builders Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 17 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Walls, A Line, 1-2.3 REPORTED TO: Michael G. Sissman DATE: 4/14/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) = Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) ' Admixture (oz) LABORATORY NO. U-923 Specimen No. A Slump (in) 4" Entrained Air Content N) 5.1% Concrete Temp. 61°F Date Sampled 4/7/03 Date Received 4/8/03 Date Tested 4/14/03 A 1% e at Test (uu'yS) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 29.4 Total Load (Ibs) 59,505 COMPRESSIVE STRENGTH (psi) 2100 Remarks. Respectfully submitted, ALLIED TESTING LABORATORIES, INC. Copy: Mr. Dave Clark, Western Builders �: v A.un* i Mr. Bill Hagen, Foley & Buhl Sy: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 16 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, B Line South of 6 Line and 21' of A Line North of 6 Line REPORTED TO: Michael G. Sissman DATE: 4/14/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement Obs) Fine Aggregate (Ibs) ' y w Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-582 U-583 U-584 U-585 Specimen No. A B C D Slump (in) 3 3/4" Entrained Air Content (%) 5.17. Concrete Temp. 68°F Date Sampled 3/17/03 3/17/03 3/17/03 3/17/03 Date Received 3/18/03 3/18/03 3/18/03 3/18/03 Date Tested 3/24/03 4/14/03 4/14/03 4/14/03 Age at Test (days) 7 28 28 28 Dimensions (in) 6x12 6x12 6x12 6x12 Area (sq in) 28.3 28.3 28.3 28.3 Wgt. of Specimen (Ibs) 29.5 29.4 29.4 29.5 Total Load (Ibs) 65,405 90,395 92,720 95,795 COMPRESSIVE STRENGTH (psi) 2310 3190 3280 3390 Remarks. Respectfully submitted, ALLIED TESTING BORATORIES, INC. Copy: Mr. Dave Clark, Western Builders 1A v Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 115 St. George Road . Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 15 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall REPORTED TO: Michael G. Sissman DATE: 4/9/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) v t Admixture (oz) � MAY - 9 2 uC3 LABORATORY NO. U-850 �Jni.J UILLLEV �1�Vi�I 1 L� i •�; Specimen No. A Slump (in) 5" Entrained Air Content N) 5.57 Concrete Temp. 64°F Date Sampled 4/2/03 Date Received 4/3/03 Date Tested 4/9/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 28.0 Total Load (Ibs) 61,015 COMPRESSIVE STRENGTH (psi) 2160 Remarks. Respectfully submitted, ALLIED TESTING BORATORIES, INC. Mr. Dave Clark Western Builders !�• ' Copy: � L� � Mr. Bill Hagen, Foley & Buhl Bye Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 14 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: South Wall and 1/2 East Wall REPORTED TO: Michael G. Sissman DATE: 4/9/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) MAY - 9 2G 00 3 Water (gals) gnu ui�t,civ nr;v 1 e„ Admixture (oz) LABORATORY NO. U-558 U-559 U-560 U-561 Specimen No. A B C D Slump (in) 3 1/2" Entrained Air Content M 5.27. Concrete Temp. 60°F Date Sampled 3/12/03 3/12/03 3/12/03 3/12/03 Date Received 3/14/03 3/14/03 3/14/03 3/14/03 Date Tested 3/19/03 4/9/03 4/9/03 4/9/03 Age at Test (days) 7 28 28 28 Dimensions (in) 6x12 6x12 6x12 6x12 Area (sq in) 28.3 28.3 28.3 28.3 Wgt. of Specimen (Ibs) 29.9 29.7 29.8 29.8 Total Load (Ibs) 58,215 84,895 85,355 85,740 COMPRESSIVE STRENGTH (psi) 2060 3000 3020 3030 Remarks. Respectfully submitted, ALLIED TESTING B�O�RA%T ORIES, INC. Co py: Mr. Dave C lark, Wes tern Builders 4u Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki AL'_I ED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 13 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, Line 3.2-4.2, A Line REPORTED TO: Michael G. Sissman DATE: 4/4/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) MAY 260 3 Admixture (oz) LABORATORY NO. U-752 Specimen No. A Slump (in) 4" Entrained Air Content (%) 4.87. Concrete Temp. 68°F Date Sampled 3/28/03 Date Received 3/31/03 Date Tested 4/4/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 29.5 Total Load (Ibs) 57,510 COMPRESSIVE STRENGTH (psi) 2030 Remarks. Respectfully submitted, ALLIED TESTING BORATORIES, INC. - Copy:Mr. Dave Clark, Weste-rn Builders '�`'�!� Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki Ford Gillen Architects, inc. TRANSMITTAL 409 Main street Amherst, MA 01002 Tel 413-253-2528 Fax 4t3-256-1553 DATE: 5/12/03 fgaofficeCfordgillen.com Kathleen E. Ford, AlA William V.Gillen, AlA TO: Dave Clark(Western Builders) Tony Patillo (City of Northampton) Bill Hagen (Foley & Buhl) RE: Sissman - 10 Strong Ave. JOB NO.: 2026 Urgent By Your pickup For Your Quote Under Separate Cover By Express Mail Per Your Request Review and Comment X_By Mail _X For Your Information Other Enclosed: Concrete test reports 13-23 from Allied Testing. V! tvt q tt [lil'+J L William V. Gillen cc: Michael Sissman (transmittal only) ALLIED TESTING LABORATORIES, INC. 1 15 St George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1 846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 12 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Walls, B Line REPORTED TO: Michael G. Sissman DATE: 4/1/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-652 Specimen No. A Slump (in) 4" Entrained Air Content (%) 5.4% Concrete Temp. 67°F Date Sampled 3/25/03 Date Received 3/26/03 Date Tested 4/1/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 30.0 Total Load (Ibs) 65,680 COMPRESSIVE STRENGTH (psi) 2320 Remarks. Respectfully submitted, ALLIED TESTING.� BORATORIES, INC. Copy. Cl Mr. Dave ark Western Builders v Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 11 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, Line B, 7-10 and Wing Wall, Line 8.5 REPORTED TO: Michael G. Sissman DATE: 3/27/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-602 Specimen No. A Slump (in) 4 1/4" Entrained Air Content N) 4.9% Concrete Temp. 63°F Date Sampled 3/20/03 Date Received 3/21/03 Date Tested 3/27/03 Age at Test (days) 7 Dimensions (in) 6x12 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 29.5 Total Load (Ibs) 70,125 COMPRESSIVE STRENGTH (psi) 2480 Remarks. Respectfully submitted, ALLIED TESTING BORATORIES, INC. Copy: Mr. Dave Clark, Western Builders Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (413) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 10 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: Wall, B Line South of 6 Line and 21' of A Line North of 6 Line REPORTED TO: Michael G. Sissman DATE: 3/24/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-582 Specimen No. A Slump (in) 3 3/4" Entrained Air Content (%) 5.1% Concrete Temp. 68°F Date Sampled 3/17/03 Date Received 3/18/03 Date Tested 3/24/03 Age at Test (days) 7 Dimensions (in) 6x!2 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 29.5 Total Load (Ibs) 65,405 COMPRESSIVE STRENGTH (psi) 2310 Remarks. Respectfully submitted, ALLIED TESTING BORA pY TORIES, INC. Co Mr. Dave Clark, Western Builders �/,k Y/ Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki ALLIED TESTING LABORATORIES, INC. 1 15 St. George Road • Springfield, Massachusetts 01 104 Phone: (413) 736-1846 Fax: (4 13) 736-1838 COMPRESSIVE STRENGTH OF CYLINDRICAL CONCRETE SPECIMENS — ASTM C39 REPORT NO: 9 CLIENT: Michael G. Sissman PROJECT: 10 Strong Avenue Block, Northampton, MA LOCATION OF CONCRETE PLACEMENT: South Wall and 1/2 East Wall REPORTED TO: Michael G. Sissman DATE: 3/19/03 CONCRETE CLASS 3000 Mixture Weights per cubic yard Cement (Ibs) Fine Aggregate (Ibs) Coarse Aggregate (Ibs) Water (gals) Admixture (oz) LABORATORY NO. U-558 Specimen No. A Slump (in) 3 1/2" Entrained Air Content (%) 5.2% Concrete Temp. 60°F Date Sampled 3/12/03 Date Received 3/14/03 Date Tested 3/19/03 Age at Test (days) 7 Dimensions (in) 6x!2 Area (sq in) 28.3 Wgt. of Specimen (Ibs) 29.9 Total Load (Ibs) 58,215 COMPRESSIVE STRENGTH (psi) 2060 Remarks. Respectfully submitted, ALLIED TESTING LABORATORIES, INC. Copy: Mr. Dave Clark, Western Builders 1h v Mr. Bill Hagen, Foley & Buhl By: Chester V. Dawicki Ford Gillen Architects, inc. 409 Main Street TRANSMITTAL Amherst,MA 01002 Tel 413-253-2528 Fax 413-256-1553 DATE: 4/14/03 fgaoffice @fordgillen.com Kathleen E.Ford, AIA William V.Gillen,AIA TO: Dave Clark(Western Builders) X Bill Hagen (Foley&Buhl) RE: Sissman - 10 Strong Ave. JOB NO.: 2026 Urgent By Your pickup For Your Quote Under Separate Cover By Express Mail Per Your Request Review and Comment XBy Mail _X For Your Information Other Enclosed: Concrete test reports 9-12 from Allied Testing. „ A D� 1 ^, C3 Gv4G��1�lL, William V. Gillen cc: Michael Sissman(transmittal only) Carlson&Schmitt Architects,Inc. FAX COVER SHEET TO Dan-Bishnp Bay State Realty Col_ (413) 585-8300 Ziter Saloomey -%8400niey ConStwCffcn 013) 2594374 Tony Bilotta Saloomey Construction Anthony Patine NclthamPlOn 131dg.-00m. {413)587-1272 FROM- Kevin Rothschild-Shea RE: Bay State Hotel—Job Meeting 01/30/03 DATE: February 3, 2003 PAGES: 2 f South End Bridge C&de Agawam,Marsachuwtu 0f001 (413)7865556 telephone (4f3)7866130 fax www.carlson-ichmits.com ail 'd 6trb9 oN QE 19 98t llIWH�S ri NOS18VO W�9l Ql SQSc 'E 9a� CSACarlson&Schmitt Architects,inc. Bay State Hotel Job Meeting Notels January 30, 2003 Attendees: Dan Bishop Ziter Saloomey, Saloomey Construction, Inc. Tony Bilotta, SalobMay C-Onsftuobcn,im, Kevin Rothschild-Shea, Carlson & Schmitt Architects, Inc. • Ziter to cart with-meeting time for next weep. • Per owner/contractor meeting with Fire Department and Building Inspector, wall assembly behind range hood to be 5/8" gypsum with stainless steel. • Elevator Shaft Vent — Damper and motor to be above roof line elevation, located within The duet with access panel. -D'=t to extend into shaft (without interfering with elevator clearance), and be equipped with flange to receive roof famlift by roister. • Machine room ceiling height to be confirmed by Baystate Elevator. • Basement floor joist treatment—Darison &Schmitt to outline requirements if any. • Carlson & Schm tttoprocess door schedule. • Interior Trim -` dute drawing A2.2 to serve as -reference for allowance review. Rooms 103, 104 and 105 to receive oak, stain and poly. Rooms 116, 11$and 149 to be-#mch, stain and poly. Second, third and fourth floors to be finger jointed, poplar, paint grade. Dan to indicate if deletion of wood Trim is an option, and exposed metal frame to be painted in lieu of trim. • Carlson & Schmitt to update Bar Elev. drawing and Wine Rack drawing for Saloomey. • First and Second floor, non-accessible bathroom doors reduced to 2'-6" wide. • First floor greaee trap frarfg—double 2x9 2 mar joists at each side and provide double 2x12 header at each end. • Schedule - Dan anxious to layout milestones, Saloomey ready to start gypsum at third floor as suQn as fire protection rough is completed. Brackets at front balconies to be completed before gypsum board can be completed at front side#building. • Dan to meet with color designer to establish finish selections and colors. Cc: Attendees Anthony Patillo, Northampton Building Commissioner 1 South End Bridge Orcle Agawam,ffip-eacbtuette 1X1001 013)786.635btakphone {419)786-&J0Jax sNwwaarLwsec/Hnitt.com ?%G -d 6tt9 *ON H19-98L iiIMS NOSI�a� iVb91 01 E00� 'E .�a8 FROM FORD GILLEN ARCHITECTS FAX NO. 413 256 1553 Mar. 13 2003 03:53RM P1 Fore]. Gillen Architects, lnc. 409 Main Street ,\rnhcr,t,MA 01002 FAX TRANSMITTAL Tel C3-253-2528 Fax 413-256 1553 f gaof f icei;4fnrdgillc n.com Kathleen E.Gerd DATE: 3/12/03 William v Gillen TO: Dave Clark(Western Builders) Tony Patillo(City of Northampton) Bill Hagen(Foley&Buhl) Re: 10 Strong Ave. JOB NO. 2026 7 sheets including this cover sheet Enclosed: Concrete test reports 1-6 from Allied Testing. 1 W J4 William V.Gillen cc: Michael Sissman --N au uG uo: L Ia Lrw 41Jb8715'/6 P. 4 Permit No. A13-03 Conditions: Driveway Permit In lieu of plan approved by City Engineer I agree to the following added conditions: 1. I will contact the Department of Public Works and have an inspector check and approve the graded gravel base prior to paving to insure compliance with slope and location; 2. I further agree that if in the inspections any of the permit conditions are not met that 1 will at no expense to the City remove and replace the driveway as directed by the City Engineer. By: `D .J Petitioner 73 Pleasant Street, P.O. Box 278 Granby, MA 01033 4L3-467-9171 Fact 14 Note: The Public Works Department recommends that you provide a plan showing the proposed driveway with grades and location in the future to avoid possible expense which you will incur by not getting approval of actual plans in advance. cc: Buildint, Inspector arp+ iu uc uO: I Ia urw g135t1 t15 lb P. j ' OF NORTHAMPTON UNION STATION ?582, PAGE 243 BANQUET ROOM shrubs orb or to he ro FONT. ON P.2 00 1 ON 2. P. � Lr P2 stairway $ bit. cone. qq I t / ire to 411. LENA W util ever a ) v� RIM-127.15' edge of pc —PROS V. OUT=123.12' 0 gran. c L LEVEL it R.C.P.) a"s. a'sa. riN m 0t 11 _ p - DW I $R&D. 1' A RfM r ^H=111 . RIM=127.59' =127.18' Sep I ue uj: iva urw '4 1 aZ)tJtI5Ib p. Permit No. D13-03 CITY OF NORTHAMPTON, MA DRIVEWAY PERMIT Date: oS_3o_0 FEE. $25.00 CHECK#: 30845 THE BOARD OF PUBLIC WORKS The undersigned respectfully petitions your honorable body for: ID S E P - 9 2002 Permission to install a driveway at 10 Strong Avenue DEPT OF BUILDING INSPECTIONS 50 Feet Maxtmum PL O.O6G maximum width at the street line. Gutter drainage not to be disturbed. All drainage shall be directed off the driveway surface to adTacent land and not on the existing roadway. Driveway surface to be paved if the grade of the proposed driveway exceeds 3� or more. By: a � V . Ft,«atPs 73 Pleasant Street P.O. Box 278 Granby, MA 01033 Telephone#: t t.;� — `f(. -7 T Y/ 7/ r . 5/ Proposed Location c CC(- 9/-3- 4A7 —56!;-41 Inspected By: �� C,7,&h-- Cv,6sPrd h/eati�� Gravel Base Grade Inspected By: Final Approval THE BOARD OF PUBLIC WORKS voted that petition be granted. George Andrikidis Director of Public Works (SUBJECT TO ATTACHED CONDITION 1 &2) cc: Building Inspector MUNICIPAL SEWER AVAILABILITY + Northampton Streets Department 125 Locust Street Northampton, MA 01060 r 587-1570 Location: 10 Strong Avenue Inquiry Made By: David Clark 413-467-9171 Date of Inquiry: 08-30-02 Municipal Sewer Main in Front of Location: Yes x No Size of Sewer Main: 8" Material: PVC Age: 1991 Depth of Sewer Main: @ 4 feet Size of Service Connection: Unknown Comments: A corresponding"sewer entrance fee" shall be paid prior to making any connection to the municipal sewer system. Arrangements of such installation shall be made with the Northampton Streets Department with a minimum of 5 working days notification. All work shall conform to Northampton Streets Department specifications. Joseph Thomas, Superintendent Streets Department M. Ned Huntley, Asst. City Engineer Anthony Patillo, Building Inspector ANNUNCaTOR PANEL SILENT KNIGHT#5230 LOCATED INSIDE FRONT DOOR SMOKE DETECTORS SYSTEMS SENSOR#21005 LOCATED PER PLANS HEAT DETECTOR CHEMTRONICS#601-135 LOCATED IN KITCHEN AREAS MANUAL PULL STATIONS FIRE LITE#BG-12 LOCATED AT ALL EXIT DOORS PER PLAN HORN/STROBES SYSTEM SENSOR#P-251575 LOCATED PER PLANS STROBES SYSTEM SENSOR#S-251575 LOCATED PER PLANS EXTERIOR STROBE SYSTEM SENSOR S-251575K LOCATED PER PLANS KNOX BOX AS REQUIRED NOTE: THIS IS A FOUR STORY COMMERCIAL BUILDING WITH OFFICE SPACE ON FOURTH FLOOR AND RESTAURANT/BAR USE ON THE 1ST,2ND AND THIRD FLOORS. ZONE BREAKDOWN IS AS FOLLOWS: ZONE 1 PULL STATIONS ZONE 2 BSMT SMOKE DET. ZONE 3 1ST FLOOR SMOKE DET. ZONE 4 2ND FLOOR " " ZONE 5 3RD FLOOR " ZONE 6 4TH FLOOR ZONE 7 DUCT SMOKE DET. ZONE S WATER FLOW SWITCH ZONE 9 WATER TAMPER SWITCH ZONE 10 ANSIL SYSTEM BAYSTATE /MULINO'S 41 STRONG AVE. NORTHAMPTON,MA. 01060 THE PROGRAMMING OF THE SILENT KNIGHT SYSTEM: THE #5208-10 ZONE SILENT KNIGHT FIRE ALARM SYSTEM AND ANNUNCIATION IS . AT DEFAULT FOR WORK AND ZONE DESCRIPTION ON THE ANNUNCIATOR WHICH WHEN ANY OF THE FIRE ALARM ZONES TRIP, THE DISPLAY SHALL READ ZONE 1 FOR ZONE 1 AND ZONE 2 FOR ZONE 2, ETC. THE PROGRAMMING OF THE SILENT KNIGHT SYSTEM: THE DIGITAL DIALER BUILT INTO THE SYSTEM DIALS TO THE CENTRAL STATION ON ANY ALARMS AND TROUBLES. THE CENTRAL STATION RESPONDS ACCORDING TO THE INFORMATION PROVIDED BY THE OWNER....FORMAT AND SPEED OF COMMUNICA- TIONS IS 4X2 2300HTZ. THE ZONES AND RELAYS ARE PROGRAMMED FOR PROPER OP- ERATION OF THE SYSTEM. FIRE ALARM DIRECTIONS AND OPERATIONS: THE FIRE ALARM SYSTEM IS A 24 VOLT DC LOW VOLTAGE SYSTEM CONSISTING OF SMOKES DETECTORS, PULLS STATIONS ,HEAT DETECTORS FOR TRIPPING THE SYSTEMS AUDIBLE DEVICES. ZONES 1 - 10, ARE REGULAR INITIATING DEVICES SMOKE DETECTORS, PULL STA- TIONS, HEAT DETECTORS& SPRINKLER FLOW SWITCHE$,AT SUCH TIME OF ALARM AC- TIVATION THEY SHALL TRIP THE MAIN SYSTEM AND CAUSE ALL AUDIBLE DEVICES TO TRIP AND CALL THE NORTHAMPTON FIRE DEPT. TO REPORT SUCH ALARM. TROUBLE, TAMPER AND LOW BATTERY SIGNALS ARE TO BE MONITORED BY A U. L. CENTRAL STA- TION. THE CENTRAL STATION WILL HVIMEDI- ATELY RELAY THIS INFORMATION TO THE OWNER FOR CORRECTIVE ACTION. INSTRUCTIONS TO RESET THE SILENT KNIGHT 5208 IN ALARM MODE, TO SILENCE, GO TO ANNUCIATOR PANEL-PRESS SILENCE THEN ENTER, CODE(#I I I I ) TO RESET THE ALARM ZONE TRIPPED -PRESS RESET ALARM, ENTER, AND (#I I I I ) ANNUNCIATOR SHOULD THEN READ" SYSTEM NORMAL/MEMORY' ?' 4 3. Conduct system operational test ftom Wpddors test connection. Local alarm must sound within 1 minute. 4. Central station must receive alarm and trouble signals. 5. Allstate Fire Sprinkler, Inc. will provide the tost certificates. Section 2 —Equipment and Tools 1. Manufacturer's Instructions. 2. Approved Narrative Report, sequence of operation section. 3. Gauges on the main riser 4. Main system drain. 5. Pipe, fittings and hangers. 6. Inspectors test station 7. Spare sprinkler head cabinet and wrench. Section 3 —Approval Requirements 1. Final approval of the fire sprinkler system will require a satisfactory functional test in accordance with 903.4 and certification by the project engineer that the systems have been installed in accordance with CMR 903.3. Section 4—FIRE PROTECTION SYSTEMS TO BE INSTALLEIP a. New six-inch underground main for the sprinkler sy&tom, b. Automatic sprinkler systems and components. c. Fire alarm systems and components-audio and visual appL*tces and pull stations installed throughout in accordance with NFPA 72. d. Manual suppression systems-one 4" standpipe with 2 %2"xl Y2-" reducers, caps and chains will be installed in the main stairwell. e. Seismic considerations—braced in accordance with NFPA Standard. f. 2.5" x 2.5" Fire department connection provided. All of the above items are required by regulations. (784CMS) All Systems are new. Sprinklers are provided in accordance with NFPA 13. 903.1.1 (1B) SEQUENCE OF OPERATION Section 1 —Wet Sprinkler System System operates automatically upon the fusing of a single fire sprinkler. Operational Sequence: 1. The activation of a single sprinkler will discharge water and close the contacts of a vane type flow switch. 2. Closed contact on the flow switch will activate local audible visual panel and provide an alarm contact for the alarm control panel. 903.1.1 (1 C) TESTING CRITERIA Section 1 — Testing Criteria System piping: 1. Hydrostatically test at a pressure of 200 psi for 2 hours without a loss of pressure. 2. 2" main drain test shall be conducted. Static and Residual pressures will be recorded on the test certificate. 903.1.1 (1A) METHODOLOGY OF DESIGN Section 1 —BUILDING DESCRIPTION Project consists of one four-story building. A.D.A./Mass Access Code modifications. New Fire Alarm and automatic fire sprinkler system. a. Building "Use" Group: A§sembly b. Type of occupancies (hazards within the building) Restaurant& Office c. Storage of commodities within the building include: Food, beer& wine as required for restaurant. d. Four stories above grade e. One story below grade. f. Type of construction is 3B Section 2 —APPLICABLE LAWS, REGULATIONS AND STANDARDS a. 780 CMS code sections "Fire Protection System Requirements", 904.0 fire suppression systems, 906.5 requires audiovisual alarm devices. b. NFPA Standards and Edition used for design of fire sprinkler system: NFPA 13, "Standard for the Installation of Sprinkler Systems". 1999 Edition. Section 3 —DESIGN RESPONSIBILITY FOR FIRE PROTECTION SYSTEMS Design—build, the installing contractor completely designs and specifies (develops a full system layout, design criteria and calculations), installs the system and certifies system installation for code compliance at completion. Fire Sprinkler Narrative Report for Renovations & Alterations to Bay State Hotel 21 Strong Av. Northampton, MA BAY STATE HGTEL Drawing Date:8-7-02 81 7102 14:15 REMOTE AREA #1 PAGE 4 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUMMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE VELOCITY Pt Pt Pn ELEV ID T LT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE K FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 7 FROM HYDRAULIC REFERENCE 15 TO B2 HEAD 15 19.2 1;44" 0 0 613" 4 .2 fps 12.4 12.4 -14" 0. 13 gpm/sq ft 1. 380" 0 0 0" 0.032 0.2 0.2 14" K= 5. 50 19.2 120 40 0 613" 0" 0. 0 12.2 60" HEAD 16 19. 3 13,�" 0 0 818" 6. 1 fps 12. 6 12. 6 -14" 0. 13 gpm/sq ft 1. 610" 0 0 0" 0. 054 0. 5 0.2 14" K= 5. 50 38. 5 120 40 0 8 ' 8" 0" 0. 0 12. 4 60" HEAD 17 19. 7 1L" 2 0 4 ' 7" 9.3 fps 13.1 13. 1 -14" 0. 13 gpm/sq ft 1. 610" 0 0 810" 0. 117 1.5 0.3 14" K= 5. 50 58.2 120 40 0 1217" 9" 0.3 12. 8 60" REF 21 2" 0 0 3" 5. 6 fps 14 . 9 2.067" 0 0 0" 0. 035 0.0 58 .2 120 40 0 3" 0" 0.0 REF B1 2" 0 0 918" 5.2 fps 14 .9 2. 157" 0 0 0" 0. 028 0.3 58 .2 120 10 0 918" 0" 0.0 REF B2 58.2 gpm PATH 7 R= 14. 96 15.1 psi BAY STATE HGTEL Drawing Date:8-7-02 81 7102 14:15 REMOTE AREA #1 PAGE 3 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUMMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE VELOCITY Pt Pt Pn ELEV ID T IT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE K FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 4 FROM HYDRAULIC REFERENCE 8 TO A3 CONTINUED REF 20 15.3 1" 0 0 5111" 11.5 fps 8.0 PATH 6 1. 049" 0 0 0" 0.286 1.7 K= 5. 42 30. 6 120 40 0 5111" 0" 0.0 HEAD 9 17.0 1;'4" 0 0 1219" 10. 3 fps 9. 7 9. 7 -14" 0. 11 gpm/sq ft 1.380" 0 0 0" 0. 171 2.2 0. 1 14" K= 5. 50 47. 6 120 40 0 1219" 0" 0.0 9. 6 60" HEAD 10 18. 8 1' 1 0 2 ' 9" 10. 6 fps 11. 9 11. 9 -14" 0.13 gpm/sq ft 1 . 610" 1 0 1210" 0. 149 2.2 0.2 14" K= 5. 50 66. 4 120 40 0 1419" 9" 0.3 11 . 6 60" REF A3 66.4 gpm PATH 4 K= 17.52 14.4 psi PATH 5 FROM HYDRAULIC REFERENCE 4 TO A2 HEAD 4 15. 3 1" 0 0 11 ' 1" 5. 7 fps 7 .5 7 . 5 -14" 0. 10 gpm/sq ft 1 . 049" 0 0 0" 0. 080 0. 9 -0. 3 14" K= 5. 50 15. 3 120 40 0 11 ' 1" 0" 0. 0 7 . 8 24" HEAD 5 15. 9 1" 0 0 816" 11.7 fps 8 . 4 8 . 4 -14" 0. 11 gpm/sq ft 1.049" 0 0 0" 0 . 297 2.5 0. 0 14" K= 5. 50 31 .2 120 40 0 816" 0" 0. 0 8 . 4 60" HEAD 6 18 . 0 13"4" 1 0 415" 10. 7 fps 10. 9 10. 9 -14" 0. 12 gpm/sq ft 1 .380" 1 0 9' 0" 0. 182 2 . 4 0.2 14" K= 5. 50 49. 3 120 40 0 13' 5" 9" 0. 3 10. 8 60" REF A2 49.3 gpm PATH 5 K= 13.32 13.7 psi PATH 6 FROM HYDRAULIC REFERENCE 7 TO 20 HEAD 7 15. 3 1" 0 0 610" 5. 8 fps 7 . 5 7 . 5 -14" 0 . 10 gpm/sq ft 1. 049" 0 0 0" 0. 080 0. 5 -0.3 14" K= 5. 50 15.3 120 40 0 610" 0" 0. 0 7 .8 24" REF 20 15.3 gpm PATH 6 K= 5.42 8.0 psi BAY STATE HOTEL Drawing Date:8-7-02 81 7102 14:15 REMOTE AREA #1 PAGE 2 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUMMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE . VELOCITY Pt Pt Pn ELEV ID T LT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE R FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 3 FROM HYDRAULIC REFERENCE 1 TO TOR HEAD 1 15.2 1" 0 0 11 ' 1" 5.7 fps 7.4 7. 4 -14" 0. 10 gpm/sq ft 1.049" 0 0 0" 0.078 0. 9 -0. 3 14" K= 5. 50 15.2 120 40 0 11 ' 1" 0" 0.0 7. 6 24t1 HEAD 2 15. 8 1t1 0 0 816" 11. 6 fps 8 .2 8.2 -1411 0. 11 gpm/sq ft 1. 049" 0 0 0" 0.292 2.5 0. 0 14" K= 5. 50 31 .0 120 40 0 816" 0" 0.0 8 .2 60" HEAD 3 17. 9 1=4" 1 0 415" 10. 6 fps 10.7 10. 7 -14" 0. 12 gpm/sq ft 1 . 380" 1 0 910" 0. 179 2.4 0.1 14" K= 5. 50 48 . 9 120 40 0 1315" 911 0.3 10. 6 60" REF Al 211 0 0 11 ' 0" 4 .3 fps 13.5 2. 157" 0 0 0" 0. 020 0.2 48 . 9 120 10 0 11 ' 0" 0" 0.0 REF A2 49.3 2" 0 0 914" 8.7 fps 13.7 PATH 5 2 . 157" 0 0 011 0.074 0.7 K= 13. 32 98 .2 120 10 0 914" 0" 0.0 REF A3 66. 4 2" 0 0 618" 14 . 6 fps 14 .4 PATH 4 2 . 157" 0 0 01t 0. 192 1 .3 K= 17 . 52 164 . 6 120 10 0 61811 0" 0.0 REF A4 4" 0 0 4" 3.7 fps 15. 6 4 . 260" 1 0 617" 0.007 0.0 164 . 6 120 10 0 6111" 0" 0.0 REF TOR 164. 6 gpm PATH 3 K= 41.54 15.7 psi PATH 4 FROM HYDRAULIC REFERENCE 8 TO A3 HEAD 8 15. 3 1" 0 0 21011 5. 7 fps 7.4 7 . 4 -14" 0. 10 gpm/sq ft 1. 049" 1 0 510" 0. 079 0. 6 -0. 3 1411 K= 5. 50 15. 3 120 40 0 710" 0" 0.0 7 . 7 24" CONTINUED - -- - 8.0 psi -- BAY STATE HGTEL Drawing Date:8-7-02 81 7102 14:15 REMOTE AREA #1 PAGE 1 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUblMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE VELOCITY Pt Pt Pn ELEV ID T LT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE K FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 1 FROM HYDRAULIC REFERENCE 12 TO TOR (PRIMARY PATH) HEAD 12 14 . 9 1" 0 0 210" 5. 6 fps 7.1 7 . 1 -14" 0. 10 gpm/sq ft 1.049" 1 0 510" 0. 075 0.5 -0. 3 14" K= 5. 50 14 . 9 120 40 0 7101' 0" 0.0 7 .3 24" REF 22 15. 0 1" 0 0 5111" 11.2 fps 7 .6 PATH 2 1. 049" 0 0 0" 0.273 1.6 K= 5.43 29. 9 120 40 0 5111" 0" 0.0 HEAD 13 16. 6 13,11, 0 0 1219" 10. 1 fps 9.2 9.2 -14" 0. 11 gpm/sq ft 1.380" 0 0 0" 0. 163 2.1 0. 1 14" K= 5. 50 46.5 120 40 0 1219" 0" 0.0 9. 1 60" HEAD 14 18 . 3 1k4" 1 0 219" 14 . 0 fps 11.3 11. 3 -14" 0 . 12 gpm/sq ft 1. 380" 1 0 910 0. 301 3.5 0.2 14" K= 5. 50 64 . 8 120 40 0 11 ' 9" 9" 0.3 11 . 1 60" REF B2 58 .2 2" 0 0 4111" 10. 9 fps 15.1 PATH 7 2. 157" 0 0 0" 0. 112 0.6 K= 14 . 96 123. 0 120 10 0 4 ' 11" 0" 0.0 REF B3 4" 0 0 4" 2. 8 fps 15.7 4 .260" 0 0 0" 0. 004 0.0 123.0 120 10 0 4" 0" 0.0 REF TOR 123.0 gpm PATH 1 K= 31.05 15.7 psi PATH 2 FROM HYDRAULIC REFERENCE 11 TO 22 HEAD 11 15. 0 1" 0 0 610" 5. 6 fps 7. 1 7 . 1 -14" 0. 10 gpm/sq ft 1 . 049" 0 0 0" 0. 076 0.5 -0. 3 14" K= 5. 50 15. 0 120 40 0 610" 0" 0.0 7 . 4 24" REF 22 15.0 gpm PATH 2 K= 5.43 7.6 psi BAY STATE HGTEL Drawing Date:8-7-02 8/ 7102 14:15 LEGEND HYD REF Hydraulic reference. Refer to accompanying flow diagram. _ K FACTOR Flow factor for open head or path where Flow (gpm) = K x -\/P SIZE Nominal size of pipe. ID Actual internal diameter of pipe C Hazen Williams pipe roughness factor TYPE Type or schedule of pipe # FITS number of fittings as follows: 90 - 90 deg Ell 45 - 45 deg Ell T - Tee LT - Long Turn 90 Ell SPEC - Fitting other than above or fitting with hydraulic equivalent length specified by manufacturer. Pt Total pressure (psi) at fitting Pf Friction loss (psi) to fitting where Pf = 1 x 4 .52 x (Q/C) ^1.85 / ID^4 .87 Pe Pressure due to change in elevation where Pe = 0. 433 x change in elevation Pv Velocity pressure (psi) where Pv = 0. 001123 x Q^2/ID^4 Pn Normal pressure (psi) where Pn = Pt - Pv Pdrop Pressure loss in pipe rise or drop to an open head. Phead Pressure at an open head. ELEV elevation from branch tee to open head. PIPE pipe length from branch tee to open head. FITS fitting equivalent length from branch tee to open head. NOTES: - Pressures are balanced to 0.001 gpm. Pressures are listed to 0. 01 psi. Addition may vary by 0. 01 psi due to accumulation of round off. - Calculations conform to NFPA 13 edition. - Velocity Pressures are not considered in these Calculations - Path #1 is from the most remote head back to the water source. - Later Paths are from the next most remote head back to previously defined paths BAY STATE HGTEL Drawing Date:8-7-02 81 7102 14:15 HYDRAULIC CALCULATION DETAILS HYDRAULIC FLOW LOSS QTY DESCRIPTION LENGTH C ID gpm psi TOTALS Hydr Ref TOR Required at Hyd Area 1 288 15.7 psi 1 4" Grvd Tee 20' 120 4 .026 288 0.5 1 Pipe 4" 10x21 CSC 42 ' 120 4 .260 288 0. 8 1 4" Grvd 90 Ell 7 ' 120 4 .026 288 0.2 1 Pipe 4" 10x21 CSC 2 ' 120 4 .260 288 0.0 1 4" Grvd Tee 20 ' 120 4 . 026 288 0. 5 1 Pipe 4" 10x21 CSC 33 ' 120 4 .260 288 0. 6 1 4" Grvd 90 Ell 7 ' 120 4.026 288 0.2 1 Pipe 4" 10x21 CSC 2 ' 120 4.260 288 0. 0 1 4" Grvd 90 Ell 7 ' 120 4 .026 288 0.2 1 Pipe 4" 10x21 CSC 4 ' 120 4 .260 288 0. 1 1 4" Grvd Shotgun Valve VIKING "F-1" 13' 120 4 . 026 288 0. 3 2 4" Fingd Gate Valve NIBCO "F-607" 4 ' 120 4 .026 288 0. 1 1 4" Fingd Back Flow Valve CONBRAC "4 CHART LOSS 288 4 . 9 Elevation Change 4210" 18 .2 1 6" x 4" Fingd 90 Ell 14 ' 120 6.065 288 0. 1 1 Pipe 6" DIx18 C1 52 300' 140 6. 590 288 0. 5 Fixed Flow Flow Loss 100 gpm Hydr Ref Rl Required at Source 388 43.0 psi Water Source104.0 psi static, 68 . 0 psi residual @ 1350 gpm 388 gpm 100.4 psi SAFETY PRESSURE 57.4 psi Available Pressure of 100.4 psi Exceeds Required Pressure of 43.0 psi This is a safety margin of 57.4 psi or 57 % of Supply Maximum Water Velocity is 14 . 6 fps 0 0 0 OD m o >0 3 �<a o m � � -4 o Z--i Co -i > 2 v, A? mO o nzm � c m N 021 Z7 �n. :2 O N h1 O .. C n n 1p (D O fD O � (D O m O O wODp O O O D a LA in 23 I Qo 00 CDM O fD CD cn m °' cn C I � o �400 w AOOO L-0 Ln. 3 I I � j O (n NI (D CD D ° j o I � f °ooM t I i � "a n CD ' 33 I II I I I I � O` ID` I I O O C --- �' i COT D� I o ' 0 BAY STATE HGTEL Drawing Date:8-7-02 81 7102 14:15 HYDRAULIC DESIGN INFORMATION SHEET Job Name: BAY STATE HOTEL Location: 41 STRONG AVENUE NORTHAMPTON, CT Drawing Date: 8-7-02 Remote Area Number: 1 Contractor: ALLSTATE FIRE SPRINKLER, INC. Telephone:860-246-7711 92 WESTON STREET HARTFORD, CT 06120 Designer: JEFF GERMAINE Calculated By:SprinkCALC CSC Systems & Design Construction: EXISTING Occupancy:RESTURANT Reviewing Authorities:LOCAL BUILDING OFFICIALS SYSTEM DESIGN Code:NAPA-13 Hazard:LIGHT System Type:WET Area of Sprinkler Operation 1500 sq ftl Sprinkler or Nozzle Density (gpm/sq ft) 0. 100 I Make:VIKING Model:M-QR Area per Sprinkler 149 sq ftl Orifice:1/2 K-Factor: 5. 50 Hose Allowance Inside 0 gpm I Temperature Rating: 155 Hose Allowance Outside 100 gpm I CALCULATION SUMMARY 17 Flowing Outlets gpm Required: 387. 6 psi Required: 43.0 @ Source WATER SUPPLY Water Flow Test I Pump Data I Tank or Reservoir Date of Test 1990 I Rated Capacity 0 gpm I Capacity 0 gal Static Pressure 104 . 0 psi I Rated Pressure 0. 0 psi Elevation 0 Residual Pres 68 .0 psi I Elevation 0 I At a Flow of 1350 gpm I Make: I Well Elevation 0" I Model: I Proof Flow 0 gpm Location: UPPER MAIN & MASONIC Source of Information: NORTHAMPTON WATER DEPARTMENT SYSTEM VOLUME 160 Gallons Notes: 0 0 0 0 °° o 0 ;uZ4WL v O ;o co -<a ° (n —tt >>0> Z –1 N N 0 D cN1i ZmO 0Zr i C m o 0 jim Cn� .. ° (D -E �.. c CLO CD _ C 0 v � -�a°, co m w o (n M C .. " �° cn 0O. x°00 D cQ-a-a Z'a N'N' t� Q" cn O D mo 10 O CD O _0 -00 A. O 3 � a c U) 0 - co m cn .a 3 A V O N_0 co N ' 3 _. OE _ C) (% Q N O tD D C Cl O 3 tQ(O n 33 i -- -- -- — -- -- - TI.3' � CD n� jcn A Q. I I i I n O BAY STATE HOTEL Drawing Date:8-7-02 81 7102 14:55 REMOTE AREA #2 PAGE 4 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUMMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE VELOCITY Pt Pt Pn ELEV ID T LT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE K FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 9 FROM HYDRAULIC REFERENCE 44 TO W HEAD 44 38.3 1" 0 0 11" 14 .3 fps 48.4 48.4 0.26 gpm/sq ft 1.049" 1 0 510" 0. 432 2. 6 0.0 K= 5.50 38 .3 120 40 0 5111" 0" 0.0 48 .4 HEAD 45 39.3 1144" 0 0 3' 7" 16.8 fps 51.0 51.0 0.26 gpm/sq ft 1.380" 1 0 6' 0" 0.420 4.0 0.0 K= 5.50 77 .5 120 40 0 917" 0" 0.0 51.0 11W" 0 0 9'0" 12 . 3 fps 55.0 1.610" 0 0 0" 0. 198 1.8 77.5 120 40 0 910" 0" 0.0 2" 1 0 6" 7 . 5 fps 56.8 2.067" 0 0 5' 0" 0.059 0.3 77 .5 120 40 0 516" 0" 0.0 4" 1 0 1" 1 .8 fps 57. 1 4 .260" 0 0 13'2" 0.002 0.0 77. 5 120 10 0 13' 3" 1" 0.0 REF W 77.5 gpm PATH 9 K= 10.25 57.2 psi BAY STATE HOTEL Drawing Date:8-7-02 81 7102 14:55 REMOTE AREA #2 PAGE 3 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUMMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE VELOCITY Pt Pt Pn ELEV ID T LT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE K FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 6 FROM HYDRAULIC REFERENCE 53 TO C1 HEAD 53 31.8 1" 0 0 1 '0" 11. 9 fps 34.0 34.0 -3" 0.21 gpm/sq ft 1 . 049" 1 0 510" 0.307 1.8 0. 6 3" K= 5.50 31. 8 120 40 0 6'0" 0" 0.0 33.5 24" REF 61 1'-2" 0 0 71211 5.1 fps 35. 9 1. 610" 0 0 0" 0.038 0.3 31.8 120 40 0 712" 0" 0.0 REF 60 31.8 1',i�" 0 0 8 ' 0" 10. 1 fps 36.2 PATH 7 1. 610" 1 0 810" 0. 137 2.2 K= 5.29 63. 6 120 40 0 16' 0" 0" 0.0 REF C1 63.6 gpm PATH 6 K= 10.27 38.4 psi PATH 7 FROM HYDRAULIC REFERENCE 52 TO 60 HEAD 52 31. 8 1" 0 0 1 ' 10" 11. 9 fps 34. 1 34 . 1 -3" 0.21 gpm/sq ft 1.049" 1 0 510" 0.307 2.1 0. 6 3" K= 5.50 31.8 120 40 0 6110" 0" 0.0 33. 5 24" REF 60 31.8 gpm PATH 7 K= 5.29 36.2 psi PATH 8 FROM HYDRAULIC REFERENCE 49 TO C2 HEAD 49 32 . 6 114" 0 0 11' 0" 7 . 1 fps 35. 1 35. 1 0.22 gpm/sq ft 1. 380" 0 0 0" 0. 084 0.9 0. 0 K= 5.50 32 . 6 120 40 0 11' 0" 0" 0.0 35. 1 HEAD 48 33. 0 1k4" 0 0 2' 10" 14 .2 fps 36.0 36. 0 0.22 gpm/sq ft 1 . 380" 1 0 610" 0. 308 2.7 0. 0 K= 5.50 65. 6 120 40 0 8 ' 10" 0" 0.0 36. 0 REF C2 65. 6 gpm PATH 8 K= 10.54 38.7 psi BAY STATE HOTEL Drawing Date:8-7-02 81 7102 14:55 REMOTE AREA #2 PAGE 2 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUMMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE VELOCITY Pt Pt Pn ELEV ID T LT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE K FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 2 FROM HYDRAULIC REFERENCE 40 TO C2 CONTINUED REF 64 29.8 134" 0 0 12'0" 12.7 fps 29.5 PATH 4 1.380" 0 0 0" 0.251 3.0 K= 5.49 58.8 120 40 0 1210" 0" 0.0 REF 63 30.5 1' " 0 0 6" 14.2 fps 32.5 PATH 5 1.610" 0 0 0" 0.257 0.1 K= 5.34 89.2 120 40 0 6" 0" 0.0 HEAD 47 31 .4 11" 0 0 5' 8" 19.2 fps 32. 6 32 . 6 0.21 gpm/sq ft 1 . 610" 1 0 81011 0. 449 6. 1 0. 0 K= 5.50 120. 6 120 40 0 1318" 0" 0.0 32. 6 REF C2 120.6 gpm PATH 2 K= 19.38 38.7 psi PATH 3 FROM HYDRAULIC REFERENCE 51 TO 62 HEAD 51 29.2 1" 0 0 110" 10. 9 fps 28. 6 28 . 6 -3" 0.20 gpm/sq ft 1 .049" 1 0 510" 0.262 1.6 0. 5 3" K= 5.50 29.2 120 40 0 6'0" 0" 0.0 28 .2 24" REF 62 29.2 gpm PATH 3 K= 5.31 30.2 psi PATH 4 FROM HYDRAULIC REFERENCE 46 TO 64 HEAD 46 29.8 1" 0 0 6" 11.2 fps 29.3 29. 3 0.20 gpm/sq ft 1 .049" 0 0 0" 0.272 0. 1 0. 0 K= 5. 50 29. 8 120 40 0 6" 0" 0.0 29. 3 REF 64 29.8 gpm PATH 4 K= 5.49 29.5 psi PATH 5 FROM HYDRAULIC REFERENCE 41 TO 63 HEAD 41 30.5 1" 0 0 1' 4" 11.4 fps 30.7 30. 7 0. 11 gpm/sq ft 1 .049" 1 0 510" 0.283 1.8 0. 0 K= 5. 50 30. 5 120 40 0 614" 0" 0.0 30. 7 REF 63 30.5 gpm PATH 5 K= 5.34 32.5 psi BAY STATE HOTEL Drawing Date:8-7-02 81 7/02 14:55 REMOTE AREA #2 PAGE 1 FLOW # OF LENGTH PRESSURE BRANCH LINE (GPM) PIPE FITS FEET SUMMARY TO HEAD HYD REF OUTLET SIZE 90 45 PIPE VELOCITY Pt Pt Pn ELEV ID T LT FITTINGS LOSS PSI/FT Pf Pv Pdrop PIPE K FACTOR PIPE C TYPE OTHER TOTAL ELEVATION Pe Pn Phead FITS PATH 1 FROM HYDRAULIC REFERENCE 50 TO W (PRIMARY PATH) HEAD 50 28 . 1 1" 1 0 1310" 10.5 fps 26. 6 26. 6 -3" 0. 19 gpm/sq ft 1.049" 0 0 210" 0.244 3. 7 0. 4 3" K= 5. 50 28. 1 120 40 0 15'0" 0" 0. 0 26. 1 24" REF 62 29.2 1" 0 0 3' 11" 21.5 fps 30.2 PATH 3 1 .049" 1 0 510" 0.912 8 .2 K= 5.31 57.3 120 40 0 8 ' 11" 0" 0.0 REF C1 63. 6 23,�" 0 0 9'3" 7 .2 fps 38 . 4 PATH 6 2. 635" 0 0 0" 0.041 0. 4 K= 10.27 120. 9 120 10 0 913" 0" 0. 0 REF C2 186.2 23'z" 0 0 3' 1" 18.2 fps 38.7 PATH 2 AND 8 2. 635" 0 0 0" 0.230 0. 7 K= 29. 92 307.2 120 10 0 311" 0" 0.0 HEAD 42 34 . 5 23-�" 2 0 12 ' 3" 20.3 fps 39. 5 39. 5 0 . 12 gpm/sq ft 2 . 635" 0 0 1616" 0.280 8.0 0. 0 K= 5.50 341 .7 120 10 0 2818" 0" 0.0 39.5 HEAD 43 37. 9 2;-�" 0 0 1210" 22. 6 fps 47 .5 47.5 0.25 gpm/sq ft 2. 635" 1 0 16' 6" 0. 340 9.7 0.0 K= 5. 50 379. 6 120 10 0 2815" 0" 0.0 47.5 REF D1 4" 0 0 4" 8 . 6 fps 57 . 1 4 .260" 0 0 0" 0. 033 0 . 0 379. 6 120 10 0 4" 0" 0. 0 REF W 379. 6 gpm PATH 1 K= 50.21 57.2 psi PATH 2 FROM HYDRAULIC REFERENCE 40 TO C2 HEAD 40 29. 0 1" 0 0 1 ' 4" 10.9 fps 27. 8 27. 8 0. 10 gpm/sq ft 1.049" 1 0 510" 0.259 1. 6 0.0 K= 5.50 29.0 120 40 0 614" 0" 0.0 27.8 CONTINUED 29.5 psi BAY STATE HOTEL Drawing Date:8-7-02 81 7/02 14:55 LEGEND HYD REF Hydraulic reference. Refer to accompanying flow diagram. _ K FACTOR Flow factor for open head or path where Flow (gpm) = K x -\/P SIZE Nominal size of pipe. ID Actual internal diameter of pipe C Hazen Williams pipe roughness factor TYPE Type or schedule of pipe # FITS number of fittings as follows: 90 - 90 deg Ell 45 - 45 deg Ell T - Tee LT - Long Turn 90 Ell SPEC - Fitting other than above or fitting with hydraulic equivalent length specified by manufacturer. Pt Total pressure (psi) at fitting Pf Friction loss (psi) to fitting where Pf = 1 x 4. 52 x (Q/C) ^1.85 / ID^4.87 Pe Pressure due to change in elevation where Pe = 0. 433 x change in elevation Pv Velocity pressure (psi) where Pv = 0.001123 x Q^2/ID^4 Pn Normal pressure (psi) where Pn = Pt - Pv Pdrop Pressure loss in pipe rise or drop to an open head. Phead Pressure at an open head. ELEV elevation from branch tee to open head. PIPE pipe length from branch tee to open head. FITS fitting equivalent length from branch tee to open head. NOTES: - Pressures are balanced to 0. 001 gpm. Pressures are listed to 0.01 psi. Addition may vary by 0. 01 psi due to accumulation of round off. - Calculations conform to NFPA 13 edition. - Velocity Pressures are not considered in these Calculations - Path #1 is from the most remote head back to the water source. - Later Paths are from the next most remote head back to previously defined paths BAY STATE HOTEL Drawing Date:8-7-02 8/ 7102 14:55 HYDRAULIC CALCULATION DETAILS HYDRAULIC FLOW LOSS QTY DESCRIPTION LENGTH C ID gpm psi TOTALS Hydr Ref W Required at Hyd Area 2 457 57.2 psi 1 4" Grvd Tee 20' 120 4 .026 457 1.3 1 Pipe 4" 10x21 CSC 21 ' 120 4 .260 457 1.0 1 4" Grvd 90 Ell 7 ' 120 4 .026 457 0.4 1 Pipe 4" 10x21 CSC 2 ' 120 4 .260 457 0. 1 1 4" Grvd Tee 20' 120 4 .026 457 1.3 1 Pipe 4" 10x21 CSC 33' 120 4 .260 457 1.5 1 4" Grvd 90 Ell 7 ' 120 4 .026 457 0.4 1 Pipe 4" 10x21 CSC 2 ' 120 4.260 457 0.1 1 4" Grvd 90 Ell 7 ' 120 4 . 026 457 0. 4 1 Pipe 4" 10x21 CSC 4 ' 120 4 .260 457 0.2 1 4" Grvd Shotgun Valve VIKING "F-1" 13' 120 4 . 026 457 0. 8 2 4" Fingd Gate Valve NIBCO "F-607" 4 ' 120 4 . 026 457 0.2 1 4" Fingd Back Flow Valve CONBRAC "4 CHART LOSS 457 4.3 Elevation Change 21 ' 0" 9.1 1 6" x 4" Fingd 90 Ell 14 ' 120 6.065 457 0.1 1 Pipe 6" DIx18 C1 52 300' 140 6. 590 457 1.2 Fixed Flow Flow Loss 100 gpm Hydr Ref Rl Required at Source 557 79.6 psi Water Source104 .0 psi static, 68 . 0 psi residual @ 1350 gpm 557 gpm 97.0 psi SAFETY PRESSURE 17.4 psi Available Pressure of 97.0 psi Exceeds Required Pressure of 79. 6 psi This is a safety margin of 17.4 psi or 18 % of Supply Maximum Water Velocity is 22. 6 fps BAY STATE HOTEL Drawing Date:8-7-02 81 7102 14:55 HYDRAULIC DESIGN INFORMATION SHEET Job Name: SAY STATE HOTEL Location: 41 STRONG AVENUE NORTHAMPTON, CT Drawing Date: 8-7-02 Remote Area Number: 2 Contractor: ALLSTATE FIRE SPRINKLER, INC. Telephone:860-246-7711 92 WESTON STREET HARTFORD, CT 06120 Designer: JEFF GERMAINE Calculated By:SprinkCALC CSC Systems & Design Construction: EXISTING Occupancy:BAR Reviewing Authorities:LOCAL BUILDING OFFICIALS SYSTEM DESIGN Code:NFPA-13 Hazard:LIGHT System Type:WET Area of Sprinkler Operation 1500 sq ftl Sprinkler or Nozzle Density (gpm/sq ft) 0. 100 1 Make:VIKING Model:M-QR Area per Sprinkler 290 sq ftl Orifice: 1/2 K-Factor: 5.50 Hose Allowance Inside 0 gpm Temperature Rating: 155 Hose Allowance Outside 100 gpm 1 CALCULATION SUMMARY 13 Flowing Outlets gpm Required: 557.1 psi Required: 79. 6 @ Source WATER SUPPLY Water Flow Test Pump Data Tank or Reservoir Date of Test 1990 Rated Capacity 0 gpm 1 Capacity 0 gal Static Pressure 104.0 psi I Rated Pressure 0.0 psi Elevation 0 Residual Pres 68 .0 psi I Elevation 0 1 At a Flow of 1350 gpm I Make: I Well Elevation 0" I Model : ( Proof Flow 0 gpm Location: UPPER MAIN & MASONIC Source of Information: NORTHAMPTON WATER DEPARTMENT SYSTEM VOLUME 156 Gallons Notes: Baystate Realty Collaborative, LLC 12 Strong Avenue _ /L5_3 Northampton, MA 01060 Phone (413) 585-9200 Fax (413) 585-8300 LETTER OF TRANSMITTAL No. 001 PROJECT: Baystate Hotel Renovation DATE: 8/28/02 TO: Northampton Building Commissioner REF: ATTN: Mr. Anthony Patillo WE ARE SENDING: SUBMITTED FOR: ! ACTION TAKEN: ❑ Shop Drawings ❑ Approval ❑ Approved As Submitted ❑ Submittals X Your Use ❑ Approved As Noted ❑ Letter X As Requested ❑ ❑ Request For Change Order ❑ Review And Comment ❑ Request For Information ❑ ❑ Contract ❑ Prints COPIES DATE DESCRIPTION 1 Sprinkler drawings for the Baystate Hotel 1 Fire Sprinkler Narrative 1 Fire Alarm System Narrative 1 Set Electrical Drawings for Alarm& Security Systems 1 Set of Sprinkler drawings Remarks: Mr. Patillo: As per the request of the Fire Chief I am sending for your file a copy of the documentation sent to the Fire Chief. If you have any questions regarding this information please feel free to call me at 585-9200. Thank You. Dan Bishop Copy To: Signed: ( Daniel J. B sh p, Sr. 10 Strong Avenue Depth(ft) Design Case 3 0 ----- - - - - - i - 5 10 1 - 15 20 25 - 30 - 35 0 1 (ksf <ct-Shonng> V 6.3 CIVILTECH SOFTWARE USA www.civiltech.com Licensed to Paul A. Deterling P.E. Earthwork Engineering Inc. Date: 8/30/2002 File Name: C:\shoring\Earthwork\2002\0270H22.sho WALL HEIGHT: 22.00 MIN. EMBEDMENT: 9.86 MIN. PILE LENGTH: 31.86 MAX. MOMENT: 77.60 AT DEPTH: 12.00 BRACE OR ANCHOR: No. DEPTH ANGLE TOTAL HORIZ. VERT. L free L fixed 1 12.0 0.0 54.7 54.7 0.0 N/A N/A TOTAL VERTICAL FORCE: 0.0 DRIVING PRESSURE (ACTIVE, WATER, &SURCHARGE) X--Vertical depth from pile top No. X top Top Pres. - - X bot. Bot. Pres. Spacing 1 0.00 0.00 22.00 0.75 8.00 2 0.00 0.00 10.00 0.00 8.00 ACTIVE PRESSURE (BELOW DREDGE LINE) Y-Vertical depth from dredge level No. Y top Top Pres. Pres. Slope Width 1 0.00 0.75 0.02 1.00 2 5.00 2.26 0.05 1.00 PASSIVE PRESSURE (BELOW DREDGE LINE) Y--Vertical depth from dredge level In the calculation, the following passive pressures are divided by a Factor of Safety =1. No. Y top Top Pres. Pres. Slope Width 1 0.00 0.00 0.22 3.00 2 5.00 1.11 0.05 3.00 UNITS: Force-kip, Moment-kip-ft, Pressure-ksf, Pres. Slope-kip/ft3, Length/Depth -ft, Deflection - in 10 Strong Avenue 53 Depth(ft) Design Case 3 __ 0 --------- ---- 5 - 10 --------- -- -- - 15 20 - 25 - 30 Balance Force 0 1 (ksf 35 <ct-Shoring> V 6.3 CIVILTECH SOFTWARE USA www.civiltech.com Licensed to Paul A. Deterling P.E. Earthwork Engineering Inc. Date: 8/30/2002 File Name: C:\shoring\Earthwork\2002\0270H14.sho WALL HEIGHT: 14.00 MIN. EMBEDMENT: 16.07 MIN. PILE LENGTH: 30.07 MAX. MOMENT: 244.75 AT DEPTH: 20.63 DRIVING PRESSURE (ACTIVE, WATER, & SURCHARGE) X--Vertical depth from pile top __No. X top Top Pres. X bot. ___Bot. Pres. Spacing 1 0.00 0.00 14.00 0.47 8.00 2 0.00 0.00 10.00 0.00 8.00 ACTIVE PRESSURE (BELOW DREDGE LINE) Y-Vertical depth from dredge level No. Y top Top Pres. Pres. Slope Width 1 0.00 0.47 0.03 1.00 2 8.00 0.75 0.02 1.00 3 13.00 2.26 0.05 1.00 PASSIVE PRESSURE (BELOW DREDGE LINE) Y--Vertical depth from dredge level In the calculation, the following passive pressures are divided by a Factor of Safety =1. No. Y top Top Pres. Pres. Slope Width 1 0.00 0.00 0.46 3.00 2 8.00 3.69 0.23 3.00 3 13.00 2.11 0.05 3.00 UNITS: Force-kip, Moment-kip-ft, Pressure-ksf, Pres. Slope-kip/ft3, Length/Depth -ft, Deflection - in 10 Strong Avenue X32 Depth(ft) Design Case 2 - 0 -- ---- - 1 5 - 10 15 20 - 25 0 1 (ks� <ct-Shoring> V 6.3 ClV1LTECH SOFTWARE USA www.civiltech.com Licensed to Paul A. Deterling P.E. Earthwork Engineering Inc. Date: 8/29/2002 File Name: C:\shoring\Earthwork\2002\0270H12b.sho WALL HEIGHT: 12.00 MIN. EMBEDMENT: 11.03 MIN. PILE LENGTH: 23.03 MAX. MOMENT: 101.77 AT DEPTH: 9.68 BRACE OR ANCHOR: No. DEPTH ANGLE TOTAL HORIZ. VERT. L free_ L fixed 1 2.0 0.0 23.0 23.0 0.0 N/A N/A TOTAL VERTICAL FORCE: 0.0 DRIVING PRESSURE (ACTIVE, WATER, & SURCHARGE) X --Vertical depth from pile top No. X top _Top Pres. X bot. Bot. Pres. Spacing 1 0.00 0.00 12.00 0.75 8.00 2 0.00 0.00 10.00 0.00 8.00 ACTIVE PRESSURE (BELOW DREDGE LINE) Y-Vertical depth from dredge level No. Y top Top Pres. Pres. Slope Width 1 0.00 0.75 0.02 1.00 2 5.00 2.26 0.05 1.00 PASSIVE PRESSURE (BELOW DREDGE LINE) Y--Vertical depth from dredge level In the calculation, the following passive pressures are divided by a Factor of Safety =1. No. Y top Top Pres. Pres. Slope Width _ 1 0.00 0.00 0.22 3.00 2 5.00 1.11 0.05 3.00 UNITS: Force-kip, Moment-kip-ft, Pressure-ksf, Pres. Slope- kip/ft3, Length/Depth -ft, Deflection - in w 10 Strong Avenue Depth(ft) Design Case I - 0 - - - -- --- --- - - 1 - 5 - 10 -- 15 20 0 1 (ksf <ct-Shoring> V 6.3 CIVILTECH SOFTWARE USA www.civiltech.com Licensed to Paul A. Deterling P.E. Earthwork Engineering Inc. Date: 8/29/2002 File Name: C:\shoring\Earthwork\2002\0270H12a.sho WALL HEIGHT: 12.00 MIN. EMBEDMENT: 6.70 (8 recommended) MIN. PILE LENGTH: 18.70 MAX. MOMENT: 61.56 AT DEPTH: 8.84 BRACE OR ANCHOR: No. DEPTH ANGLE TOTAL HORIZ. VERT. L free L fixed 1 2.0 0.0 18.3 18.3 0.0 N/A N/A TOTAL VERTICAL FORCE: 0.0 DRIVING PRESSURE (ACTIVE, WATER, & SURCHARGE) X--Vertical depth from pile top No. X top Top Pres. X bot. Bot. Pres. Spacing 1 0.00 0.00 12.00 0.42 8.00 2 0.00 0.10 10.00 0.10 8.00 ACTIVE PRESSURE (BELOW DREDGE LINE) Y -Vertical depth from dredge level No. Y top Top Pres. Pres. Slope Width 1 0.00 0.42 0.02 1.00 2 5.00 1.01 0.05 1.00 PASSIVE PRESSURE (BELOW DREDGE LINE) Y--Vertical depth from dredge level In the calculation, the following passive pressures are divided by a Factor of Safety =1. No. Y top Top Pres. Pres. Slope Width 1 0.00 0.00 0.22 3.00 2 5.00 1.11 0.05 3.00 UNITS: Force-kip, Moment-kip-ft, Pressure-ksf, Pres. Slope- kip/ft3, Length/Depth -ft, Deflection -in Table 3-3. Empirical values for 0,D„and unit weight of granular soils based on the standard penetration number with corrections for depth and for fine saturated sands ` Very Description Very loose i Loose Medium Dense �I dense Relative density D, 0 0.15 0.35 0.65 0.85 1.00 Standard penetra- tion no.N 4 10 30 50 Approx.angle of internal i i friction ¢°t 2T-30° 27-32° 30-35' 35-40° 38-43° Approx.range 1 of moist unit - weight,(7)pcf 70-100$ 90-115 1 110-130 110-140 130-150 (kN(m') (11-16) (14-18) i (17-20) I (17-2 ) (20-23) I ' USBR [Gibbs.and Holtz (1957)]. f After Meyerhof(1956). 0 =25 +25D,with more than 5 percent fines and = 30+25D, with less than 5 percent fines.Use larger values for granular material with 5 percent or less fine sand and silt. $ It should be noted that excavated material or material dumped from a truck will weigh 70 to 90 pcf. Material must be quite dense and hard to weigh much over 130 pcf.Values of 105 to 115 pcf for nonsaturated soils are common. Table 3-4. Empirical values for q„' and consistency of cohesive soils based on the'standard penetration number Very Very Consistency soft Soft Medium Stiff stiff Hard i i t I i q.,ksf (2-CZ) 0 0.5 10 2.0 4.0 8.0 N,standard penetration ` resistance 0 2 4 8 16 32 7� ►,pcf 100-120 110-130 120-140 - (kN/m') (16-19) (17-20) (19-22) •These values should be used as a guide only. Local cohesive samples should be tested, and the relationship between N and the unconfined compressive strength q.established as q.= KN. bate: 8/30/2002 Page: 16 of 16 Maximum Soil Pressure = PS := Ka•7gran•H PS = 745 psf PS•L2.1•ft Maximum Bending Moment = Mmax := 8 50% Mmax = 2.28 kft Calculate allowable bending stress based on: Working Stress of Timber = Fby := 1100•psi Modification Factors: CD := 1.15 (Load Duration Factor for t=2 months) CF := 1.10 (Size Factor for 3" Thickness) Cf, := 1.20 (Flat Use Factor - 3") Allowable Bending Stress = Fb := Fby•(CD)•(CF)•(Cfu) Fb = 1670 psi Required Section Modulus = Sieq := Mmax Fb Sreq = 16.4 in Required Lagging Thickness = t := Sreq-6 12-in t = 2.86 in Use 3" Thick Timbers for La_g_gin_g END OF CALCULATIONS r r Date: 8/30/2002 Page: 15 of 16 Required Section Modulus = SX :_ Mb 0.60-(36•ksi) SX = 10.23 in Use W12 x 26 for Bracket (S = 3x 3.4 in31 Bracket to Sheetpile Connection The weld will be designed for the applied bending load to the bracket section and the vertical shear force. The weld will be designed in accordance with "Design of Welded Structures"by Blodgett. Length of Weld Across Top Flange = b := 6-in Length of Weld Down Each Side of Web = d := 10.5-in Section Moduli of To Weld S [(2-b-d + d2) Top = wt := 3 St = 79 in Section Moduli of Bottom Weld = S d2-(2-b + d) 2 wb := Swb = 50 in 3•(b + d) Design Section Modulus = Sd := if(Swt < Swb,Swt,Swb) Sd = 50 in Mb Force on Weld for Bending = fwb := S fWb = 4.41 kpi d WtW Force on Weld for Shear = fw,, := fw, = 0.34kpi (b+ 2•d) Force on Weld = fw := Ifb 2 +f wV 2 fw = 4.42 kpi Required Weld Size = tw :_ fw cos(45-deg)-0.30•(70-ksi) tw = 0.298 in Use 5116-Inch (0.3125") E70 Welds - 6" Top and 10.5"Sides o Lagging Design Lagging will be used between the soldier piles to retain the soils. Lagging will be designed to resist the lateral soil loading. Due to soil arching between piles this loading will be reduced by 50% as recommended in FHWA Report No. RD-75-128, "Lateral Support Systems and Underpinning", Vol. I. The maximum clear span between pile flanges will be 7 feet. Maximum Clear Span = L := 7-ft Maximum Excavation Height = H = 22ft Date: 8/30/2002 Page: 14 of 16 Combined Axial and Bending Loading F a + C ffb = 0.581 < 1.00 OK (Eq. H1-1, AISC 9th Ed.) a 1 — F •Fb e fa + fb = 0.407 < 1.00 OK (Eq. 1­11-2, AISC 9th Ed.) 0.60•Fy Fb Use HP14x73 For Corner Brace o Corner Brace to Wale Connection Design Based on AWS D1.1, the allowable load on a fillet weld, assuming E70XX electrodes. Weld Yield Strength = Ft := 70•ksi Allowable Strength = FW := 0.30-Ft FW = 21 ksi Weld Size = w := 5-in 16 Weld will be designed to resist the compressive and shear loads at the connection. Req. Weld Capacity = PW := Pa PW = 232 kip Req. Weld Length =LW :_ PW cos(45•deg)•FWw LW = 50.0 in Provide 50" Weld of 5116"E70XX Weld By inspection the same wale section (HP14xl 17) can be used at the stairway area where the span between braces is reduced from 29 feet to 16 feet. o Wale Support Bracket Connection Wale seats will be used to temporarily support the wales and cross braces during installation. Each wale seat will be designed to carry the wale and brace load plus 50% impact loading. The wale seats will be cut from sections of structural steel. Weight of Wale and Brace =Wtw := [(40•ft)•(117.plf) + 20•ft•(73.plf) ]-(150%) Wtw = 9.21 kip Bending Moment in Bracket = Mb :_ (2-ft)-(Wt') Mb = 18.4 kft Date: 8/30/2002 Page: 13 of 16 Combined Stresses Analysis: Fy := 50•ksi E := 29000.•ksi Cm := 1.00 Trial Section: HP1473 A := 21.4•in2 d := 13.61-in Wt := 73•plf Sy := 35.8•in3 ry := 3.49-in Af := 7.36•in2 o Applied Stresses: fa := Pa fa = 10.84ksi A Wt•LU z 8 fb := S fb = 1.22 ksi Y o Allowable.Axial Stress: k := 1.0 „ X k•:= L X = 69 ry Fy FC, := C, = 107 X2 1 — Y 2 F 2.C� Fa := Fa = 21.16ksi 5 X X3 3 8•Ce 8 Cc3 o Allowable Bending Stress Fbl := 0.60•Fy Fbl = 30ksi Cb := 1.0 Y :_ d Y = 1.85 in 1 Af 12000•Cb Fb2 := d ksi Fb2 = 27.0 ksi 1u•Aff Fb := if(Fbl > Fb2,Fb2,Fbl) Fb = 27 ksi 12•�c2•E o Allowable Euler Stress Fe :_ Fe = 31.58ksi 23•�X2� 1 Date: 8/30/2002 Page: 12 of 16 Local Flange Bending: P 5 9 g bf := •R PH = 139 kip (Eq. K1-1) 3 Pbf tfn := 0.4 — Fy tfb = 0.667 in < tf = 0.805 in OK Local Web Yielding: Rmaxl := 0.66•Fy•[t,•(N + 5•k)] (Eq. K1-2) Rmaxl = 561 kip > R = 83 kip OK t 1.5 t For Web Crippling: R..ax2 := 67.5•tW2 1 + 3• a tf •F.tf • 1 ksi (Eq. K1 ) Rmax2 = 1198 kip > R = 83 kip OK Sidesway Web Buckling: L„ := 32•ft (Eq. K1-6) (d- 2•k) tW X :_ x = 0.53 < 2.30 Lu bf 6800•ksi•t 3 Rside w •(1 + 0.4•x3) (d- 2•tf) Rside = 298 kip > R = 83 kip OK Web stiffeners are not required at brace to wale connections o Corner Brace Design A corner brace will be installed in the area adjacent to the stairway where there are higher lateral loads from the soldier piles. The corner brace will be designed for the applied axial stress from the wales and for the moment due to the dead weight of the brace. Unsupported Length = L„ := 20•ft Number of Piles Supported = N := 3 Angle of Brace to Wale = a := 45-deg Axial Load = P, :-- (B3•N) cos(a) Pa = 232 kip Date: 8/30/2002 Page: 11 of 16 12-n 2 E o Allowable Euler Stress Fe := Fe = 10.93 ksi 23•(X2) Combined Axial and Bending Loading f + Cm fb = 0.709 < 1.00 OK (Eq. H1-1, AISC 9th Ed.) Fa F a Tb Fe fa + fb = 0.403 < 1.00 OK (Eq. 1­11-2, AISC 9th Ed.) 0.60•Fy Fb Use HP14x73 For Cross Braces o Cross Brace to Wale Connection Design Based on AWS D1.1, the allowable load on a fillet weld, assuming E70XX electrodes. Weld Yield Strength = Ft := 70-ksi Allowable Strength = FW := 0.30-Ft F,,, = 21 ksi Weld Size = w := 5•in 16 Weld will be designed to resist 10% of the compressive loads at the connection. Req. Weld Capacity = PW := Pa-10% P,,, = 8 kip Req. Weld Length =LW :_ PW cos(45•deg)•FW•w L, = 1.8 in Provide 8" Weld of 5116"E70XX Weld Check If Web Stiffeners Required at Wales The brace to wale connection will be analyzed to determine if web stiffeners are required. AISC Manual (9th Ed.) Equation K1-2 will be used to analyze local web yielding and Equation K1-4 will be used to analyze web crippling. For HP14xl17 d := 14.21-in t, := 0.805-in tf := 0.805-in k := 1.500-in For HP14x73 N := 13.61-in Fy := 50•ksi Normal Force = R := Pa R = 83 kip bate: 8/30/2002 Page: 10 of 16 Weight of Brace = wt := 73•plf Tributary Length for Axial Load = Lt := 29-ft Lt = 29 ft Design Axial Load in Brace = Pa := w•Lt Pa = 83 kip 2 Wt. Bending Moment in Brace = Mb := 8 Mb = 10.5 kft o Applied Stresses: fa := Pa fa = 3.9 ksi A wt.Lu 2 fb := 8 S fb = 3.54 ksi Y o Applied Stresses: fa := Pa fa = 3.9ksi A fb := Mb b fb = 3.54 ksi Y o Allowable Axial Stress: k := 1.0 (Table C-C2.1, AISC 9th Ed. for pinned) k•L„ X := X = 117 ry FF Cc := Cc = 126 X2 1 — 2 Cc FY Fa := Fa = 10.7ksi (53) X3 8-Cc 8 Cc3 o Allowable Bending Stress Fbt := 0.60-FY Fbt = 21.6ksi Cb := 1.0 Y := d Y = 1.85 in 1 Af 12000•Cb Fb2 := d ksi Fb2 = 15.9 ksi Af Fb := if(Fb I > Fb2,Fb2,Fb1) Fb = 15.9ksi Date: 8/30/2002 Page: 9 of 16 o Allowable Bending Stress Fb := 0.60•Fy Fb = 30ksi 2 o Allowable Euler Stress F 12-7 .E Fe := Fe = 36ksi 23•(X 2) Combined Axial and Bending Loading a + Cm-fb = 0.962 < 1.00 OK (Eq. H1-1, AISC 9th Ed.) F a a 1 — Tb e fa + fb = 0.906 < 1.00 OK (Eq. 1-11-2, AISC 9th Ed.) 0.60•Fy Fb Use HP14x117 for Wales o Welded Connection Design Welded connections will be design for the combined compressive and shear loading at the wale to wale connection.. Wale to Wale Connection Compressive Load at Connection = C := 15•ft•w C = 43 kip Shear Load at Connection = V := 16-ft-w V = 46kip Resultant Weld Load = R := FP—+V2 R = 63 kip Weld Strength = FW := 0.30•(70•ksi) FW = 21 ksi Weld Size = W := 5-in 16 Required Weld Length = LW := R LW = 13.6 in cos(45•deg)•FW W Provide 16 Inches of 5116-inch E70 Weld o Cross Brace Design The cross braces will be designed for the axial load and the bending moment due to the weight of the brace. A combined stress analysis for the brace design will be done. Unsupported Length of Bracing = L„ := 34-ft (Wale to Wale Span) Combined Stresses Analysis: FY := 36-ksi E := 29000..ksi Cm := 1.00 Trial Section: HP14x73 A := 21.4•in2 ry := 3.49-in Sy := 35.8-in' Af := 7.36-in2 d := 13.61-in t, := 0.505-in bf := 14.585•in tf := 0.505-in r 1 r Date: 8/30/2002 Page: 8 of 16 e.) Bracing Design The bracing will be designed for the most critical loading applied. o Wale Design The wales will be designed to resist the maximum moment and axial load due to soil and surcharge loading. Clear Span Between Bracing = Lc := 32-ft Soldier Pile Spacing = S := 8-ft Maximum Lateral Load = B2 = 23 kip B Equivalent Uniform Loading = w := S w = 2.9k1f Axial Load in Wale = Pa := 18•ft•w Pa = 52 kip w-L,2) Design Moment = Mb := Mb = 368 kft 8 Trial Section: HP14x117 A := 34.4•in2 d := 14.21-in SX := 172•in3 rX := 5.96.in Combined Stresses Analysis: Fy := 50•ksi E := 29000.-ksi Cm := 1.00 o Applied Stresses: fa := Pa fa = 1.5 ksi A M fb := b fb = 25.67 ksi SX o Allowable Axial Stress: k := 1.0 (Table C-C2.1, AISC 9th Ed. for pinned) k•Lc X := X = 64 rX �2•E Cc := Cc = 107 FF 7 Y X2 1 — 2 Cc2 Ty Fa := Fa = 21.95 ksi 5 X X' + 3 — 3 8•Cc 8.Cc3 Date: 8/30/2002 Page: 7 of 16 d.) Soldier Pile Design The soldier piles will be designed for the maximum bending moment from above. Two design sections will be used for the 12' cut and the full 22' cut. Soldier Pile Section for 12' Cut The soldier piles will be designed for the maximum bending moment determined in the above analysis. Soldier Pile Yield Strength :Fy := 36-ksi (ASTM A36 Steel) Design Moment = Md := MmaX2 Md = 102 kft Required Section Modulus = SX :_ Md 0.667•Fy SX = 50.9 in3 Use HP12x53 Soldier Pile with SX = 66.8 in3 Soldier Pile Section for 22' Cut The soldier piles adjacent to the stairway will be designed for the maximum bending moment determined in the above analysis. Soldier Pile Yield Strength :Fy := 50•ksi (ASTM A572 Steel) Design Moment = Md := Mmax3a Md = 245 kft Required Section Modulus = S Md X :_ 0.667•Fy SX = 88.1 in3 Use HP14x73 Soldier Pile with SX = 107 in3 Soldier Pile Embedment The required toe embedment is taken from the results above and will vary. The length of piles will be 20 feet along Strong Avenue, 25 feet along the back of the site and 35 feet at the stairway area. Date: 8/30/2002 Page: 6 of 16 Using the above lateral loadings on the excavation support system a computer analysis was run to determine the maximum bending moment and lateral bracing load and the results are on page B3. The analysis also determines the required toe embedment for moment equilibrium about the bracing level. The calculated embedment will be increased by 20% to provide a factor of safety. Maximum Bending Moment = Mmax3a := 244.75•kft Minimum Soldier Pile Length =L3a := H + 120%(16.07-ft) L3a = 33 ft Full Excavation Condition - H=22' Total Height of Excavation = He := 22-ft Height of Support = H := 22-ft - Depth to Water Table = hW := 22-ft Active Pressure Active Pressure at Subgrade = Pa := Ka•(ygran•He) Pa = 745psf Slope of Active in Granular Below Subgrade = Sa := Ka-7bg Sa = 17 pft Active Pressure at Clay = Pa := Kai•(7gran-He +7bg•5•ft) — 2•S„ Pa = 2263psf Slope of Active in Clay = Sa := Kac-7bc Sa = 53 psf Passive Pressure Slope of Passive in Granular Soil =SP := KP*Ybg Sp = 231 pft Passive Pressure at Clay = PP := Kpc•(7bg•5•ft) + 2•Su Pp = 1113psf Slope of Passive in Clay = SP := Kpc*7bc SP = 53 psf Using the above lateral loadings on the excavation support system a computer analysis was run to determine the maximum bending moment and lateral bracing load and the results are on page B4. The analysis also determines the required toe embedment for moment equilibrium about the bracing level. The calculated embedment will be increased by 20% to provide a factor of safety. Maximum Bending Moment = Mmax3b := 77.60•kft Brace Load per Pile = B3 := 54.7-kip Minimum Soldier Pile Length =L3b := H + 120%.(9.86-ft) Lab = 34 ft Date: 8/30/2002 Page: 5 of 16 Maximum Bending Moment = Mmax2 := 101.77•kft Brace Load per Pile = B2 := 23.0-kip Minimum Soldier Pile Length =L2 := H + 120%.(11.03.ft) L2 = 25ft c.) Design Case 3 - 22' Excavation With No Surcharge This design case will apply to the excavation support to be installed along the stairway. The lateral pressures on the excavation support system will be due to soil loading. The design height of support will be 22 feet with no surcharge and a level of bracing will be installed at a depth of 12 feet. The water table will be assumed at subgrade. Initial Cantilever Condition - H=14' At the stairway area a temporary cantilever condition of 14 feet will be required to install the level of internal bracing. This condition will first be analyzed. Height of Support = H := 14-ft Depth to Water Table = hW := 22•ft Active Pressure Active Pressure at Subgrade = Pa := Ka•(7gran'H) Pa = 474psf Slope of Active in Granular Below Subgrade = Sa := Ka.7gran Sa = 34 psf ft Active Pressure at Water = Pa := Ka•[7gran'(H + 8-ft)] Pa = 745 psf Slope of Active in Granular Below Water :Sa := Ka-rbg Sa = 17 psf ft Active Pressure at Clay = Pa := KaJygran-(H + 8-ft) +ybg•5•ft] — 2-S,, Pa = 2263 psf Slope of Active in Clay = Sa := Kac'Ybc Sa = 53 psf ft Passive Pressure Slope of Passive in Granular Soil =S := Kp•ygran Sp = 461 pft Passive Pressure at Water = Pp := Kp•(ygran-8-ft) PD = 3690psf Slope of Passive in Clay = Sp := Kp•ybg Sp = 231 pft Passive Pressure at Clay = Pp := Kpc.(7gran'8.ft+7bg-5•ft) +2.S„ Pn = 2113 psf Slope of Passive in Clay = Sp := Kpc*7bc Sp = 53 psf ft r 1 Date: 8/30/2002 Page: 4 of 16 Using the above lateral loadings on the excavation support system a computer analysis was run to determine the maximum bending moment and lateral bracing load and the results are on page B1. The analysis also determines the required toe embedment for moment equilibrium about the bracing level. The calculated embedment will be increased by 20% to provide a factor of safety. Maximum Bending Moment = Mmaxl := 61.56-kft Brace Load per Pile = B1 := 18.3-kip Minimum Soldier Pile Length =L1 := H + 120%•(6.70-ft) L1 = 20ft b.) Design Case 1 - 12' Excavation With Sloping (No Surcharge) This design case will apply to the excavation support to be installed along the back side of the site. The lateral pressures on the excavation support system will be due to soil loading. The design height of support will be 12 feet with no surcharge and due to the soft clays a level of bracing will be installed at a depth of 2 feet. The water table will be assumed at subgrade. Total Height of Excavation = He := 22-ft Height of Support = H := 12-ft Depth to Water Table = hW := 12.ft Active Pressure Active Pressure at Subgrade = Pa := Ka•(7gran*He) Pa = 745 psf Slope of Active in Granular Below Subgrade = Sa := Ka•7bg Sa = 17 psf ft Active Pressure at Clay = Pa := Kac-(ygran-He +ybg•5•ft) — 2-Su Pa = 2263 psf Slope of Active in Clay = Sa := Kac'ybc Sa = 53 pft Passive Pressure Slope of Passive in Granular Soil =Sp := Kp*ybg Sp = 231 pft Passive Pressure at Clay = Pp := Kpc.(ybg-5.ft) + 2-S„ Pp = 1113psf Slope of Passive in Clay = Sp := Kpc•ybc Sp = 53) psf ft Using the above lateral loadings on the excavation support system a computer analysis was run to determine the maximum bending moment and lateral bracing load and the results are on page B2. The analysis also determines the required toe embedment for moment equilibrium about the bracing level. The calculated embedment will be increased by 20% to provide a factor of safety. Date: 8/30/2002 Page: 3 of 16 The minimum factor of safety against base heave required is typically 1.50. A factor of safety of less than 1.00 indicates that there will be a problem with base heave. Since the excavation does not extend down into the clay layer but stops in the medium dense granular soils the factor of safety should be higher than calculated. However the above analysis clearly indicates there may be a problem with bottom stability. It may therefore be necessary to excavate the basement area in sections and then place the wall footings and backfill before excavating an adjacent area. The excavation subgrade should be closely monitored for any signs of base heave during excavation. 5.0 Design of Excavation Support System The height of excavation varies around the site and therefore several design cases will be analyzed. Along Strong Avenue the height of support will be 12 feet with no sloping. Along the back side of the site 12 feet of support will be provided with 10 feet of sloping above. In the area adjacent to the stairway full height support of 22 feet will be provided with a level of internal bracing. Rankine earth pressures will be used for the cantilever conditions and rectangular earth pressure envelops using 25xH will be used for the braced condition. The passive pressures below subgrade will be mobilized over 3 pile widths, in accordance with Brom's theory. a.) Design Case 1 - 12' Excavation With No Sloping This design case will apply to the excavation support to be installed along Strong Avenue. The lateral pressures on the excavation support system will be due to soil and surcharge loadings. The design height of support will be 12 feet with no sloping and due to the soft clays a level of bracing will be installed at a depth of 2 feet. The water table will be assumed at subgrade. Height of Support = H := 12-ft Depth to Water Table = hW := 12-ft Equipment Surcharge = S := 100-psf (0' to 10') Active Pressure Active Pressure at Subgrade = Pa := Ka.(ygran'H) Pa = 406psf Slope of Active in Granular Below Subgrade = Sa := Ka'ybg Sa = 17 psf Active Pressure at Clay = Pa := Kac'(Ygran'H +7bg•5•ft) - 2.Su Pa = 1013psf Slope of Active in Clay = Sa := Ka,'Ybc Sa = 53 psf Passive Pressure Slope of Passive in Granular Soil =SP := Kp•7bg SP = 231 pft Passive Pressure at Clay = PP := Kpc.(ybg•5.ft) + 2-Su PP = 1113psf Slope of Passive in Clay = SP := Kpc•ybc SP = 53 pft t rl t Date: 8/30/2002 Page: 2 of 16 o Clay Layer Unit Weight = 7clay := 115•pcf (Below 1T) Buoyant Weight = Y 9 Ybc (Yclay—Yw) ybc = 53 pcf Active Pressure Coefficient = Kai := 1.00 Passive Earth Pressure Coefficient = Kpc := 1.00 Shear Strength = SU := 400•psf 4.0 Stability of Excavation The stability of the excavation will be analyzed by looking at the "Stability Number" for the given excavation and the Factor of Safety against basal heave. Maximum Excavation Height = H := 22-ft Shear Strength at Subgrade = S„ = 400psf 4.A.) Bottom Stability The driving force in the bottom stability calculation will be from the soil weight outside the excavation. The resisting force will be derived from the shear strength of the clay layer. .H Bottom Stability Number = NS := Ygran S„ NS = 6.88 As per the discussion given on page 462 of "Foundation Engineering" by Peck, Hanson and Thornburn, for a Bottom Stability Number of between 6 and 8 the movements of the bracing system and heave of the clay below the base level are expected to be relatively large. To minimize this movement no surcharges should be placed at the top of the cut slope. 4.B.) Factor of Safety Against Base Heave Width of Excavation = B := 40-ft Length of Excavation = L := 200-ft Shape Factor = B = 0.2 Depth to Width Ratio = a := B a = 0.55 Bearing Capacity Factor = Nc := 6 Nc'(S„) Factor of Safety Against Base Heave = FSbh :_ 1'gran'H FSbh = 0.87 Y r � Date: 8/30/2002 Page: 1 of 16 Temporary Excavation Support Design 60 Strong Avenue North Hampton, MA 1.0 Units ft f lbf psf lbf:= 2 pcf lbf:= 3 plf lb :_ f lb := ft•lbf psi := 2 7, := 62.4-pcf ft ft ft in klf := plf•10 3 3 kip kip kip 2 kft := ftlb•1000 kip := lbf•10 kpi :_ — ksi :_ ksf := 2 in in ft 2.0 Design Procedure and Assumptions The excavation support system required for construction of the new building at 10 Strong Avenue in North Hampton, MA will consist of internally braced soldier piles and lagging. The height of excavation will be vary from 12 to 22 feet. The system will be designed to resist lateral pressures due to soil and surcharge loadings. The resulting forces on the excavation support system will be determined using the CT-Shoring Computer Program. From the calculated forces the soldier piles, lagging and bracing will be designed. 3.0 Design Parameters and Variables Based on the three site borings it is anticipated that the soil conditions will generally consist of 17 feet of medium dense granular soils over a thick soft clay layer. The design of the lateral support system shall be based on rankine earth pressures. The rankine pressures are determined using the following soil properties taken from Table 3-3 and 3-4 of "Foundation Analysis and Design", Bowles, 2nd Ed. (pg. Al of calc). The water table is assumed at subgrade. Soil Properties o Granular Soil Unit Weight = ygran := 125-pcf (0' to 17') Weight Buoyant = Y 9 Ybg :- (Ygran—Yw) Ybg = 6')pcf Friction Angle = := 35-deg � 2 Active Pressure Coefficient =Ka := tan 45-deg— — 2 Ka = 0.271 2 Passive Pressure Coefficient = Kp := tan 45-deg+ 2) Kp = 3.690 f DESIGN OF TEMPORARY EXCAVATION SUPPORT 10 STRONG AVENUE NORTH HAMPTON, MASSACHUSETTS Prepared Bv: Earthwork Engineering, Inc. 175 Ridge Road Hollis, NH 03049 (603) 465-9500 Prepared For: National Shoring P.O. Box 248 Stonington, CT 06378 (860) 535-4025 RECEIVE [ SEP - 5 L'uv2 lesternBuilders RECEIVED \AOFM ��P�� ASS9cy SEP — 5 2002 �� PAUL A. G� DETER LING CIV.34437 WesternBuilders A ,� IL No �o- F STEM F /0 Paul A. Deterling, P.E Mass. P.E. No. 344 August 30, 2002 T.Pabilo August 21,2002 Alarm verification must be active on all smoke detection zones. The Fire Alarm Control Panel must be marked with a red engraved sign with one-inch white lettering "Fire Alarm Control Panel': The Fire Alarm Annunciator Panel must be marked withy a red engraved sign with one inch white lettering "Fire Alann Annunciator Panel". o Permits must be pulled for all fire alarm and fire suppression work. • 5 Pound ABC Dry Chemical Fire Extinguisher is required at the pull station and on the ground floor. • A mini-hom is required in each residential unit to alert the residents to a fire alarm condition. o A red 120-candela strobe light that actuates upon an alarm condition is required above the Knox box. 0 Page 2 w Northampton Department Memorandum To: Tony Patillo J From: B. P. Dugga r( Date: August 21, 2002 Mr. Strong Avenue Block— 10 Strong Avenue Secondary to a review of the plans and fire protection narrative that you submitted to me on August 13, 2002, 1 concur with the issuance of a building permit for this property subject to the following conditions: • A permit is required for the storage of flammable liquids and for the dumpster. • The Fire Department Connection is to be a 4" locking Storz connection with an attached chain. In addition a sign reading "Fire Department Connection" 3 " white letters on a red background is to be mounted above the connection. An electric bell actuated upon water flow must be located above this sign. • The standpipe must have signage at ech valve and be equipped with the proper adaptors to reduce the connection from 2 112 ` NST to 1 1/2 " NST. • All pull stations referenced in the fire protection narrative are to be of the double action type and those in areas where children may congregate must be covered by Stopper 11 protection. • A graphic representation of the structure must be installed at the Fire Alarm Control Panel (FACP) and at the Fire Alarm Annunciator Panel (FAAP). •Page 1 O O Gift of 'Wcrfl7a111i l#011 _ L "^" m DEPARTMENT OF BUILDING INSPECTIONS INSPECTOR 212 T1ain Street ' Municipal Building Northampton, Mass. 01060 n y Square Footage Amount Basement @ .10 5687 568.70 1st Floor @ .40 4263 1,705.20 2nd Floor @ -20 5687 1,137.40 1/2 Floors, Attic, Garage _ 10 1424 142.40 >x(x x1 0 xKxxxx= 3rd Floor @ .20 4263 852.60 $4,406.30 TOTAL j-zyC'C� �;� 10 Strong Ave. �n E C E � W E SEP 2 3 2002 L DEP?Of BUILDING INSPECTIONS rd1.2?W%'DT0N,MA 01060 FP.OM : FORD G I LLDN ARCH I TECT�.S r7k t io. X113 2 rJ 1;53 Sep. i 1 2002 G.�:�9 r1 P3 Climate-Specific Requirements Gro„ Cavity Cont. Propo�cd BUCI.et Component Name/Description Area R-Value R-Value 1J-Factor 11-Factor Roof 2: Structural Slab 5690 --- 30.0 O.I)3 0.054 Comments: Lxterior Wall 1: Other, HC 1.0 10106 --- --- 0.M3 0.079 Comment_~: Window 1: Wood Frame,Double Pane with Low-2 ]432 - - 0.1S0(b) O.S l7 clear,shsc 0.30 Comments: [door 1: Solid 308 --- ... 0.700(b) 0.127 Comments: Door 3: Glass,Clear, zh_u_c 0.54 150 --- - 0.920(h) 0 50 Comments: lnt.erior Wall 4: Other, HC 1.0 236 --- - - 0.053 0.127 Comments: Basemen Wall 4: Solid Concrete or Masonry% S" Fw-rn-:None, Wall Ht 8.9,Depth R.G. 8.8 2412 --- 17.0 0.053 0.103 Comment;: Floor 1:All-Food Joist'Truss 142 5-5.0 U•U 0.019 0.046 Comments: studio floor Floor 2: Unheated Below-Grade Slab(c) 0 - 15.0 --- --- Comm;nt:;: ai Buus-t U-factors arc used for sofwarc baseline calculations ONLY,and arc not code requirements. (I)j Claimcd performancc does net exceed dafaulta in T ablcs 1301.9.3.1.No tnanufacturcr certification reyuire�. (c)Curtain building use types rcyuir c.mliruiiu under-slab tasulation(sce MFL\SSCF LLSCLt:i Crude Section 1304.2"and 130.1?.°1. Envelope PASSES: Desigm 27 ,,bctt,r than code Section 4: Compliance Statement The proposed envelope desi5n represented in this document is consistent with the buildin plans,specifications and other calculations submitted with this permit application. The proposed envelope system has been de,i^ned to meet. the Massachuserts Commercial Code requirements in COMc•heck-L•Z Version 2.3 Release 1. Principal;='nvelope Designer-Name Signature Date FPON : FORD G I LLErl ARCHITECTS FH;: r 1O. : 41 2`56 1557 Sep. 11 2002 0::58F l P2 Gam Envelope Compliance Report Massachusetts Commercial Code COvic i��k E/_ Software Vr.rsion 2.3 Release 1 Data tilcrtame: `'0an`SHAREU`2026 STRONG AVE'.2026 Srccs',Strong Ave. Envelope compliance WNIcheck.cck Section 1: Project Information Project.Name: Stron- Ave Block Designer/Cont,-actor: Ford Gillen Architect. 409 Main St. ,,mherst,MA 01002 Document Author: _W1 _LAP^ Telephone: �3�� � Date -Q�r- Section 2: General Information Builduig Location: Northampton,Massacltusetts Climate Zone: 14a Heating De'gree Days(base 65 de-ces F): 6894 Conlin.,Dcgree Days(base 65 degrees F): 507 Buildim4 Use Method of Compliance: Whole Building Method Building-Type Floor.Area (JTficc 1 Prof:ct Description(check one): New Constn:etion _Addition _Alteration _Unconditioned Shell (File Affdavit) Section 3: Requirements Checklist :fir Leakage,Component Certification,and Vapor Retarder Requirements Inspection Approved Initial Date All joints and penetrations are caulked,gaskeied. weather-stripped, or othetivise sealed _ Windows, doors,and sk,,,liohts certified as meet�t-leakage requirements — Componcnt R-values&- U-factors labeled as certified Vapor retarder installed - FROM FORD GILLEN ARCHITECTS FAX NO. : 413 256 1553 Sep. 10 2002 10:46AM P2 e (� OAK ttMf P�Q �\ of Nortirttmpfail y - � f ���aacl,rtactta j^ (� DEPARTMENT OF 13VILDZNG INSPECTIONS INSPECTOR 212 Main Street 0 Municipal Building Y / Nnrthampmn,MA 01060 SECONDARY CONSTRUCTION CONTROL DOCUMENT (for Professional Engineers/Architects responsible for only portion of a controlled project) Project Title: ,o S-tfo►x-�. ANf-- Date: { 1 Ib Project Location: 10 Strong Ave, Map: 32A Parcel: 153 Zone: CB Scope of Project: \ 9— �}.l (shell only) housing 5 retail shops, -6--residences garages In accordance Mth the ixth edition Massachusetts State Building Code,780 CMR SECTION 116.0: 1, � Mass, Registration Number �l� Being a registered professional Engineer/Architect hereby CERTIFY that I have prepared or directly supervised the preparation of all design plans,computations and specifications concerning: 'Pine protection (J Architectural [)Structural [)Mechanical (J Electrical (J Other(specify) for tl►e above named project and that to the best of my knowledge,such plans,computations and specifications meet the applicable provisions of the Massachusetts State Building Code,all acceptable engineering practices and all applicable laws for the proposed project. Furthermore,I understand and AGREE that I shall perform the necessary professional services to determine that the above mentioned portions of the work proceed in accordance with the documents approved for the building permit. Upon completion of the work,I shall submit a final report as to the satisfactory completion of the above- mentioned*r don of the work, Signature and Seal of registered professional: a KOS C. OWSKI v wg a7$l0 Fax 413-587-1272 -phone 413-587-1240 6� 0.�tWdPT a �rf�? of wort l 1 a 111p tall m DCPARTMENT OF BUILDINC 1NSPECT1oNs ' /i INSPECTOR 212 Main Street 0 Municipal Building Norlh:unrton. MA 01060 SECONDARY CONSTRUCTION CONTROL DOCUMENT (for Professional Engineers/Architccts responsible for only portion of 3 controlled project) ProjectTitic: 10 Strong Ave. Datc: September 12 , 2002 Project Location: 10 Strong Ave, Map: 32A pasCel: 153 Zone. CB Scope of Project: Construction of 1 building housing 5 retail shops, 6 residences & 5 garages shell only) In accordance with the sixth edition Massachusetts State Building Code, 780 CMR SECTION 116.0: I, Robert W. Hall P.E. Mass. Registration Number 34985 Being a registered professional Engineer/Architect hereby CERTIFY that I havc prepared or directly supervised the preparation of all design plans,computations and specifications concerning: - ()Fire protection ( J Architectural (J Structural (J Mechanical K Electrical (] Other(specify) for the above named project and that to the best of my knowledge,such plans,computations and STecificauons meet the applicable provisions of the Massachusetts State Building Code, all acceptable engineering pracuces and all applicable laws for the proposed project. Furthermore,I understand and AGREE that I shall perform the necessary professional services to determine that the above mentioned portions of the work proceed in accordance with the documents approved for the building permit. Upon completion of the work, I shall submit a final report as to the satisfactory completion of the above- mentioned portion of the work- .% OF Signature and Seal of registered professional: 3��`ROBE T "f" Gti o TRICAL EsIs1E��� Ss�WIIA Fax 413-587-1272 phone 413-587-1240 RS I IA.N PT �0 e �it� Of Xort[lalliptall _J y+nh]tfltl�li8(ttt � l t I- Ktt 1- m DEPARTMENT OF BUILDING INSPeCT10vs INSPECTOR 212 Main Stmt ! Municipal Building Nortli.ampton. MA 01060 SECONDARY CONSTRUCTION CONTROL DOCUMENT (for Professional Engincers/Architccts responsible for only portion of a controlled project) ProjectTitk: 10 Strong Ave. lute: September 12 , 2002 ProjcctLocation: 10 Strong Ave. Map: 32A Parcel 153 Zone. CB Scope of Project: Construction of 1 building housing 5 retail shops, 6 residences & 5 garages shell only) In accordance with the sixth edition Massachusetis Statc Building Code,780 CvLR SECTION 116.0': 1, R-0 1-1 t W I Ha_11 P E. Mass. Registration Number 19 2 8 3 Being a registered professional Engineer/Architect hereby CERTIFY that 1 have prepared or directly supervised the preparation of all design plans,computadons and specifications concerning: - (J Fire protection ()Architectural (] Structural Mechanical [) Electrical [� Other(specify)_ Plumbing for the above named project and that to the best of my knowledge,such plans,computations and specifications meet the applicable provisions of the Massachusetts State Building Code,all acceptable engineering pracuces and all applicable laws for the proposal project. Furthermore,I understand and AGREE that 1 shall perform the necessary professional services to determine that the above mentioned portions of the work proceed in accordance with the documents approved for the building pennit. Upon completion of the work, I shalt submit a final report as to the satisfactory completion of the above- mentioned portion of the work_ Signature and Seal of egistered profes .18283 Fax 413-j87-1272 -pltone 413-587-1240 rROP1 FORD CILLCN RRCHITECTO FRX NO. t -410 200 1553 Cce. 10 2002 losaaRti r2 (rite of Wortljanip tali � �assatltur�tt0 m DEPARTMENT OF BUILDING INSPECTIONS INSPECTOR 212 M;dn Street • Municipal Building Norowunpton,MA 01060 SECONDARY CONSTRUCTION CONTROL DOCUMENT (for Professional EngincerslArchitects responsible for only portion of a controlled project) Project Title: 10 Strong Ave. Date: 9/13/02 Project Location:_,10 Strong Ave. Map: 32A parcel: 153 Zo,ye: CB ScQpe of 1 building housing 5 retail shops, 6 residences and 5 garages shell only In accordance with the sixth edition Massachusetts State.Hnilding Codn,78n('MR SFCTTnN 116.0- 1, Mass.Registration Numt)er e Y Being a registered professional Engineer/Arehiteet hereby CERTIFY that I have prepared or directly supervised the preparation of all design plans,computatinns and gwific-atinns cnncrming• []Fire protection [] Architectural XStructural (I Mechanical (J Electrical j Other(specify) y✓ �� for the above named project and that to the best of my knowledge,such plans,computations and specifications meet the applicable provisions of the Massachusetts State Building Code,all acceptable engineering practices and all applicable taws for the proposed project. Furthermore,I understand and AGRFR that 1 5h411 preform tale necessary professional se.rvicr,s to determine that the above mentioned portions of the work proceed in accordance with the documents approved for the building permit. Upon completion of the work,I shall submit a final report as to the satisfactory eompiction of the above- mentioned portion of the work. e' x, Signature and Seal of registered professional: e.r r-' Fax 413-587-1272 -phone 413-587-1240 OQ`'�tiAMpTp GTZt� of Xort4anipta t � 4 � � }�liassac}fnsctts �` c4 DEPARTMENT OF BUILDING INSPECTIONS INSPECTOR 212 Main Street * Municipal Building Northampton, MA 01060 CONSTRUCTION CONTROL DOCUMENT (for professional Engineers/Architects responsible for Entire Project) Project Title: 10 Strong Ave. Date: 9/19/02 Project Location: 10 Strong Ave. Map: 32A Parcel: 153 Zone: CB Scope of Project: Construction of 1 building housing 5 retail shops, 6 residences and 5 garages (sheil(she only) In accordance with the sixth edition Massachusetts State Building Code,780 CMR SECTION 116.0: I William V. Gillen Mass. Registration Number 2657 Being a registered professional Engineer/Architect hereby CERTIFY that I have prepared or directly supervised the preparation of all design plans,computations and specifications concerning: h, Entire Project for the above named project and that to the best of my knowledge, such plans, computations and specifications meet the applicable provisions of the Massachusetts State Building Code, all acceptable engineering practices and all applicable laws for the proposed project. Furthermore, I understand and AGREE that I shall perform the necessary professional services to determine that the above mentioned portions of the work proceed in accordance with the documents approved for the building permit and shall be responsible for the following as specified in section 116.2.2: 1. Review of shop drawings,samples and other submittals of the contractor as required by the construction documents as submitted for the building permit,and approval for the conformance to the design concept. 2. Review and approval of the quality control procedures for all code-required controlled materials. 3. Be present at intervals appropriate to the stage of construction to become generally familiar with the progress and quality of the work and to determine, in general, if the work is being performed in a manner consistent with the construction documents. I shall submit periodically, in a form acceptable to the building official,a progress report together with pertinent comments. Upon completion of the work, I shall submit to the building official a final report as to the satisfactory completion and readiness of the project for occupancy. Signature and Seal of registered professional: h, a No.2657 c� AMHER3T ~ o MASS. Jy q�'l OF MP`'P Fax 413-587-1272 -phone 413-587-1240 i t OQ�t�tPTO B� E� Grow of 'Xiartij allTptoll gB �asaxchnsctls' _ m DEPARTMENT OF BUIL)FNG INSPECTIONS 212 Main Street ' Municipal Building 'e Northampton, Mass. 01060 ,~ WORKER'S COMPENSATION INSURANCE AFMAVIT j Western Builders, Inc. (licenserJpermlttee) with a principal place of business/residence at: 73 Pleasant St. , Granby, MA 01033 (phone#) (413) 467-9171 (stirei/ci ty/staiela p) do hereby certify, under the pains and penalties of per}ury, that: (X� 1 am an employer providing the following worker's compensation coverage for my employees working on this job: Transportation Insurance Co. WC250077915 07/01/03 (Insurance Company) (Polio Number) (Ft-piration Date) O 1 am a sole proprietor, general contractor or homeowner (circle one) and have hired the contractors listed below who have the following worker's compensation policies: tration Date (Name of Contractor) (Insurance Company/Policy Number) (gyp ) ., (Name of Contractor) (Insurance Company/Policy Number) (Expiration Date) (Name of Contractor) (Insurance Company/Policy Numlxs) (Expiration Date) (Name of Contractor) (Insurance Company/Policy Number) (Expiration Date) (attach additioeul shcc ifnecc=cityto inch information peztaSR_;�C to all coatsadvrs) ( ) I am a sole proprietor and have no one working for me. ( ) I am a home owner performing all the work myself. NOTE:please be aware that while homernvncn who employ puzoos w cio may ...m,noe,coa4rudroo or repair work ou a dwelling of not more than throe unit+in which the homeowner rendes or oo the grounds appurtenaoi thac(v arc oat srncrally ooaridcrcd to be employcr3 under the workru's oompmsation Act(GL152,si 1(5)�application by a bomcowna for a ticcwe cc pamd may cvidcooc the legal stshu of an omployec under the Workeet Convaxution Act I unAcreAnd the a copy of this rut-11 may be forwcuded to tbo Dcpnrtmmt of Indau &!Arxidenf_{OfF oo of Iuainncn for the oovcrage verification mad that failure to so=re ooverago under sociion 25A of MOL 152 can lead to the inrQositioa of criminal penalties oomisting of a fine of up to S 1,500.00 and/or imprisoanx of up to one year and avtil pcaalties is the form of a Stop Work Ordc and a fr>m of 5100.00 a day against mc. For dcparta si uic only Permit Number OL, Maps Lot# rt, Si gua of Liccnsec[Permittee e Versionl.7 Commercial Building Permit May 15,2000 SECTION'10=STRUCTURAL".PEER REVIEW'(780 CMR.110 Tl) Independent Structural Engineering Structural Peer Review Required Yes......❑ No.....JO SECTION 11-`tOWNER;AUTHORIZATION -TO°BE,COMPLETED WHEN. OWNERS AGENTOR'CONTFtACTOR APPLIES°FOR BUfI'D'tNGPERMIT Michael G. Sissman as Owner of the subject property hereby authorize _David V. Clark, Western Builders, Inc. to act on my b aif, in all matters rel to wor uthorized by tl}is building permit application. 9/19/02 Si nature of Owner Date I, David V. Clark m /Authorized Agent hereby declare that the statements and information on the foregoing application are true and accurate, to the best of my knowledge and belief. Signed under the pains and penalties of perjury. David V. Clark Print Name 9/19/02 Signature of w6*/Agent Date SEq'T N 12-CONSTRUCTION SERVICES: 0.1 Licensed Construction (Supervisor: Not Applicable 4` Name of License Holder: D/�Lo f!0 �'L% �' IC d6 416 1,5c2 License Number Address Expiration Date r,—\ �L C Signature Telephone SECTIOU13,-WORKERS'COMPENSATION'INSURANCE AFFI DAVIT(M G.L. c.'152, §,25C(6)) Workers Compensation Insurance affidavit must be completed and"submitted with this application. Failure to provide this affidavit will result in the denial of the issuance of the building permit. Signed Affidavit Attached Yes....... 0 No...... ❑ Versionl.7 Cornmercial Building;Pcmtit May 15,2000 SECTION 9- PROFESSIONAL DESIGN AND CONSTRUCTION SERVICES . FOR BUILDINGS AND STRUCTURES SUBJECT TO CONST CTION CONTROL PURSUANT TO 780 CMR 116(C-MTAINING MORE THAN 35,000 C.F.OF ENCLOSED SPACE) 9.1 Registered Architect: _. Not Applicable ❑ William V. Gillen Name(Registrant): 2657 409_ Main St:. , Amherst, MA 01002 Registration Number Address _8431103 V;It 413-253-2528 Expiration Date Signature Telephone 92 Registered Professional Eiigineer(s): Robert W. Hall Electrical Name Area of Responsibility 540 Meadow Street Ext , Agawam, MA 01001 34985 _ Adaress �� Registration Number 1 lAQ, i f Ctt- 413-789-0960 06/30/03 Signature Telephone Expiration Date Robert W. Hall Plumbing Name Area of Responsibility 540 Meadow Street Ext , Agawam, MA 01001 19283 Address Registration Number 413-789-0960 06/30/03 - Signature Telephone Expiration Date Richard A. Foley Structural Name Area of Responsibility 9 Str et, S. 240, Watertown, MA 02472 20114 Address Registration Number 617-926-9150 6/30/04 Sign ure �� Telephone Expiration Date Name - Area of Responsibility Address Registration Number Signature Telephone — I Expiration pate 9.2 General Contractor Western Builders, Inc. Not Applicable M Company Name. David V. Clark Responsible In Charge of Construction 73 Pleasant St. Granby, MA 01033 Address U 413-467-9171 Signature Telephone Version 1.7 Commercial Building Permit May 15,2000 7. Water Supply(M.G.L. c. 40, § 54) 17.1 Flood Zone Information: 17.3 Sewage Disposal System: Public IM Private ❑ Zone: 0 Outside Flood Zone M Municipal 0 On site disposal system ❑ 8. NORTHAMPTON ZONING Existing Proposed Required by Zoning This column to be filled in by Building Department Lot Size 6,180 No change Frontage 201.71 201.71 Setbacks Front Side L: R: L: 0 R: 3 Rear Building Height N/A 37' X 26' Bldg.Square Footage N/A % 5,755 94% Open Space Footage % (Lot area minus bldg&paved N/A 353 6% parking) #of Parking Spaces N/A 5 Fill: volume&Location) None None A. Has a Special Permit/Variance/Finding ever been issued for/on the site? NO DON'T KNOW YES X IF YES, date issued: ZBA 5/23/02, Pianning Bd. SP 5/31/02, Decision dates for both: 5/23/02 IF YES: Was the permit recorded at the Registry of Deeds? NO DON'T KNOW YES X IF YES: enter Book 6682 ZBA Page 289 and/or Document # 6682 Plan Bd. 292 B. Does the site contain a brook, body of water or wetlands? NO x DON'T KNOW YES IF YES, has a permit been or need to be obtained from the Conservation Commission? Needs to be obtained Obtained Date Issued: C. Do any signs exist on the property? YES NO IF YES, describe size, type and location: D. Are there any proposed changes to or additions of signs intended for the property?YES No IF YES, describe size, type and location: Versionl.7 Commercial Building Permit May 15,2000 SECTION.;.4-CONSTRUCTION SERVICES FOR PROJECTS LESS THAN 35,000 CUBIC FEET-7:0F ENCLOSED-.,S PACE Interior Alterations Existing Wall Signs Existing Ground Signs Additions ❑ Roofing ❑ ❑ ❑ Exterior Alterations Demolition❑ New Signs [ ] Change of Use [ ] Other [ ] ❑ Accessory Building[ ] Repairs [ ] Non separated, usiness and residential, 3 stories containing 5 retail, (ZT(JT� 6 residential SECTION,5 USE GROU D CONSTRUCTION TYPE USE GROUP(Check as applicable) CONSTRUCTION TYPE A Assembly 10 A-1 ❑ A-2 ❑ A-3 ❑ 1A ❑ A-4 ❑ A-5 ❑ 1B ❑ B Business IN 2A ❑ E Educational ❑ 2B ❑ F Factory ❑ F-1 ❑ F-2 ❑ 2C ❑ H High Hazard ❑ 3A ❑ Institutional ❑ 1-1 ❑ 1-2 ❑ 1.3 ❑ 3B ❑ M Mercantile ❑ 4 ❑ R Residential 12X R-1 ❑ R-2 ❑ R-3 Kl 5A S Storage ❑ S-1 ❑ -2 IX 5B U Utility ❑ Specify: M Mixed Use EIK Specify: S Special Use ❑ Specify: COMPLETE THIS SECTION IF EXISTING;BUILDING UNDERGOING RENOVATIONS,.ADD1TlONS AND%QR CHANG,E IN IISE Existing Use Group: Proposed Use Group: Existing Hazard Index 780 CMR 34): Proposed Hazard Index 780 CMR 34): SECTION &BUILDING HEIGHT AND AREA �O 1G ONLY US BUILDING AREA EXISTING PRO POSED NEW CONSTRUCTION r 'a ,,`i's, 'm :SA;�$. «„«,:< Floor Area per Floor(sf) 15t 5,755 2nd 5,755 g 15t �� ki 5 ga E a x4 4,322 3rd �r'�a��as A � 2ndtxs� 4 th 3rd � "ent �Acm v 5 f NA 4th A z� Aii Total Area (sf) Total Proposed New Construction (sf) A 15s832 .................�_....-_-_____.._ — Total Height(ft) 37' Total Height ft -------------------- 'qu �M s NO Version 1.7 Commercial Building Permit May 15,2000 City of Northampton Building Department 212 Main Street Room 100 Northampton, MA 01060 phone 413-587-1240 Fax 413-587-1272 APPLICATION TO CONSTRUCT, REPAIR, RENOVATE, CHANGE THE USE OR OCCUPANgy C7 1,,OR vy)r iL SH ANY NG OTHER THAN A ONE OR TWO FAMILY DWELLINGit r Ur 7 s. SECTION1` SITE[NFORMATIQN' 1.1 Property Address: 10 Strong Avenue 5ECTION.2 P�tOPERTY OWNERSHIP/AUTHORIZED AGENT 2.1 Owner of Record: Michael G. Sissman 134 South Street, Northampton, MA Nam (Print) Current Mailing Address: 413-586-3658 Signature Telephone 2.2 Authorized Agent: David V. Clark—Western Builders, Inc. 73 Pleasant Street, Granby, MA 01033 Name(Print) Current Mailing Address: 413-467-9171 Signature Telephone S'ECTION.3-'ESTIMATED CONSTRUCTION:COSTS Item Estimated Cost (Dollars)to be Official Use Only completed by ermit applicant 1. Building (a) Building Permit'Fee 1,603,000 2. Electrical �b)Estimated Total Cost of ` 20,000 Construction from 6 3. Plumbing Building Permit Fee,' 36,000 4. Mechanical (HVAC) 5. Fire Protection 18,000 6. Total =(1 + 2 + 3 +4 + 5) 1,677,000 Check'Number O This Section For Off icial'Use.Only BuildingP Date Issued: Signature Building`Commissioner/Inspector of Buildings Date File#BP-2003-0310 APPLICANT/CONTACT PERSON WESTERN BUILDERS INC ADDRESS/PHONE P O BOX 278 (413)467-9171 PROPERTY LOCATION 10 STRONG AVE MAP 32A PARCEL 153 001 ZONE CB THIS SECTION FOR OFFICIAL USE ONLY: PERMIT APPLICATION CHECKLIST ENCLOSED REQUIRED DATE ZONING FORM FILLED OUT Fee Paid Buildin Pernut Filled out Fee Paid � Q,3' O Typeof Construction: CONSTRUCT 3 STORY BLDG(BUS RES RET TOWNHOUSES,GARAGES) New Construction Non Structural interior renovations Addition to Existing Accessory Structure Building Plans Included• Owner/Statement or License 000152 3 sets of Plans/Plot Plan THE FOLLOWING ACTION HAS BEEN TAKEN ON THIS APPLICATION BASED ON INF94CMATION PRESENTED: Approved Additional permits required(see below) PLANNING BOARD PERMIT REQUIRED UNDER:§ Intermediate Project: Site Plan AND/OR Special Permit With Site Plan Major Project: Site Plan AND/OR Special Permit With Site Plan ZONING BOARD PERMIT REQUIRED UNDER: § Finding Special Permit Variance* Received&Recorded at Registry of Deeds Proof Enclosed Other Permits Required: Curb Cut from DPW Water Availability Sewer Availability Septic Approval Board of Health Well Water Potability Board of Health Permit from Conservation Commission Permit from CB Architecture Committee Permit from Elm Street Co on d�L-- Signature of Building Official Date Note:Issuance of a Zoning permit does not relieve a applicant's burden to comply with all zoning requirements and obtain all required permits from Board of Health,Conservation Commission,Department of public works and other applicable permit granting authorities. *Variances are granted only to those applicants who meet the strict standards of MGL 40A.Contact Office of Planning&Development for more information. 10 3`I4:ONG AVE BP-2003-0310 GIs#: COMMONWEALTH OF MASSACHUSETTS -Hio&32A- 153` CITY OF NORTHAMPTON Lot: -001 Permit BuilCling Category: BUILDING PERMIT Permit# BP-2003-0310 Project# JS-2003-0525 Est. Cost: $1677000.00 Fee: $4406.30 PERMISSION IS HEREBY GRANTED TO: Const. Class: 5B Contractor: License: Use Group: R3,S2 WESTERN BUILDERS INC 000152 Lot Size(sg. ft.): 6054.84 Owner: SISSMAN MICHAEL Zoning: CB Applicant: WESTERN BUILDERS INC AT. 10 STRONG AVE Applicant Address: Phone: Insurance: P O BOX 278 (413) 467-9171 Workers Compensation GRANBYMA01033 ISSUED ON.1019102 0:00:00 TO PERFORM THE FOLLOWING WORK.-CONSTRUCT 3 STORY BLDG (BUS,RES, RET, TOWNHOUSES, GARAGES) - SECTION 116 POST THIS CARD SO IT IS VISIBLE FROM THE STREET Inspector of Plumbing Inspector of Wiring D.P.W. Building Inspector Underground: Service: Meter: Footings: Rough: Rough: House# Foundation: Driveway Final: Final: Final: Rough Frame: Gas: Fire Department Fireplace/Chimney: Rough: Oil: Insulation: Final: Smoke: Final: THIS PERMIT MAY BE REVOKED BY THE CITY OF NORTHAMPTON UPON VIOLATION OF ANY OF ITS RULES AND REGULATIONS. Certificate of Occupancy si nature: Fee T e: Receipt No: Date Paid: Check No: Amount: Building 10/9/02 0:00:00 26545 $4406.30 212 Main Street,Phone(413)587-1240,Fax: (413) 587-1272 Building Commissioner-Anthony Patillo