Loading...
11-002 Weekly Activity Report Summary 3 WEEKLY ACTIVITY REPORT SUMMARY VAMC Northampton, MA Contract # VA241-C-0125 Week of: June 14-18, 2010 Site Superintendent: Pat Mahan QA/QC Manager: Mark Campbell, PE AES Project Manager: Philip Smith, P.G. Operations: Bates working on establishing north limits of landfill, pulling back trash extending beyond those limits. Most areas require 1-2’ of excavation below proposed grades, but one area was as deep as 4-6’. Bates dug two test pits to verify trash removal. Backfilling with sand, which is more available in this area than common fill. Also working on the perimeter berm and temporary haul road. Working on installing baffles in basins as well as the skimmer unit. Clear and grub at the Smith School laydown area. Materials Purchased/Delivered/Installed: Multiple loads of sand to be used as common fill. Mulitple loads of loam in prep for constructing the temporary haul road. Subcontractor Work: Removal of stumps. Note: all stumps have been removed. Equipment on site: See report for last week. Equipment to be on site for most of the project. Bates added an operator for the dozer as well as a laborer Safety Violations: None MA DEP/City of Northampton Personnel Site Visits: Larry Hanson, DEP. Larry will be providing coverage until Charlie Cline returns. Comments: Visit from Larry Hanson was positive. He was happy with the work being performed and has worked with Bates in the past so is comfortable. Discussed with Larry the potential that the final grades at the highest point of the landfill will be lower than indicated on the plans. Larry confirmed that as long as required slopes are met that is not an issue. Submitted By: Mark Campbell, PE Photos: None Plans: None On-Schedule: Yes