Operations: Bates completed work establishing north limits of landfill, including temp haul road and swale/berm. Commenced work on south and east limits of landfill, completing that
work as well including temp haul road and swale/berm. Bates dug six test pits to verify trash removal, for a total of eight altogether as required by specifications. Encountered significant
amounts of metal trash in the middle run along the south side; heaviest concentration of trash encountered to date. Bates brought in a large roller to start compacting and shaping the
final landfill contours.
Materials Purchased/Delivered/Installed: Multiple loads of sand to be used as common fill. Geomembrane material was delivered (7 rolls total), along with test certs.
Subcontractor Work: None
Equipment on site: See report for last week. Equipment to be on site for most of the project. Large vibratory roller also added.
Safety Violations: None
MA DEP/City of Northampton Personnel Site Visits: None
Comments: I have been inspecting the loads of trash removed from outside the limits on an ongoing basis and have seen no evidence of ACM. Most material is brick, concrete, etc with
a fair amount of metal as well. No signs of buried drums either.
Submitted By: Mark Campbell, PE
Photos: None Plans: None On-Schedule: Yes