Loading...
11_002 Weekly Activity Report Summary 2 WEEKLY ACTIVITY REPORT SUMMARY VAMC Northampton, MA Contract # VA241-C-0125 Week of: June 7-11, 2010 Site Superintendent: Pat Mahan QA/QC Manager: Mark Campbell, PE AES Project Manager: Philip Smith, P.G. Operations: Work at basins #1 and #2 completed. Note that the berms held up real well given the amount of rainstorms. No significant signs of erosion. Bates has diligently followed the lift and compaction requirements for the clay barrier. Bates dug dest pits at basin #2 to verify all trash was removed from beneath it. Bates commenced work on establishing the edge of the landfill on the north side, removing trash from outside the limits and pulling it back inside the landfill area. Stumps continue to be hauled away. Note: the contract drawings showed a concrete seepage block around the outlet pipe from the pond. However, that detail was suited for use of concrete pipe. Bates is using CPP, and so I advised Bates they could just stick with the clay, as its swelling characteristics will be more effective given the use of the CPP. I also gave Bates the option to hold off on building the rip-rap swale at the access road and just bury pipe for now. Swale would then be constructed as one of the last items of work. I inspected the drainage structures upon arrival on site and found them to be without cracks or damage. Materials Purchased/Delivered/Installed: Slope stabilization material. Multiple loads of sand to be used as common fill. Drainage structures. Seed for basins. Subcontractor Work: Removal of stumps Equipment on site: See report for last week. Equipment to be on site for most of the project. Safety Violations: None MA DEP/City of Northampton Personnel Site Visits: None Comments: Submitted By: Mark Campbell, PE Photos: None Plans: None On-Schedule: Yes