11_002 Weekly Activity Report Summary WEEKLY ACTIVITY REPORT SUMMARY VAMC Northampton, MA Contract # VA241-C-0125 Week of: May 25-28 Site Superintendent: Pay Mahan QA/QC Manager: Paul Compagna, PE AES Project Manager: Philip Smith, P.G. Operations: Excavating basins 1 and 2 to subgrade. Fill removed from basin areas moved to upper landfill area. Continue clear and grub. Removal of all stumps completed. Performed silt fence maintenance. Layout edge of basisn and grades. Materials Purchased/Delivered/Installed:Additional hay bales and silt fence. 8 loads of clay @ 17 yds per load. Subcontractor Work: Equipment on site: See report for last week. Equipment to be on site for most of the project. Safety Violations: None MA DEP/City of Northampton Personnel Site Visits: Charlie Cline DEP Comments: Submitted By: Mark Campbell, PE on behalf of Paul Compagna, PE Photos: None Plans: NOne On-Schedule: Yes