32A-255 (64) `
_
^
accessible but are not directly interaccessible. To get from the
lower two levels to the upper level , one would travel outside
approximately forty (40 ' ) feet from the new south entrance to the
Wiggins Tavern entrance and then take a new enclosed lift to the
upper level .
Also important would be the loss of eight (8) seats due to the
installation of the lift plus a loss of four (4) seats due to the
new south door brings the total seating from fifty-six (56) to
forty-four (44) and imposes an economic hardship on The Hotel .
Lift� $6, 500. 00 .
$l ,000. 00
$1 ,000. 00
5,000. 00
~
'
'
. ~
�
In the case of the two new bathrooms, we were confronted with an
existing concrete foundation stair and floor which was previously
open to the exterior. (see before plans) We were unable to
design a ramp or lift in the space aNangement shown in
coniunction with two (2) accessible bathrooms without blocking
legal use of the existing stairs and landing.
We decided to ask The Board for a variance for the additional
bathroom which we would be unable to build under section 30. 1 .
We were able to design one handicapped bathroom accessible from
the Justin Morgan function room by raising the floor of the new
bathroom eight (8" ) inches, putting in a new doorway through a
brick wall and installing a lift in the function room space.
We felt the additional ~ fixtures would free use of all other
toilets and generally improve the situation for all users.
ance
It is unfeasible to install two accessible bathrooms in the space
given the existing conditions. Therefore, the cost of compliance
in this case is irrelevant as there are no other practical
locations to be considered. The true costs of compliance are
loss of an amenity and an additional load on the existing
fixtures. We and The Hotel feel the location of the present
design is the only one feasible while best suited to the use of
the spaces.
it-
In the case of the Coolidge Park Cafe accessibility , we were
confronted with two interior levels and a third exterior patio
level to connect. We designed an enclosure for the exterior
patio level , and a ramp to connect it to the lower of the
interior levels. We also designed a new exterior Cafe Park
terrace with an accessible entrance into the existing interior
lower level . We are requesting a variance to allow The Hotel not
to connect by ramp or lift the middle with the upper level of the
Coolidge Cafe. A ramp connecting the two levels would have to be
30 ' long and would result in loss of use of the middle level . A
lift by necessity would have to be placed in the middle of the
restaurant space, operation of which we feel , unfortunately,
places the focus of attention by all in the space upon any user
of the lift. We feel , and it may be a point of contention , that
a handicapped person may feel more inclined to use less efficient
means of access if given the choice of a more private , less
obtrusive way. In our case, all levels of the Cafe are
8. For each variance requested, state in detail the reasons why compliance with
the Board's regulations would not be practical. State the necessary cost of
the work required to achieve compliance. (You should submit cost estimates
detailing the amount of compliance) USE ADDITIONAL SHEETS IF NECESSARY.
Please see attached sheet.
9. Has a building permit been applied for? Yes, several permits
If yes, state the date the permit was issued: 3/7/87 , 4/23/87 , 6/3/87 ,
7/28/87
10. State the estimated cost of construction as stated on the building permit.
(1) enclosing patio 57, 000 (2) center porch 54 ,000 . (3) ballroom
enclosure 75 , 000 . (4) patio park 11, 500 .
If a building permit has not been issued, state the anticipated construction
cost:
11 . Has a certificate of occupancy been issued for the facility?
If yes, state the date: Never revo iced
12. State the actual assessed valuation of the BUILDING ONLY AS RECORDED IN THE
ASSESSOR'S OFFICE of the municipality in which the building is located:
$2 , 717 , 900 .-00
13. State the phase of design or construction of the facility as of the date of
this application: 80% designed - 30% constructed
14. State the name and address of the architectural or engineering firm
including the name of the individual architect or engineer responsible for
preparing drawings of the facility: Metcalfe * Thorne , 150 Main St. ,
Northampton, MA 01060 - —
Tristram W. Metcalfe III TEL: 5Rh_-,77r, (413)
15. State the name and address of the building inspector responsible for
overseeing this project: William Nimohay, Buildihq Inspector
City of Northampton. 210 Main StrPP±� Northampton, MA 01060
PLEASE NOTE: The Board may, in its discretion, hold a hearing on your
application for variance. The BuaLd may also decide your application without a
hearing, upon the information you submit. You should therefore, include all
relevant information with your application. At minimum, the plans should
include a site plan, all floor plans, elevations, sections and details.
Photographs are Extremely helpful.
Date: 11117 SIGN)TURE OF OWNER OR AUTHORIZED AGENT
f
--- TEVr-N
PLEASE PRINT OWNER/AGENT'S NAME
d7
Awcaec-ve 61�ce 0,19Wo .alcy
cxJ�?��Gy2L�C�CGxaL cX�cCPiJS �%�G�C7�
Michael S. Dukakis �,7�
Governor .��liurCan lace - ✓Corn,,. /3/0
Charles V. Barry 0artan, ✓&jjadzzaeiZ OV OS .
Secretary (1697) 727-M610
Voice & TDD
APPLICATION FOR VARIANCE
In accordance with M.G.L. , Chapter 22, Section 13A, I hereby apply for
modification of . or substitution for the rules and regulations of the
Architectural Access Board as they apply to the facility described below on the
grounds that literal compliance with the Board requlations is impracticable in
my case.
1. State the names and address of the owner of the building/facility: Hotel
Northampton Operative Cooperation, 36 Kinq Streeter Northamptnn,
Massachusetts 01060
2. State the name and address or other identification of the building/facility:
Hotel Northampton, 36 King Street, Northampton, MA 01060
3. Describe the facility: (number of floors, type of functions, etc.):
Hotel : Five stories and basement; assembly, residential,
restaurants
4. Check the work performed or to be performed:
X New construction X Reconstruction, Alteration,
__..._. Remodeling
X Addition Change of Use
5. Briefly describe the extent and nature of the work performed or to be
performed: Enclosed porches on existing foundations, updated
handicap access new bathrooms, new 12ark
6. State each section of the Rules and Regulations of the Architectural Access
Board for which a variance is being requested.
SECTION NUMBER DESCRIPTION
3 . 3B Com]21Pte a cessihilitV
30:1 Public toilet accessibility
17 . 2 Ramps connPnti ng 1 eyrel s -in
YPSta17YaT'1t
Michael S.'Dukakis
Governor •r one �Wt& �o9a dace - Rawn
Charles V. „m "" �o !►r.,✓l ta,,e Z 02 08
Secrete �-� .
(6'97J 7.27 0660
41988
TO: LOCAL BUILDING INSPECTOR
MASSACHUSETTS INDEPENDENT LIVING PROGRAM
LOCAL HANDICAPPED COMMISSION
FROM: DEBORAH RYAN , ARCHITECTURAL ACCESS BOARD
SUBJECTi Hotel Northampton, 36 King Street , Northampton, MA 01060
DATE: December 30,1987
Enclosed please find the following materf_.ml regarding the
above premises :
: Application for Variance Decision of Board
Notice of Hearing Correspondence
_Letter of Meeting
The purpose of this memo is to inquire as to whether or not
your office has any input on the application filed with
respect to the above project. Also, to make you aware that
a hearing has been or will be held on the matter.
If you have any information that you feel would assist the
Board in making a decision on this case, could you please
advise this office as soon as possible. You may call the
office at (617) 727-0660 or submit a letter of
recommendations and/or comments .